Projects / Poland · Announced

OSGE Warsaw potential BWRX-300 location (2023 list)

In April 2023 OSGE listed Warsaw among seven potential BWRX-300 locations.

Current status

Stage
Announced
How current
General record check . Bounded evidence review . 1 of 4 listed sources has a publication or document date recorded here: 11 Feb 2025. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • No map pin is shown for this record.
Same design
18 tracked: 1 construction, 4 licensing, 10 siting, 3 announced. 96 tracked at announced across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Boiling water reactor. How it works, with a 3D view.
Schematic of BWRX-300. A tall reactor vessel with, from bottom to top, control rods and drives, the core, a tall chimney, steam separators and a steam dryer.
Schematic of BWRX-300.

Description

Unlike the other six, it has no decision in principle, and no later OSGE statement was found. Current status is unknown; cancellation is not inferred.

Key facts

Design
BWRX-300 (SMR)
Technology
Boiling water reactor (BWR) · light water
Reactor vessel of this design
27 m tall, 4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 25.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Operator(s)
Not recorded
Vendor for linked design
GE Vernova Hitachi Nuclear Energy
Design origin
United States: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
Location
Warszawa (OSGE potential location) · Poland · precision: town or locality only
The sources name this place but publish no coordinate for it, so no pin is shown.
Coordinates
Town named, no map pin
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
low
Record reviewed
2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

OSGE Warsaw potential BWRX-300 location (2023 list) is recorded at Warszawa (OSGE potential location), Masovian, Poland. Operator: No operator is recorded. Recorded vendor: GE Vernova Hitachi Nuclear Energy. Stage: Announced. Location precision: town or locality only; town named, no map pin.

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project. The linked design record states 870 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Reactor supplier
Not found in the sources we checked (5): Customer or offtaker; Contractor; Funding and government decisions; Fuel; Comparable schedule revision
Customer or offtaker

ORLEN Synthos Green Energy's 17 April 2023 page lists Warsaw among seven potential BWRX-300 locations and says these include energy-intensive plants and places suited to district heating, but it names no plant, heat network or buyer in Warsaw. The Warsaw street address printed on the page is the company's office. OSGE: first locations presented

Contractor

ORLEN Synthos Green Energy's 17 April 2023 page says the company, which holds exclusive Polish rights to the BWRX-300, would analyze seven potential locations including Warsaw over two years, and that dozens of Polish firms would join the supply chain. It names no engineering, study or construction contractor for Warsaw. OSGE: first locations presented

Funding and government decisions

ORLEN Synthos Green Energy's 17 April 2023 page says power from a small unit would ultimately cost far less than gas and that about half the spending on the first SMR would stay in Poland, but states no amount, funder or financing for a Warsaw reactor. OSGE: first locations presented

Fuel
No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.

ORLEN Synthos Green Energy's 17 April 2023 page describes the BWRX-300's output and 60-year life but names no fuel type, supplier, quantity or delivery for Warsaw or any of the seven listed locations. OSGE: first locations presented

Comparable schedule revision

Comparable schedule revision not established. ORLEN Synthos Green Energy's 17 April 2023 page aims to build at least one BWRX-300 in Poland by 2030, without naming Warsaw, and says the seven locations would be analyzed over the next two years. No construction or operation date is given for Warsaw, so no revision is shown. OSGE: first locations presented

Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
Operator or intended licensed owner
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Assessments of the design (not of this site)

(2)
  • BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
    The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
    Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs
  • CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
    CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(5 notes, 1 not yet reviewed)
  • Evidence review. The OSGE page shows 17 April 2023 and lists Warszawa among seven potential BWRX-300 locations, with Ostrołęka, Włocławek, Stawy Monowskie, Dąbrowa Górnicza, Kraków-Nowa Huta and Stalowa Wola. It says implementation decisions come only after agreement, and that dialogue with residents will decide the final locations. The page does not name an operator, a module count, or an output for Warszawa. The Warszawa street address on the page is the company office, not a reactor plot. Stored operator OSGE is not supported and is not established in this source scope. OSGE remains the proposer, and BWRX-300 stays the named technology. Last checked 19 Oct 2026. OSGE: first locations presented
    What would change this

    A later OSGE decision that selects Warszawa, drops it, or records a decision in principle for this location. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed: Not disclosed in the reviewed evidence. Warszawa is one of seven potential locations. The page says final locations are decided later, after dialogue. That is not a disclosed reactor site. Last checked 19 Oct 2026. OSGE: first locations presented
    What would change this

    An OSGE decision that names a Warszawa plot or removes Warszawa from the potential list. Next scheduled check: 19 Jan 2027.

  • Permissions and public process. OSGE listed Warsaw among seven potential BWRX-300 locations in April 2023, saying local communities would be invited to dialogue once potential was confirmed. World Nuclear News reported that OSGE then applied for decisions in principle for six locations, omitting Warsaw, and the six decisions issued in December 2023 did not include it. No later permit step or consultation for Warsaw is shown in the sources reviewed. Last checked 23 Oct 2026. OSGE: first locations presented; Progress in environmental permitting of Polish SMR projects; OSGE six decisions in principle
    What would change this

    An OSGE statement on Warsaw, or a decision in principle application for a Warsaw location. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). OSGE's April 2023 release names only Warsaw as one of seven towns near which it would study building a first small unit, chosen as places with energy-intensive industry or district-heating needs. No plot, grid connection or cooling-water arrangement for a Warsaw location is identified in the sources reviewed. Last checked 23 Oct 2026. OSGE: first locations presented
    What would change this

    An OSGE announcement naming a Warsaw site. Next scheduled check: 23 Oct 2027.

  • Next decision and prerequisites. OSGE's April 2023 announcement says the company would spend the following two years analyzing in detail whether to build its first small reactor near seven localities, including Warsaw; its locations page says naming a location is not a decision to build, and the final decision follows those studies and public consultation. That two-year window has passed. OSGE's December 2023 decisions in principle, the first permit step, cover six other locations, not Warsaw. No later OSGE statement on Warsaw was found, so whether the Warsaw analysis continues is not recorded here. Last checked 23 Oct 2026. OSGE: first locations presented; Lokalizacje (planned locations and Q&A); OSGE six decisions in principle
    What would change this

    An OSGE statement about Warsaw, or an application or decision in principle for a Warsaw location, would change this answer. Next scheduled check: 23 Apr 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(1 of 4 sources with a publication or document date)
Latest dated listed source publication: Progress in environmental permitting of Polish SMR projects: 11 Feb 2025.Latest dated recorded event: no date recorded.3 of 4 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(4)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: OSGE Warsaw potential BWRX-300 location (2023 list) — https://smrmap.com/projects/osge-warszawa/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “OSGE Warsaw potential BWRX-300 location (2023 list)”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/osge-warszawa/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.