Projects / Romania · Licensing
NuScale VOYGR Doicești (Romania)
Six-module Doicești proposal by RoPower Nuclear, which CNCAN's August 2025 national report calls the project owner.
Current status
- How current
- General record check . Bounded evidence review . 8 of 18 listed sources have a publication or document date recorded here; the newest is 29 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Under review: Doicești NuScale siting license application. An application under review is not a permit. All permissions and applications
- Latest development
- 29 Oct 2026 · Recorded development: Nuclearelectrica shareholders adopt RoPower measures. Shareholders took note of the Doicești conditions and strategy update without a vote, and adopted the measures in the meeting's note with about 90 percent of the votes present or represented. Source: Nuclearelectrica: convening page for the 29 October 2026 general meetings of shareholders (published 21 Sep 2026); Nuclearelectrica: shareholder note on the Doicești investment-decision conditions and RoPower Nuclear measures (October 2026, English); Nuclearelectrica: current report on the resolutions of the 29 October 2026 general meetings of shareholders (dated 29 Oct 2026). Updates entry
More on this development
The resolution does not repeat the measures, and whether RoPower has carried them out is not recorded.
- Next dated milestone
- Planned step: 31 Dec 2026 (target). Target: interim report on RoPower Nuclear's measures. This is not an achieved milestone. Source: Nuclearelectrica: shareholder note on the Doicești investment-decision conditions and RoPower Nuclear measures (October 2026, English); Nuclearelectrica: current report on the resolutions of the 29 October 2026 general meetings of shareholders (dated 29 Oct 2026).
- Selected limitations
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 4 tracked: 1 licensing, 1 announced. Separately: 1 canceled, 1 earlier-plan record. 19 tracked at licensing across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Integral pressurized water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
That report says an application for design and siting licenses had been submitted with part of the supporting documents and that regulatory review was ongoing; it does not state a submission date or say either license was granted. A June 2026 account of CNCAN's reply says RoPower filed the request and that no opinion, approval or permit had been issued. Shareholders approved a conditional investment decision on 12 February 2026 and in July rejected starting steps to reassess the 2022 strategy. Nuclearelectrica's note for an extraordinary shareholders' meeting convened for 29 October 2026 says over 80 percent of the February conditions remain unfulfilled, including a framework agreement and a binding module-procurement commitment from NuScale. Natural gas at the adjacent Soceram site has delayed site-characterization studies needed for the site license; a final independent study is due in October 2027. The note gives notice of a strategy update that keeps NuScale as the working scenario and asks shareholders to approve cutting RoPower's project staff by at least 60 percent for about six months. At the meeting on 29 October 2026 shareholders took note of the conditions and the strategy update without a vote, adopted the measures in that note with about 90 percent of the votes of shareholders present or represented, and authorized Nuclearelectrica's representative to vote for them at RoPower's own meeting. The resolution refers to the note and does not repeat the measures, and whether RoPower has carried them out is not recorded. In the same report the Ministry of Energy, for the Romanian state as majority shareholder, said the strategy update should include a comparative assessment of available technologies and development scenarios, and that the company will take steps to clarify, as soon as possible, the technology partner's willingness to enter binding commercial commitments. Financing so far comes from the shareholders: Nuclearelectrica says RoPower's debt is owed entirely to it under a loan facility raised to USD 243 million, and the US EXIM board approved a USD 98 million loan for pre-project services in 2024. In May 2026 RoPower reported that EXIM was analyzing instruments of about USD 5.6 billion and that DFC had issued a letter of intent for up to USD 2 billion; both are indicative and non-binding. The licensing stage records the application, not a license or construction start.
Key facts
- Design
- NuScale VOYGR (US460 / NPM) (SMR)
- Technology
- Integral pressurized water reactor (iPWR) · light water
- Operator(s)
- Not recorded
- Vendor for linked design
- NuScale Power
- Design origin
- United States: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
- Location
- Doicești NuScale site · Romania · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the Doicești NuScale unit 1 entry at the former coal plant area (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); site-area point. Replaces an earlier hand-placed point about 4 km away. - Coordinates
- 44.9967, 25.3672 · site-area point (approximate)
- Electrical capacity
- 462 MWe (gross) · scope: plant
- Thermal capacity
- Not recorded
- Inclusion basis
- SMR by design class
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 11 Nov 2026. How current names both.
Site and capacity notes
NuScale VOYGR Doicești (Romania) is recorded at Doicești NuScale site, Dâmbovița, Romania. Operator: No operator is recorded. Recorded vendor: NuScale Power. Stage: Licensing. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'doicesti-nuclear-power-plant-1' (44.9967, 25.3672)
Recorded electrical output is 462 MWe (gross), scope plant. Modules planned: 6. Thermal output is not recorded on this project. The linked design record states 250 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project. The linked design record states 77 MWe (gross); the project figure is kept separate.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerRoPower Nuclear S.A. · source
- Application filing entityRoPower Nuclear S.A. · source
- Reactor supplier
- Vendor for the linked designNuScale Power
- Contractor
Source-backed project statement World Nuclear News reported on 2 October 2024 that Nuclearelectrica and RoPower Nuclear signed the FEED Phase 2 contract with Fluor in July 2024 for design and engineering services at Doicești. Nuclearelectrica's 12 February 2026 release still lists Pre-EPC contract negotiations and identification of contractors as work ahead of execution. The Fluor contract is front-end engineering, not a construction or EPC award. World Nuclear News: US Exim Bank approves loan for Romanian SMR project; Nuclearelectrica: Doicești SMR project obtains the final investment decision
- Funding and government decisions
- Funder or lender named for this projectExport-Import Bank of the United States · sourceBoard approved a final commitment for a USD98 million loan for pre-project services (reported 2 October 2024); disbursement not recorded.
- Funder or lender named for this projectSN Nuclearelectrica SA · sourceEUR4 million share capital in RoPower Nuclear and a shareholder loan facility with a USD243 million ceiling, drawn only if other financing is not secured; amount drawn not stated.
- Funder or lender named for this projectNova Power & Gas · sourceShare capital in RoPower Nuclear matching Nuclearelectrica's EUR4 million contribution, per Nuclearelectrica (21 May 2026).
Source-backed project statement
Nuclearelectrica said on 21 May 2026 that it contributed 4 million euros to RoPower's share capital, matching Nova Power & Gas, and that shareholders raised its loan ceiling to RoPower to 243 million dollars, drawable only if other financing is not secured. World Nuclear News reported on 2 October 2024 that the US Export-Import Bank board approved a final commitment for a 98 million dollar loan for pre-project services. Amounts drawn are not stated, so these are an equity contribution, an approved ceiling and a loan commitment, not recorded disbursements. Nuclearelectrica: Clarifications regarding the development of the Doicești SMR project; World Nuclear News: US Exim Bank approves loan for Romanian SMR project
- Site host or owner
- Current site ownerRoPower Nuclear S.A. · source
- Comparable schedule revision
Source-backed project statement Nuclearelectrica's September 2022 strategy note placed the Doicești commercial-operation stage in 2029–2030, starting with energy sales from module 1. Its later final-investment-decision submission note gives July 2033 for the first NuScale Power Module and December 2034 for the whole plant, dependent on the remaining modules' commercial agreements. The later note has no filled-in issue date: January 2026 is suggested by its file location and metadata, not stated on the document. It describes alternative conditional procurement arrangements, not a simple reduction to one module. These documents support a partial first-module schedule history, not a precise delay calculation or confirmation that either forecast remains current. The English translations defer to the Romanian originals. Nuclearelectrica: Statement regarding the summary of the report of the Control Body of the Prime Minister of Romania; Nuclearelectrica: Doicești SMR project obtains the final investment decision; World Nuclear News: US Exim Bank approves loan for Romanian SMR project; Nuclearelectrica: SMR strategy note; Nuclearelectrica: SMR final-investment-decision submission note
Not found in the sources we checked (2): Customer or offtaker; Fuel
- Customer or offtaker
Nuclearelectrica's 12 February 2026 investment-decision release and 21 May 2026 clarifications describe Doicești financing, licensing steps and a price per megawatt-hour, and its 28 July 2026 statement addresses the schedule and the site. None names a buyer, offtake agreement or contract for difference for the plant's electricity. The February release describes 462 MW replacing the former thermal plant, which is a purpose, not a named customer. Nuclearelectrica: Doicești SMR project obtains the final investment decision; Nuclearelectrica: Clarifications regarding the development of the Doicești SMR project
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
Nuclearelectrica's 12 February 2026 and 21 May 2026 releases and World Nuclear News's 2 October 2024 financing report describe Doicești engineering, financing and investment-decision conditions. None names a fuel supplier, fabrication contract or delivery for the six-module plant. Nuclearelectrica: Clarifications regarding the development of the Doicești SMR project; Nuclearelectrica: Doicești SMR project obtains the final investment decision; World Nuclear News: US Exim Bank approves loan for Romanian SMR project
Not recorded in SMRMap's reviewed evidence (2): Operator or intended licensed owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Reviewed 20 Oct 2026: not disclosed in the reviewed evidence.
- Programs and agreements naming the project
Timeline
Recorded developments
- · Recorded development
Nuclearelectrica shareholders adopt RoPower measures - · Recorded development
Nuclearelectrica publishes the government Control Body's report on the Doicești SMR - · Recorded development
Nuclearelectrica answers a government Control Body report on the Doicești SMR - · Recorded development
Doicești FID conditions remain unresolved - · Recorded development
Doicești: shareholders reject a strategy reassessment and note unmet investment-decision conditions
Earlier developments (5)
- Announced · Recorded development
RoPower reports non-binding US EXIM and DFC financing interest for Doicești - · Final investment decision
Doicești conditional shareholder investment decision - Reported · Recorded development
NuScale says FEED Phase 2 work for RoPower finished in late 2025 - Signed · Contract
RoPower signs FEED Phase 2 engineering contract with Fluor for Doicești - Reported October 2024 · Recorded development
US EXIM approves a USD 98 million loan for Doicești pre-project services
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Target: interim report on RoPower Nuclear's measures
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Site applications and decisions
- Doicești NuScale siting license application
Site permission sought · Under review · CNCAN
CNCAN's August 2025 national report says an application for the NuScale VOYGR-6 design and Doicești siting licenses was submitted with only part of the supporting documents, and regulatory review was ongoing. The report does not date the filing or grant a license. A June 2026 report quoting CNCAN says no approval or permit had been issued. Nuclearelectrica's note for its 29 October 2026 shareholder meeting says the start of site-characterization studies required to obtain the site license has been delayed; that is the company's statement and reports no CNCAN decision. This action tracks the site application, not design certification or construction authority.
Sources: CNCAN: Romania tenth national nuclear-safety report, August 2025; DC Business: CNCAN reply on the Doicești SMR file (1 June 2026); Nuclearelectrica: shareholder note on the Doicești investment-decision conditions and RoPower Nuclear measures (October 2026, English)
Assessments of the design (not of this site)
(1)
- NRC standard design approval for the NuScale US460 — applies to the design, not to a site
Design assessment · Issued / approved · NRC · decided 29 May 2025 · ADAMS ML25129A004, ML25086A073 · 90 FR 23716
The NRC issued a standard design approval to NuScale Power for the US460 small modular reactor design on 29 May 2025, completing its staff technical review. NuScale submitted the application in stages: the first part by letter dated 23 November 2022 and the remaining portions in stages between 29 November and 31 December 2022. The NRC notified NuScale by letter dated 31 July 2023 that the application was acceptable for docketing. The approval lets an applicant reference the design in a construction permit, operating license, combined license or manufacturing license application. It is a design approval only: it grants no permission for any site, construction or operation.
Sources: Federal Register 90 FR 23716 (4 Jun 2025): NuScale US460 standard design approval; Federal Register FR Doc. 2023-05457 (17 Mar 2023): NuScale US460 standard design approval application received; Federal Register FR Doc. 2023-16679 (4 Aug 2023): NuScale US460 standard design approval application accepted for docketing
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. RoPower is a jointly owned project company for a NuScale SMR plant at the former coal site in Doicești. The CNCAN response reported by DCBusiness says RoPower filed for project and site authorization and that the file remained under evaluation, with no approval or construction authorization reported. A press account describes six 77 MWe modules, or 462 MWe total; that is a reported configuration, not a newly selected operating output. Shareholders approved a conditional final investment decision on 12 February 2026; the October shareholder note says over 80 percent of its conditions remained unmet. Nuclearelectrica's report of 29 October 2026, read on 3 November 2026, says the meeting took place that day and that shareholders adopted the proposed RoPower measures. The sources do not name an intended reactor operator or document nuclear construction. Last checked 11 Nov 2026. CNCAN: Romania tenth national nuclear-safety report, August 2025; DC Business: CNCAN reply on the Doicești SMR file (1 June 2026); World Nuclear News: US Exim Bank approves loan for Romanian SMR project; Nuclearelectrica: Doicești SMR project obtains the final investment decision; Nuclearelectrica: shareholder note on the Doicești investment-decision conditions and RoPower Nuclear measures (October 2026, English)
What would change this
A CNCAN notice changing the authorization status, the interim report on RoPower's measures due by 31 December 2026, or the updated SMR strategy. Next scheduled check: 31 Dec 2026.
- Operator or intended licensed owner: Not disclosed in the reviewed evidence. The attached project and regulatory sources identify the project company and shareholders but do not name a current or intended reactor operator. A project owner, filer or technology supplier is not treated as operator. Last checked 20 Oct 2026. CNCAN: Romania tenth national nuclear-safety report, August 2025
What would change this
A CNCAN filing, operating-authority document or project statement naming the reactor operator. Next scheduled check: 20 Jan 2027.
- Next decision and prerequisites. Nuclearelectrica's 21 September 2026 investor page convenes an extraordinary meeting for 29 October 2026, and again on 30 October, to note the February 2026 investment-decision conditions and to vote on measures for RoPower Nuclear. The English note for that meeting says more than 80 percent of those conditions remain unmet, including the NuScale framework agreement, a binding module commitment and Soceram gas measures, and that a final site study is due in October 2027. Nuclearelectrica's report of 29 October 2026 says the meeting took place that day and that shareholders adopted the proposed RoPower measures. The shareholder note calls for an interim report on those steps by 31 December 2026 and gives the strategy update six months; whether RoPower has carried the measures out is not recorded. Last checked 3 Nov 2026. Nuclearelectrica: convening page for the 29 October 2026 general meetings of shareholders; Nuclearelectrica: shareholder note on the Doicești investment-decision conditions and RoPower Nuclear measures (October 2026, English); Nuclearelectrica: current report on the resolutions of the 29 October 2026 general meetings of shareholders
What would change this
The interim report on RoPower's measures due by 31 December 2026, the updated strategy, or the October 2027 site study. Next scheduled check: 5 Jan 2027.
- Permissions and public process. CNCAN's August 2025 national report says an application for a design license and a siting license for Romania's first SMR, the NuScale VOYGR-6, was submitted with only part of the support documents and that review was ongoing. DC Business reported on 1 June 2026 that CNCAN told it no opinion, approval or authorization had been issued for Doicești, including none for construction. An application under review is not a permit. Last checked 23 Oct 2026. CNCAN: Romania tenth national nuclear-safety report, August 2025; DC Business: CNCAN reply on the Doicești SMR file (1 June 2026)
What would change this
A CNCAN decision granting or refusing the Doicești design license or siting license. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). Nuclearelectrica's 28 July 2026 statement says the project company acquired the Doicești land at market value, while no rebilling payment had been made and SNN had not approved financing that acquisition. Its shareholder note for the 29 October 2026 meeting says natural-gas measures at the adjacent Soceram site are unmet and delayed site-characterization studies for the site license, with a final study due in October 2027. Grid connection and water arrangements are not stated; the gas work is a hazard study, not a secured arrangement. Last checked 11 Nov 2026. Nuclearelectrica: Statement regarding the summary of the report of the Control Body of the Prime Minister of Romania; Nuclearelectrica: shareholder note on the Doicești investment-decision conditions and RoPower Nuclear measures (October 2026, English)
What would change this
A completed land-payment record, a grid or water agreement, or the October 2027 site study. Next scheduled check: 9 Feb 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. CNCAN's August 2025 national report, Nuclearelectrica's 2026 Doicești releases and the shareholder note for the 29 October 2026 meeting describe licensing, financing and site hazards. They do not state a spent-fuel, radioactive-waste or closure arrangement for the Doicești plant. Last checked 11 Nov 2026. CNCAN: Romania tenth national nuclear-safety report, August 2025; Nuclearelectrica: Doicești SMR project obtains the final investment decision; Nuclearelectrica: shareholder note on the Doicești investment-decision conditions and RoPower Nuclear measures (October 2026, English)
What would change this
A RoPower or CNCAN document stating spent-fuel, waste or closure arrangements for Doicești. Next scheduled check: 9 Feb 2027.
Evidence dates
(8 of 18 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(18)
- EnergyNote 2026 SMR licensing map (news report, accessed 1 Oct 2026)
- Nuclear News Network — SMRs explained (news report, accessed 1 Oct 2026)
- Doicești development conditions — July 2026 (company, accessed 1 Oct 2026)
- Nuclearelectrica: Doicești SMR project obtains the final investment decision (company, accessed 2 Oct 2026)
- Nuclearelectrica: current report on the resolutions of the general meeting of shareholders of 15 July 2026 (company, accessed 6 Oct 2026)
- DC Business: CNCAN reply on the Doicești SMR file (1 June 2026) (news report, accessed 6 Oct 2026)
- ENSREG SMR Task Force dashboard, third edition (3 March 2026) (government, accessed 6 Oct 2026)
- CNCAN: Romania tenth national nuclear-safety report, August 2025 (regulator, accessed 8 Oct 2026)
- Nuclearelectrica: shareholder note on the Doicești investment-decision conditions and RoPower Nuclear measures (October 2026, English) (company, accessed 16 Oct 2026)
- Nuclearelectrica: convening page for the 29 October 2026 general meetings of shareholders (company, published 21 Sep 2026, accessed 16 Oct 2026)
- Nuclearelectrica: Clarifications regarding the development of the Doicești SMR project (company, published 21 May 2026, accessed 18 Oct 2026)
- World Nuclear News: US Exim Bank approves loan for Romanian SMR project (news report, published 2 Oct 2024, accessed 18 Oct 2026)
- energynomics.ro: Financing potential of over 6.5 bln. for the Doicești project from US financial institutions (news report, published 5 May 2026, accessed 18 Oct 2026)
- Nuclearelectrica: Statement regarding the summary of the report of the Control Body of the Prime Minister of Romania (company, published 28 Jul 2026, accessed 18 Oct 2026)
- Nuclearelectrica: SMR strategy note (company, dated 9 Sep 2022, accessed 24 Oct 2026)
- Nuclearelectrica: SMR final-investment-decision submission note (company, accessed 24 Oct 2026)
- Nuclearelectrica: current report on the resolutions of the 29 October 2026 general meetings of shareholders (company, dated 29 Oct 2026, accessed 3 Nov 2026)
- Nuclearelectrica current report: publication of the Prime Minister's Control Body report (audit of 15 October 2025 to 20 March 2026) (government, published 11 Sep 2026, accessed 11 Nov 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: NuScale VOYGR Doicești (Romania) — https://smrmap.com/projects/nuscale-doicesti/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “NuScale VOYGR Doicești (Romania)”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/nuscale-doicesti/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.