Projects / United States · Siting

Oklo Aurora at Eielson AFB (DAF microreactor pilot)

Department of the Air Force microreactor pilot at Eielson AFB, Alaska.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . None of the 3 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • The mapped point is not an exact surveyed coordinate.
Same design
4 tracked: 1 construction, 2 siting, 1 announced. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Sodium-cooled fast reactor. How it works, with a 3D view.

Description

DLA Energy Notice of Intent to Award to Oklo (2025) for an Aurora powerhouse under a long-term PPA, contingent on NRC licensing. Distinct from Oklo Aurora-INL. The opened Air Force page and the 2025 Oklo award notice do not state an electrical or thermal rating. Oklo's Alaska page, checked on 7 October 2026, says expected output is approximately 60 MWth of reactor heat, used to provide at least 5 MWe of electricity and 50 to 100 thousand pounds per hour of steam. Those qualified figures are not stored as ratings, and 5 MWe is not stored as an exact output. A discovery-tracker label of about 5 MW is not stored. The Aurora class ceiling of up to 75 MWe is not copied onto this project. The same page says site characterization is underway and that borehole drilling is to begin in late 2026.

Key facts

Design
Aurora (Microreactor)
Technology
Sodium-cooled fast reactor (SFR) · sodium
Operator(s)
Oklo Inc.
Vendor for linked design
Oklo Inc.
Location
Eielson Air Force Base · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the Eielson Air Force Base entry (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); base-area point, the microreactor pad is not finally sited.
Coordinates
64.6699364, -147.0615698 · site-area point (approximate)
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
1
Inclusion basis
Labeled microreactor
Confidence
medium
Record reviewed
7 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Oklo Aurora at Eielson AFB (DAF microreactor pilot) is recorded at Eielson Air Force Base, Alaska, United States. Operator: Oklo Inc.. Recorded vendor: Oklo Inc.. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'eielson-air-force-base-nuclear-power-plant' (64.6699364, -147.0615698)

Electrical output is not recorded on this project. Modules planned: 1. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Reactor supplier
Customer or offtaker
  • Prospective customer / offtaker (binding offtake not established)U.S. Department of the Air Force · sourceNOITA names Oklo as intended awardee for an anticipated long-term PPA serving Eielson. An executed PPA is not established; the Air Force’s host role remains separate.
Source-backed project statement

Oklo said on 11 June 2025 that DLA Energy, on behalf of the Department of the Air Force, issued a Notice of Intent to Award for an Aurora powerhouse at Eielson Air Force Base, with electricity and heat to be delivered under a long-term power purchase agreement. The release calls that agreement anticipated, so it is not an executed offtake. Oklo’s Alaska page says operation would follow Nuclear Regulatory Commission licensing and other federal approvals. The Air Force is the prospective power and heat customer in that notice; its separate role as site host is not itself the offtake. Oklo: Selected as intended awardee for Eielson AFB; Oklo: Alaska Aurora-Eielson powerhouse

Fuel
  • Fuel form stated for Aurorametal fuel
  • Enrichment stated for AuroraHALEU, recycled fuel or other qualified fuels
No project-specific fuel supply arrangement is recorded as a structured fact.

Oklo's Alaska page describes expected output and remote-logistics benefits, and its company description mentions fuel material awarded from Idaho National Laboratory without tying it to Eielson. Neither source names a fuel supplier, allocation or delivery for the Eielson Aurora plant. Oklo: Alaska Aurora-Eielson powerhouse

Site host or owner
Not found in the sources we checked (3): Contractor; Funding and government decisions; Comparable schedule revision
Contractor

Oklo's 11 June 2025 release says that under the anticipated agreement from DLA Energy's Notice of Intent to Award, Oklo itself would design, construct, own and operate the Eielson plant. Oklo is the vendor and intended operator, so this is not a separate contractor appointment. Neither the release nor Oklo's Alaska page names an engineering or construction contractor. Oklo: Selected as intended awardee for Eielson AFB

Funding and government decisions

Oklo's 11 June 2025 release says DLA Energy issued a Notice of Intent to Award for an Aurora plant at Eielson that Oklo would own, delivering power under a long-term power purchase agreement. A purchase agreement is an offtake arrangement, not project financing, and neither the release nor Oklo's Alaska page states a funder, amount or financing for the plant. Oklo: Selected as intended awardee for Eielson AFB

Comparable schedule revision

Comparable schedule revision not established. Oklo's Alaska page says site characterization is under way, borehole drilling is to begin in late 2026 and operations are targeted for the early 2030s after NRC licensing. Oklo's 11 June 2025 release gives no operation date. Each target appears once, so there is no revision. Oklo: Alaska Aurora-Eielson powerhouse

Not recorded in SMRMap's reviewed evidence (2): Project proposer or applicant; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(4 notes, 1 not yet reviewed)
  • Evidence review. Oklo's release (the saved copy is undated; its URL places it in 2025) says DLA Energy, on behalf of the Department of the Air Force and the Department of Defense, issued Oklo a Notice of Intent to Award for an Aurora powerhouse as the DAF's microreactor pilot, and that under the anticipated agreement Oklo would design, construct, own and operate the plant, delivering electricity and heat to Eielson Air Force Base, Alaska, under a long-term power purchase agreement. Oklo's undated Alaska page describes the Aurora-Eielson powerhouse as a smaller sodium fast reactor with expected output of approximately 60 MWth used to provide at least 5 MWe and 50-100 thousand pounds per hour of steam, at Eielson AFB about 26 miles south-east of Fairbanks, with site characterization underway, borehole drilling to begin in late 2026 and target operations in the early 2030s following NRC licensing. It adds that the DAF and the NRC are preparing environmental reviews for the pilot under NEPA. The instrument is the NOITA, an intent to award rather than a signed contract, and no NRC application is shown. The next documentary decision is the final contract award or power purchase agreement and Oklo's NRC license application, together with the NEPA review. The stored Aurora design, Oklo as vendor and operator, one unit, the siting stage and the unstored qualified 60 MWth and 5 MWe figures stay; the Eielson AFB microreactor page could not be opened when checked (access refused). Last checked 19 Oct 2026. Oklo: Selected as intended awardee for Eielson AFB; Oklo: Alaska Aurora-Eielson powerhouse
    What would change this

    DLA Energy's final contract award or the signed power purchase agreement, Oklo's NRC license application for Aurora-Eielson, or the DAF/NRC NEPA environmental document for the pilot. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. Oklo’s Alaska page says target operation in the early 2030s follows Nuclear Regulatory Commission licensing and other federal approvals, and that the Air Force and the Commission are preparing environmental reviews for siting and related matters. Those are the next decisions the page names. It does not say a license application for Eielson has been filed. Last checked 23 Oct 2026. Oklo: Alaska Aurora-Eielson powerhouse
    What would change this

    A docketed Eielson license application, or publication of the Air Force or Commission environmental review. Next scheduled check: 21 Jan 2027.

  • Permissions and public process. Oklo’s Alaska page says the Department of the Air Force and the Nuclear Regulatory Commission are preparing environmental reviews for the Eielson microreactor pilot, including siting reviews under the National Environmental Policy Act. Preparation of those reviews is not a permit or a license. The 11 June 2025 notice of intent is a procurement step, and the Air Force project page could not be reviewed. Last checked 23 Oct 2026. Oklo: Alaska Aurora-Eielson powerhouse; Oklo: Selected as intended awardee for Eielson AFB
    What would change this

    An Air Force or Commission environmental decision, or a docketed license application, for the Eielson microreactor. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water): Not disclosed in the reviewed evidence. Oklo’s Alaska page places the project at Eielson Air Force Base and says it is designed to interconnect with the base central heat and power plant for electricity and steam, while site characterization is still under way. A design intention is not a secured land, grid, or water arrangement. Neither that page nor the 11 June 2025 release states a lease, an interconnection agreement, or a water arrangement. Last checked 23 Oct 2026. Oklo: Alaska Aurora-Eielson powerhouse
    What would change this

    A land-use instrument, an interconnection agreement, or a water arrangement for the Eielson powerhouse. Next scheduled check: 21 Jan 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(0 of 3 sources with a publication or document date)
Latest dated listed source publication: no date recorded.Latest dated recorded event: no date recorded.3 of 3 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(3)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Oklo Aurora at Eielson AFB (DAF microreactor pilot) — https://smrmap.com/projects/oklo-aurora-eielson-afb/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Oklo Aurora at Eielson AFB (DAF microreactor pilot)”. Record reviewed 7 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/oklo-aurora-eielson-afb/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.