Projects / United States · Announced
Oklo Aurora power for Diamondback Energy near Midland, Texas (2024 LOI)
On 8 April 2024 Oklo and Diamondback Energy signed a non-binding letter of intent toward a 20-year power purchase agreement.
Current status
- How current
- General record check . Bounded evidence review . The listed source has no publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- No map pin is shown for this record.
- Expected for this stage but not recorded as a structured fact: Site location recorded as disclosed (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
- Same design
- 4 tracked: 1 construction, 2 siting, 1 announced. 96 tracked at announced across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Sodium-cooled fast reactor. How it works, with a 3D view.
View on the map · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Oklo intends to license, build and operate Aurora powerhouses supplying 50 MWe collectively to Diamondback E&P LLC, Diamondback Energy’s subsidiary, near Midland, Texas. The supply is not a disclosed module rating or count. No executed PPA, operating permission, reactor plot or later milestone is established in these sources; cancellation is not inferred.
Key facts
- Design
- Aurora (Microreactor)
- Technology
- Sodium-cooled fast reactor (SFR) · sodium
- Intended operator(s)
- Oklo Inc.
- Vendor for linked design
- Oklo Inc.
- Location
- Diamondback Energy Permian operations near Midland · United States · precision: region only
Searchable without an invented map pin. - Coordinates
- Region only, no map pin
- Electrical capacity
- 50 MWe (gross/net unspecified) · scope: plant
Proposed collective electricity supply under a non-binding letter of intent; this figure does not establish a selected plant or module nameplate. - Thermal capacity
- Not recorded
- Modules planned
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Oklo Aurora power for Diamondback Energy near Midland, Texas (2024 LOI) is recorded at Diamondback Energy Permian operations near Midland, Texas, United States. Intended operator: Oklo Inc.. Recorded vendor: Oklo Inc.. Stage: Announced. Location precision: region only; region only, no map pin.
Recorded electrical output is 50 MWe (gross/net unspecified), scope plant. Proposed collective electricity supply under a non-binding letter of intent; this figure does not establish a selected plant or module nameplate. Module count is not recorded. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- Reactor supplier
- Vendor for the linked designOklo Inc.
- Customer or offtaker
- Prospective customer / offtaker (binding offtake not established)Diamondback E&P LLC · source
Source-backed project statement
Oklo's 8 April 2024 release says Oklo and Diamondback Energy signed a non-binding letter of intent toward a 20-year power purchase agreement for 50 MW from Aurora powerhouses to power Diamondback's Permian Basin operations. A letter of intent is not an executed power purchase agreement, and no later step is recorded. Oklo signs LOI to supply 50 MW to Diamondback Energy
- Fuel
- Fuel form stated for Aurorametal fuel
- Enrichment stated for AuroraHALEU, recycled fuel or other qualified fuels
Oklo's 8 April 2024 announcement says the company was awarded fuel material from Idaho National Laboratory and is developing fuel recycling, but those company statements do not mention Diamondback or Midland. No fuel allocation, supplier or delivery is stated for these powerhouses. Oklo signs LOI to supply 50 MW to Diamondback Energy
Not found in the sources we checked (3): Contractor; Funding and government decisions; Comparable schedule revision
- Contractor
Oklo's 8 April 2024 announcement of its non-binding letter of intent with Diamondback Energy says Oklo itself intends to license, build and operate Aurora powerhouses supplying 50 MW to Diamondback E&P near Midland, Texas. No separate engineering, licensing or construction contractor is named. Oklo signs LOI to supply 50 MW to Diamondback Energy
- Funding and government decisions
Oklo's 8 April 2024 announcement states no price, capital amount or financing for the Diamondback powerhouses. It says Oklo's design-build-own-operate model should let customers like Diamondback buy power without capital requirements, which describes the business model rather than a funding commitment for this supply. Oklo signs LOI to supply 50 MW to Diamondback Energy
- Comparable schedule revision
Comparable schedule revision not established. Oklo's 8 April 2024 announcement gives a 20-year proposed power purchase term with a 20-year renewal option and a 40-year design life, which are durations, not milestone dates. It states no construction or operation date for the Midland powerhouses, so no revision is shown. Oklo signs LOI to supply 50 MW to Diamondback Energy
Not recorded in SMRMap's reviewed evidence (2): Site host or owner; Programs and agreements naming the project
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes, 1 not yet reviewed)
- Evidence review. On 8 April 2024 Oklo and Diamondback Energy signed a non-binding letter of intent to collaborate on a 20-year power purchase agreement. The letter says Oklo intends to license, build, and operate Aurora powerhouses capable of generating 50 MW electric for Diamondback E&P LLC near Midland, Texas. That 50 MW figure is the combined supply of those powerhouses, not a single-module rating, and no module count is stated. Diamondback is described as a customer that would buy power, not as the operator. No reactor plot is named. The stored 50 MWe, plant scope, Aurora design, and announced stage stay. Last checked 19 Oct 2026. Oklo signs LOI to supply 50 MW to Diamondback Energy
What would change this
A binding power purchase agreement, or a project filing that names the reactor site and the licensee, rather than this non-binding letter. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed: Not disclosed in the reviewed evidence. The letter places the customer’s operations near Midland, Texas. It does not name a reactor site or plot. Last checked 19 Oct 2026. Oklo signs LOI to supply 50 MW to Diamondback Energy
What would change this
An Oklo or Diamondback filing that names the reactor location rather than the customer’s area. Next scheduled check: 19 Jan 2027.
- Plant capacity (scope qualified). Proposed collective electricity supply under a non-binding letter of intent; this figure does not establish a selected plant or module nameplate. Last checked 19 Oct 2026. Oklo signs LOI to supply 50 MW to Diamondback Energy
What would change this
A binding power purchase agreement or technical filing that defines plant and module capacity separately. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The next consequential step named in Oklo's April 2024 release is turning the non-binding letter of intent into a 20-year power purchase agreement, with options to extend for a further 20 years. The release gives no date for that agreement, and these sources record no executed agreement or later milestone. Last checked 23 Oct 2026. Oklo signs LOI to supply 50 MW to Diamondback Energy
What would change this
Execution of the Oklo-Diamondback power purchase agreement, or an announcement that the letter of intent has lapsed. Next scheduled check: 23 Apr 2027.
- Permissions and public process: Not disclosed in the reviewed evidence. Oklo's 8 April 2024 release says that under a non-binding letter of intent Oklo intends to license, build and operate Aurora powerhouses supplying 50 MWe to Diamondback's subsidiary near Midland, Texas. It names no NRC application, state permit or local consultation for a Permian Basin plant, so no permission is established in this source. Last checked 23 Oct 2026. Oklo signs LOI to supply 50 MW to Diamondback Energy
What would change this
An Oklo NRC filing or Texas permit application for powerhouses serving Diamondback. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water): Not disclosed in the reviewed evidence. Oklo's April 2024 release places the planned supply near Midland, Texas, for Diamondback's Permian Basin operations, but names no plot, land agreement, grid or behind-the-meter connection, or water arrangement for the powerhouses. The site arrangements are therefore not disclosed in this source. Last checked 23 Oct 2026. Oklo signs LOI to supply 50 MW to Diamondback Energy
What would change this
An Oklo or Diamondback announcement of a site or connection arrangement near Midland. Next scheduled check: 23 Apr 2027.
Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.
Evidence dates
(0 of 1 source with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(1)
- Oklo signs LOI to supply 50 MW to Diamondback Energy (company, accessed 2 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Oklo Aurora power for Diamondback Energy near Midland, Texas (2024 LOI) — https://smrmap.com/projects/oklo-diamondback/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Oklo Aurora power for Diamondback Energy near Midland, Texas (2024 LOI)”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/oklo-diamondback/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.