Projects / Poland · Siting
OSGE Ostrołęka BWRX-300 proposal
One of six locations named in OSGE decisions in principle.
Current status
- How current
- General record check . Bounded evidence review . 2 of 7 listed sources have a publication or document date recorded here; the newest is 5 Nov 2025. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Announced 7 Dec 2023 · Announcement: OSGE Ostrołęka BWRX-300 proposal documented. One of six locations named in OSGE decisions in principle. Source: OSGE six decisions in principle. Updates entry
More on this development
Further regulatory applications are required; this is not a construction license. The 24-unit fleet total does not establish a site module count.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- State or province is not recorded.
- Same design
- 18 tracked: 1 construction, 4 licensing, 10 siting, 3 announced. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Boiling water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Further regulatory applications are required; this is not a construction license. The 24-unit fleet total does not establish a site module count.
Key facts
- Design
- BWRX-300 (SMR)
- Technology
- Boiling water reactor (BWR) · light water
- Reactor vessel of this design
- 27 m tall, 4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 25.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Not recorded
- Vendor for linked design
- GE Vernova Hitachi Nuclear Energy
- Design origin
- United States: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
- Location
- Ostrołęka · Poland · precision: town or locality only
Approximate coordinates for the named Ostrołęka proposal location from the NuclearChain reactors export (CC BY 4.0; derived from GEM's tracker). - Coordinates
- 53.0674, 21.561 · town-level point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded. The page says 24 BWRX-300 reactors can be deployed across the six sites.
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 2 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
OSGE Ostrołęka BWRX-300 proposal is recorded at Ostrołęka, state or province not recorded, Poland. Operator: No operator is recorded. Recorded vendor: GE Vernova Hitachi Nuclear Energy. Stage: Siting. Location precision: town or locality only; town-level point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'ostro-eka-nuclear-power-plant-1' (53.0674009, 21.5610332)
Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project. The linked design record states 870 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerORLEN Synthos Green Energy · source
- Reactor supplier
- Vendor for the linked designGE Vernova Hitachi Nuclear Energy
Not found in the sources we checked (5): Customer or offtaker; Contractor; Funding and government decisions; Fuel; Comparable schedule revision
- Customer or offtaker
The reviewed sources do not establish a named project-specific power or heat purchaser, contractual quantity or completed offtake. Intended uses, host municipalities and general company customer plans are not buyer commitments. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. OSGE six decisions in principle; OSGE: first locations presented; OSGE CfD application three sites
- Contractor
The reviewed sources do not establish an additional project-specific engineering, preparatory-work or construction assignment. A supplier’s general capabilities or an industry-wide agreement do not establish a contract for this site. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. OSGE six decisions in principle; OSGE news index reviewed 21 October 2026; OSGE: first locations presented
- Funding and government decisions
The reviewed sources do not establish a project-specific financing commitment or amount. General company backing, ownership and policy support do not by themselves establish allocated or paid project funding. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. OSGE CfD application three sites; OSGE six decisions in principle; OSGE: first locations presented; OSGE news index reviewed 21 October 2026
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
The reviewed sources do not establish a project-specific fuel supplier commitment or delivery. General supply-market plans and reactor-design fuel requirements are kept separate. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. OSGE: Orano regional SMR deployment framework; OSGE six decisions in principle
- Comparable schedule revision
Comparable schedule revision not established. The reviewed sources do not establish two dated statements revising the same project milestone. A single target, a fleet-level ambition or a different project’s timetable is not a schedule revision. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. OSGE six decisions in principle; OSGE CfD application three sites; OSGE: first locations presented; OSGE: Orano regional SMR deployment framework
Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Reviewed 20 Oct 2026: not disclosed in the reviewed evidence.
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- Announced · Announcement
OSGE Ostrołęka BWRX-300 proposal documented
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Assessments of the design (not of this site)
(2)
- BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs - CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes)
- Evidence review. The decisions in principle are not a construction license and that the 24-unit sentence is a fleet total, so no module count is stored for Ostrołęka. The carried six-city sentence names Ostrołęka with the other five locations. The same OSGE page says 24 BWRX-300 reactors can be deployed at the sites, that OSGE's special-purpose companies submitted the applications, and that the decision in principle lets OSGE apply later for a siting decision or a construction license. Twenty-four is not this city's count. The participating organizations retain only their source-supported roles; a reactor operator is not assigned from the study, proposer, parent, existing-fleet or proposed-owner relationship. Last checked 20 Oct 2026. OSGE six decisions in principle
What would change this
A further Ostrołęka application that states a unit count or a parcel, or a siting decision or construction license. Next scheduled check: 20 Jan 2027.
- Module/unit count: Not disclosed in the reviewed evidence. The page says 24 BWRX-300 reactors can be deployed across the six sites. That fleet figure is not a count for Ostrołęka. Last checked 19 Oct 2026. OSGE six decisions in principle
What would change this
A site-specific OSGE application that states how many BWRX-300 units are proposed at Ostrołęka. Next scheduled check: 19 Jan 2027.
- Operator or intended licensed owner: Not disclosed in the reviewed evidence. The reviewed sources establish other participant roles, but do not appoint the recorded party as this reactor’s operator. The operator remains unassigned; this does not assert that no operator exists. Last checked 20 Oct 2026. OSGE six decisions in principle
What would change this
A project-specific filing, operating agreement or developer statement explicitly names the proposed reactor operator. Next scheduled check: 20 Jan 2027.
- Next decision and prerequisites. With its decision-in-principle, OSGE may apply for further permits for Ostrołęka, such as a siting decision and later a construction license. No application or date for those steps is recorded in the opened source. Last checked 23 Oct 2026. OSGE six decisions in principle
What would change this
An OSGE application for, or issue of, a siting decision for the Ostrołęka project. Next scheduled check: 21 Jan 2027.
- Permissions and public process. OSGE reports that Poland's Ministry of Climate and Environment issued a decision-in-principle for a BWRX-300 plant at Ostrołęka, one of six issued on applications by OSGE's special-purpose companies. Under Polish law this is the first administrative decision for a nuclear investment. It is not a siting decision, environmental decision or construction license, and none is recorded for this site. Last checked 23 Oct 2026. OSGE six decisions in principle
What would change this
A siting decision, environmental decision or construction-license application for the Ostrołęka project. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). World Nuclear News reported in February 2025 that GDOŚ issued the scope of the environmental report for OSGE's Ostrołęka project, allowing environmental and siting research to begin, with cooling-system solutions among the areas to be covered. Ostrołęka was not among the three sites in OSGE's June 2026 contract-for-difference application. No plot, cooling-water source or grid connection has been fixed in the sources reviewed. Last checked 23 Oct 2026. Progress in environmental permitting of Polish SMR projects; OSGE: first locations presented; OSGE CfD application three sites
What would change this
The Ostrołęka environmental impact report or grid connection conditions for the site. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. OSGE's November 2025 release says it signed a framework agreement with Orano covering fuel-cycle services for its BWRX-300 program, including spent fuel reprocessing and recycling, transport and storage, and decommissioning. The agreement is fleet-wide and does not name Ostrołęka; it is a framework, not a contract for specific services, and no site-specific spent fuel storage or disposal arrangement for Ostrołęka is described in the sources reviewed. Last checked 23 Oct 2026. OSGE: Orano regional SMR deployment framework
What would change this
An environmental impact report, license application or services contract setting spent fuel and waste arrangements for the Ostrołęka plant. Next scheduled check: 23 Oct 2027.
Evidence dates
(2 of 7 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(7)
- OSGE six decisions in principle (company, accessed 1 Oct 2026)
- Global Energy Monitor Global Nuclear Power Tracker (directory or tracker, accessed 2 Oct 2026)
- OSGE: first locations presented (company, accessed 2 Oct 2026)
- OSGE CfD application three sites (company, accessed 1 Oct 2026)
- OSGE news index reviewed 21 October 2026 (company, accessed 21 Oct 2026)
- OSGE: Orano regional SMR deployment framework (company, published 5 Nov 2025, accessed 21 Oct 2026)
- Progress in environmental permitting of Polish SMR projects (news report, published 11 Feb 2025, accessed 23 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: OSGE Ostrołęka BWRX-300 proposal — https://smrmap.com/projects/osge-ostroleka/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “OSGE Ostrołęka BWRX-300 proposal”. Record reviewed 2 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/osge-ostroleka/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.