Projects / United States · Construction
Oklo Aurora-INL
Oklo's Aurora powerhouse at Idaho National Laboratory, a liquid-metal-cooled fast reactor described as up to 75 MWe, was selected for DOE's Reactor Pilot Program in August 2025.
Current status
- How current
- General record check . Bounded evidence review . 6 of 16 listed sources have a publication or document date recorded here; the newest is 6 Nov 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: DOE Aurora-INL B5.26 environmental categorical exclusion (20 Jul 2026). 1 other recorded action, such as a withdrawn, denied or superseded step. All permissions and applications
- Latest development
- 20 Jul 2026 · Environmental decision recorded: Environmental decision recorded: DOE Aurora-INL B5.26 environmental categorical exclusion. DOE Idaho approved environmental determination DOE-ID-INL-26-018 on 20 July 2026 for the proposed Aurora-INL reactor construction, installation and operation scope under B5.26. Source: DOE Aurora-INL B5.26 environmental determination, DOE-ID-INL-26-018. Updates entry
More on this development
The document describes anticipated activities and a planned construction period; it is an environmental determination, not evidence that reactor construction occurred, an approval of the preliminary safety analysis, or authority to load fuel or operate.
- Next dated milestone
- Commercial operation: 2028 (target). Aurora-INL commercial deployment target. This is not an achieved milestone. Source: Oklo: Idaho Aurora-INL powerhouse; Oklo quarterly report (Form 10-Q) for the quarter ended 30 September 2026 (investor-relations copy) (dated 6 Nov 2026); Oklo quarterly report (Form 10-Q) for the quarter ended 30 June 2026 (investor-relations copy) (dated 7 Aug 2026).
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage (reviewed: source unavailable; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
- Same design
- 4 tracked: 1 construction, 2 siting, 1 announced. 13 tracked at construction across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Sodium-cooled fast reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The up to 75 MWe figure is a stated upper bound and is not stored as a rating. Oklo's Idaho page, checked on 7 October 2026, says construction began in 2025 and that licensing is advancing alongside development; commercial deployment in 2028 is a company target. Oklo's report on Form 10-Q signed 6 November 2026 gives a target of 2028-2029 for deploying its first powerhouse, which it places at INL; its report signed 7 August 2026 gave 2028. These are company targets. DOE categorical exclusion DOE-ID-INL-25-033 R1 (CX-035336), approved on 10 December 2025, covers limited non-nuclear site and support construction and states that no reactor components will be installed or constructed under that determination. Those sources report physical construction, so the stage is construction. They do not record reactor-component installation or operating authority. It is following DOE authorization, not an NRC license. An NRC audit plan records that Oklo submitted a Nuclear Safety Design Agreement and a preliminary documented safety analysis to DOE. On 5 June 2026 the NRC sent preliminary feedback on its observation of those submittals (ML26147A372). The letter says DOE's determination is independent and that a final audit report will follow. It is not a DOE approval and not an NRC license. Oklo announced on 11 June 2026 that DOE approved the preliminary analysis; the DOE approval document was not opened. A preliminary approval would not be authority to load fuel or operate. At the NRC, a 2020 combined license application was denied without prejudice on 6 January 2022, and the NRC lists pre-application activity only. Microreactor label applied. Oklo stated on 11 June 2026 that DOE's Idaho Operations Office had approved the Aurora-INL preliminary documented safety analysis under the Reactor Pilot Program; the DOE approval letter has not been available for review, so the approval is recorded as a company claim, not a DOE regulatory action. A separate DOE environmental categorical exclusion, DOE-ID-INL-26-018, was approved on 20 July 2026. It covers the proposed reactor construction, installation and operation scope under B5.26, with construction planned for July 2026 through February 2028. That planned scope is not proof that reactor construction or operation occurred, and the document does not state DOE approved the preliminary safety analysis or issued operating authority. It describes initial output of approximately 45 MWe and 147 MWth, with upper bounds of 75 MWe and 234 MWth; these are planned operational parameters, not a fixed achieved output. Oklo says Aurora-INL has been granted access to fuel recovered from the Experimental Breeder Reactor-II following a competitive DOE process launched in 2019, and that its initial fuel assemblies will be fabricated from that material at Oklo's Aurora Fuel Fabrication Facility at Idaho National Laboratory. These are company statements.
Key facts
- Design
- Aurora (Microreactor)
- Technology
- Sodium-cooled fast reactor (SFR) · sodium
- Operator(s)
- Oklo Inc.
- Vendor for linked design
- Oklo Inc.
- Location
- Idaho National Laboratory — Aurora site south of the Materials and Fuels Complex · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
DOE categorical exclusion CX-035336 places the 40-acre Aurora site at INL, south of the Materials and Fuels Complex (MFC) and north of U.S. Highway 20. The pin reuses the recorded OpenStreetMap building center of the EBR-II containment at MFC (43.59507, −112.65716): it marks the MFC area, not the Aurora parcel. Replaces an earlier Central Facilities Area point about 24 km to the west. - Coordinates
- 43.59507, -112.65716 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: module
- Thermal capacity
- Not recorded
- Purpose
- Research or test reactor
- Construction start
- 2025Oklo-reported Aurora-INL construction start
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Could not be confirmed on . Attempted official source: NRC pre-application activities: Oklo Aurora Powerhouse. This is an access or status observation only; the record review date is unchanged.
Site and capacity notes
Oklo Aurora-INL is recorded at Idaho National Laboratory — Aurora site south of the Materials and Fuels Complex, Idaho, United States. Operator: Oklo Inc.. Recorded vendor: Oklo Inc.. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: building center of the EBR-II containment (DOME) at the Materials and Fuels Complex, 43.59507, −112.65716
Electrical output is not recorded on this project. Modules planned: 1. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorOklo Inc.
- Reactor supplier
- Vendor for the linked designOklo Inc.
- Contractor
- Construction contractorKiewit Nuclear Solutions Co. · sourceSelected as lead constructor under a master services agreement (15 July 2025) supporting design, procurement and construction; contract value not disclosed.
Source-backed project statement
Kiewit's 15 July 2025 release says Oklo selected Kiewit Nuclear Solutions as lead constructor for Aurora-INL under a newly executed master services agreement to support design, procurement and construction, and Oklo's 22 September 2025 groundbreaking release restates that role. The contract value is not disclosed. DOE's December 2025 categorical exclusion covers only non-nuclear site and support construction, so reactor construction is not shown. Kiewit: Oklo selects Kiewit as the lead constructor for first Aurora powerhouse in Idaho; Oklo breaks ground on first Aurora powerhouse
- Funding and government decisions
Source-backed project statement Oklo's second-quarter 2024 shareholder letter says Oklo will fund the first Aurora powerhouses, starting with its first plant in Idaho. That is a company statement of self-funding with no amount, and no outside funder or financing for Aurora-INL is named in the sources read. Oklo second-quarter 2024 shareholder letter
- Fuel
- Fuel supplier named for this projectU.S. Department of Energy · sourceAwarded fuel recovered from EBR-II in 2019, per Oklo; as of Sep 2025 Oklo had completed two of four steps toward DOE authorization to fabricate the initial core at its INL facility.
- Fuel form stated for Aurorametal fuel
- Enrichment stated for AuroraHALEU, recycled fuel or other qualified fuels
Source-backed project statement
Oklo's 22 September 2025 groundbreaking release says DOE awarded Oklo fuel recovered from EBR-II in 2019 and that Oklo had completed two of four steps toward DOE authorization to fabricate the initial core at its Aurora Fuel Fabrication Facility at INL. Oklo's Idaho page says that facility is under construction. This is an awarded fuel allocation with fabrication still pending authorization. No core has been fabricated or delivered. Oklo breaks ground on first Aurora powerhouse; Oklo: Idaho Aurora-INL powerhouse
- Site host or owner
- Site hostIdaho National Laboratory · source
- Programs and agreements naming the project
- Government program; activeDOE Reactor Pilot Program (DOE-authorized advanced test reactors)
- Comparable schedule revision
Source-backed project statement Oklo's report on Form 10-Q for the quarter ended 30 June 2026 (signed 7 August 2026) states an ambitious target of deploying its first powerhouse in 2028. The corresponding Plan of Operations passage in its report for the quarter ended 30 September 2026 (signed 6 November 2026) states 2028-2029. Both reports expect the construction of the first powerhouse at INL, and the passages cited give no reason for the change. Oklo's undated Idaho page, read on 7 October and again on 11 November 2026, targets commercial deployment in 2028; the reports' word 'deploying' is not defined as commercial operation. Earlier statements (a 2027 aim in Oklo's August 2024 shareholder letter, Kiewit's late 2027 to early 2028 in July 2025) used different milestone terms. These are company targets, not a DOE schedule or authorization, and no deployment is recorded as achieved. Oklo quarterly report (Form 10-Q) for the quarter ended 30 June 2026 (investor-relations copy); Oklo quarterly report (Form 10-Q) for the quarter ended 30 September 2026 (investor-relations copy); Oklo: Idaho Aurora-INL powerhouse; Oklo second-quarter 2024 shareholder letter; Kiewit: Oklo selects Kiewit as the lead constructor for first Aurora powerhouse in Idaho
Not found in the sources we checked (1): Customer or offtaker
- Customer or offtaker
Oklo's Idaho page says Aurora-INL supports Oklo's first planned commercial operations, with construction begun in 2025 and commercial deployment targeted for 2028. It names no buyer or power purchase agreement for Aurora-INL's output, and the Kiewit and groundbreaking releases name none either. Oklo: Idaho Aurora-INL powerhouse
Timeline
Recorded developments
- · Environmental decision recorded
Environmental decision recorded: DOE Aurora-INL B5.26 environmental categorical exclusion - Announced · Announcement
Oklo announces DOE approval of the Aurora-INL preliminary safety analysis - · Recorded development
NRC preliminary feedback on its observation of Aurora-INL DOE submittals - · Construction start
Oklo-reported Aurora-INL construction start - · Other regulatory action: Denied
Other regulatory action: Denied: Oklo Aurora custom combined license application (2020), denied without prejudice
Earlier developments (1)
- · Application submitted
Application for the Aurora combined license
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Commercial operation
Aurora-INL commercial deployment target
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Environmental decision
- DOE Aurora-INL B5.26 environmental categorical exclusion
Environmental decision · Issued / approved · U.S. Department of Energy, Idaho Operations Office · decided 20 Jul 2026
DOE Idaho approved environmental determination DOE-ID-INL-26-018 on 20 July 2026 for the proposed Aurora-INL reactor construction, installation and operation scope under B5.26. The document describes anticipated activities and a planned construction period; it is an environmental determination, not evidence that reactor construction occurred, an approval of the preliminary safety analysis, or authority to load fuel or operate.
Sources: DOE Aurora-INL B5.26 environmental determination, DOE-ID-INL-26-018
Other applications and decisions
- Oklo Aurora custom combined license application (2020), denied without prejudice
Other regulatory action · Denied · NRC · decided 6 Jan 2022 · submitted 11 Mar 2020 · docket 52-049 · ADAMS ML20075A001, ML21357A034 · 87 FR 1441
Oklo Power applied on 11 March 2020 for a custom combined license, which covers construction and operation, for one Aurora microreactor at Idaho National Laboratory. The NRC denied it without prejudice by letter of 6 January 2022 because requested information was not provided, and said Oklo may resubmit. This is an earlier application than the current Aurora powerhouse, which is following DOE authorization under the Reactor Pilot Program. The NRC's page, last reviewed 15 September 2026, lists pre-application activity only (project 99902095) and no docketed application.
Sources: Federal Register 87 FR 1441 (11 Jan 2022): Oklo Aurora combined license application, denial; NRC pre-application activities: Oklo Aurora Powerhouse
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes)
- Evidence review. Oklo's Idaho page calls the Aurora powerhouse at INL its first fast fission power plant, developed on federal land with DOE under the Reactor Pilot Program, and says construction began in 2025 with commercial deployment targeted for 2028; future commercial deployment is subject to NRC licensing. The NRC places it in Blackfoot, Idaho on the INL site, and DOE categorical exclusion DOE-ID-INL-25-033 R1 (CX-035336, approved 10 December 2025) places the work on a 40-acre site south of the Materials and Fuels Complex and north of U.S. Highway 20. CX-035336 covers only non-nuclear site preparation (clearing, roads, utilities, support and turbine buildings without safety-related equipment, and excavation of the reactor building footprint), expected to begin as early as fall 2025 and last up to three years, and states that no reactor components will be installed or constructed under it; no opened source reports reactor-component installation or safety-related nuclear construction. An NRC audit plan says Oklo submitted a Nuclear Safety Design Agreement and a preliminary documented safety analysis to DOE, that a documented safety analysis reflecting the as-built facility follows construction, and that Oklo plans an NRC license application after DOE authorization. Oklo's release (stored as 11 June 2026) says DOE's Idaho Operations Office approved the preliminary analysis, and Nuclear Engineering International (16 June 2026) calls that the third of four steps toward full federal authorization to construct and operate; DOE's own approval was not opened, so this remains a company-reported step, not a construction or operating permission. The NRC lists only pre-application activity and describes the Oklo reactors as liquid-metal-cooled, metal-fueled fast reactors with a maximum of 75 MWe; no fixed plant rating is published, so none is stored. DOE's July 2026 environmental determination DOE-ID-INL-26-018 could not be opened on 19 October 2026 (access refused), so its stored construction period (July 2026 to February 2028) and planned 45 MWe/147 MWth initial output could not be re-read. Oklo says it expects to gain operating experience with Aurora-INL. Oklo as developer and intended operator and the INL site match the sources. At that review the record had no participant roles; roles recorded since are listed on this page. The stored construction stage rests on Oklo's statement and non-nuclear site work; no opened source documents nuclear construction, so a licensing stage based on the DOE safety-analysis submittals is proposed for the coordinator. Last checked 19 Oct 2026. Oklo: Idaho Aurora-INL powerhouse; NRC audit plan: observation of DOE authorization activities for the Oklo Aurora powerhouse at INL (ADAMS ML26020A209); DOE-ID categorical exclusion CX-035336 for Oklo limited construction; Oklo Aurora-INL PDSA approval announcement; Nuclear Engineering International: Oklo clears DOE safety milestone; NRC pre-application activities: Oklo Aurora Powerhouse; DOE Aurora-INL B5.26 environmental determination, DOE-ID-INL-26-018
What would change this
DOE publishes the Aurora-INL preliminary safety analysis approval or the authorization to construct the reactor, or Oklo or DOE reports installation of reactor components at the INL site. Next scheduled check: 19 Jan 2027.
- Plant capacity (scope qualified): Not disclosed in the reviewed evidence. No fixed Aurora-INL rating is published in the readable sources. The NRC describes the Oklo reactors as having a maximum power level of 75 MWe, which is an upper bound. DOE's 20 July 2026 environmental determination, which earlier reviewers read as giving a planned initial output of about 45 MWe and 147 MWth with upper bounds of 75 MWe and 234 MWth, returned an access refusal (HTTP 403) on 19 October 2026 and could not be re-read. Planned parameters and bounds are not stored as a rating. Last checked 19 Oct 2026. NRC pre-application activities: Oklo Aurora Powerhouse; DOE Aurora-INL B5.26 environmental determination, DOE-ID-INL-26-018
What would change this
DOE authorization documents or an Oklo filing state the Aurora-INL design rating. Next scheduled check: 19 Jan 2027.
- Permission evidence appropriate to stage: Source unavailable. Aurora-INL follows DOE authorization under the Reactor Pilot Program, not an NRC license; the NRC lists pre-application activity only. Oklo states that DOE's Idaho Operations Office approved the preliminary documented safety analysis, and trade press calls that the third of four federal steps toward authorization to construct and operate, but DOE's approval document was not readable and no DOE authorization to construct or operate the reactor is published. DOE's environmental determination of 20 July 2026 returned an access refusal (HTTP 403) on 19 October 2026. CX-035336 of 10 December 2025 covers only non-nuclear site work. Last checked 19 Oct 2026. Nuclear Engineering International: Oklo clears DOE safety milestone; Oklo Aurora-INL PDSA approval announcement; DOE Aurora-INL B5.26 environmental determination, DOE-ID-INL-26-018
What would change this
DOE publishes the PDSA approval or a construction or operating authorization for Aurora-INL. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. Oklo's Idaho page, checked 7 October 2026, says construction began in 2025 and targets commercial deployment in 2028, with licensing and engineering advancing in parallel. The June 2026 NRC letter says Oklo intends to move Aurora-INL from DOE authorization to an NRC power reactor license through a future application. The 2028 date is a company target, and these sources do not date the next DOE authorization after the June 2026 preliminary safety approval. Last checked 23 Oct 2026. Oklo: Idaho Aurora-INL powerhouse; NRC preliminary feedback on observation of DOE authorization for Aurora-INL (ADAMS ML26147A372)
What would change this
A DOE start-up or fuel-loading authorization, a revised commercial-deployment date, or an NRC application filing for Aurora-INL. Next scheduled check: 23 Jan 2027.
- Permissions and public process. Oklo's 11 June 2026 release says DOE's Idaho Operations Office approved the preliminary documented safety analysis for Aurora-INL under DOE's Reactor Pilot Program; Oklo's Idaho page says future commercial deployment is subject to NRC licensing. A June 2026 NRC letter says Oklo has no Aurora-INL licensing application before the NRC and only asked it to observe DOE's review. A preliminary safety approval is not authority to load fuel or operate, and these sources record no public consultation or hearing. Last checked 23 Oct 2026. Oklo Aurora-INL PDSA approval announcement; Oklo: Idaho Aurora-INL powerhouse; NRC preliminary feedback on observation of DOE authorization for Aurora-INL (ADAMS ML26147A372)
What would change this
A DOE approval of the final safety analysis or start-up authorization, or an NRC license application for Aurora-INL. Next scheduled check: 23 Jan 2027.
- Site dependencies (land, grid, water). DOE Idaho's December 2025 categorical exclusion for Oklo's non-nuclear construction places Aurora-INL on a 40-acre site south of INL's Materials and Fuels Complex and north of U.S. Highway 20, with water, septic and electrical utilities in scope. It says transmission lines to or from the facility are not included and that septic and industrial wastewater reuse systems need state permits. These sources show no grid interconnection, offtake or water-right arrangement. Last checked 23 Oct 2026. DOE-ID categorical exclusion CX-035336 for Oklo limited construction
What would change this
A transmission or interconnection agreement, a state wastewater or water permit, or a DOE environmental document covering grid connection. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure: Source unavailable. No readable source states a spent-fuel, waste or closure arrangement for Aurora-INL. Oklo's Idaho page and its 11 June 2026 release say nothing on Aurora-INL waste; its Form 10-Q signed 6 November 2026 describes company-wide used-fuel recycling plans and five metric tons of HALEU produced from recovered uranium from irradiated EBR-II fuel, but no Aurora-INL used-fuel or decommissioning arrangement. DOE's CX-035336 (non-nuclear site work) covers construction waste only. The DOE determination for the reactor scope, DOE-ID-INL-26-018 (approved 20 July 2026, categorical exclusion B5.26), is the document most likely to address it. Direct fetches from the VPS returned an access refusal (HTTP 403) (8 and 19 October 2026); it was opened once in a public web reader on 8 October 2026, when its scope and planned output were recorded but no spent-fuel or waste statement was recorded, and it was not re-read for this review. A web search on 13 November 2026 found no source on who holds Aurora spent fuel. Reviewed 13 November 2026. Last checked 13 Nov 2026. Oklo: Idaho Aurora-INL powerhouse; Oklo press release: DOE approves Aurora-INL PDSA (11 June 2026); Oklo quarterly report (Form 10-Q) for the quarter ended 30 September 2026 (investor-relations copy); DOE-ID categorical exclusion CX-035336 for Oklo limited construction; DOE Aurora-INL B5.26 environmental determination, DOE-ID-INL-26-018
What would change this
A readable copy of DOE-ID-INL-26-018, or a DOE or Oklo document stating who holds and disposes of Aurora-INL used fuel and the closure arrangement. Next scheduled check: 12 Feb 2027.
Evidence dates
(6 of 16 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(16)
- Oklo Aurora-INL PDSA approval announcement (company, accessed 1 Oct 2026)
- NRC audit plan: observation of DOE authorization activities for the Oklo Aurora powerhouse at INL (ADAMS ML26020A209) (regulator, accessed 5 Oct 2026)
- NRC preliminary feedback on observation of DOE authorization for Aurora-INL (ADAMS ML26147A372) (regulator, accessed 5 Oct 2026)
- NRC pre-application activities: Oklo Aurora Powerhouse (regulator, accessed 18 Oct 2026)
- Federal Register 87 FR 1441 (11 Jan 2022): Oklo Aurora combined license application, denial (regulator, accessed 5 Oct 2026)
- DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212) (government, accessed 15 Oct 2026)
- Oklo press release: DOE approves Aurora-INL PDSA (11 June 2026) (company, accessed 18 Oct 2026)
- Oklo: Idaho Aurora-INL powerhouse (company, accessed 7 Oct 2026)
- DOE-ID categorical exclusion CX-035336 for Oklo limited construction (government, accessed 7 Oct 2026)
- DOE Aurora-INL B5.26 environmental determination, DOE-ID-INL-26-018 (government, accessed 8 Oct 2026)
- Nuclear Engineering International: Oklo clears DOE safety milestone (news report, published 16 Jun 2026, accessed 18 Oct 2026)
- Kiewit: Oklo selects Kiewit as the lead constructor for first Aurora powerhouse in Idaho (company, published 15 Jul 2025, accessed 21 Oct 2026)
- Oklo breaks ground on first Aurora powerhouse (company, published 22 Sep 2025, accessed 21 Oct 2026)
- Oklo second-quarter 2024 shareholder letter (company, published Aug 2024, accessed 21 Oct 2026)
- Oklo quarterly report (Form 10-Q) for the quarter ended 30 September 2026 (investor-relations copy) (company, dated 6 Nov 2026, accessed 11 Nov 2026)
- Oklo quarterly report (Form 10-Q) for the quarter ended 30 June 2026 (investor-relations copy) (company, dated 7 Aug 2026, accessed 11 Nov 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Oklo Aurora-INL — https://smrmap.com/projects/oklo-aurora-inl/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Oklo Aurora-INL”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/oklo-aurora-inl/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.