Projects / United States · Commissioning
Radiant Kaleidos demonstration at INL DOME
Radiant's Kaleidos Demonstration Unit is a planned 3.5 MWth test experiment in DOE's DOME test bed at Idaho National Laboratory, not a commercial plant or achieved output.
Current status
- How current
- General record check . Bounded evidence review . 6 of 14 listed sources have a publication or document date recorded here; the newest is 29 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Announced 29 Oct 2026 · Announcement: Radiant says DOE approved its Kaleidos safety analysis. Radiant says a DOE Readiness Review comes next, before nuclear operations can begin, with fuel loading and a test campaign to follow. Source: Radiant (29 Oct 2026): DOE approval of the Kaleidos Documented Safety Analysis (published 29 Oct 2026). Updates entry
More on this development
This is Radiant's account, and the DOE document was not opened. No date is given, and no startup or criticality is recorded.
- Next dated milestone
- No upcoming target date is recorded. Most recent target: Planned step: Jul–Sep 2026 (target). Radiant target: 150-hour continuous full-power run at DOME. Date passed; not recorded as met. Source: radiantnuclear.com: Kaleidos reactor ships from El Segundo to INL (published 12 Aug 2026).
- Selected limitations
- Electrical output is not recorded.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions); Construction start evidence (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions); Operation or grid target (type stated) (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
- Same design
- 4 tracked: 1 commissioning, 1 siting, 2 announced. 5 tracked at commissioning across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- High-temperature gas-cooled reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
A March 2026 NRIC presentation gave fuel loading, criticality and operation dates as plans; those dates do not prove the steps occurred. DOE conditionally selected Radiant for the first DOME tests on 1 July 2025 and said the company was working through DOE's multi-phase authorization process. Radiant announced on 9 February 2026 that DOE approved its preliminary safety-analysis equivalent, but the DOE approval document was not opened. DOE reported on 8 April 2026 that DOME was complete and that Radiant had started its scheduled year-long test campaign, with initial startup anticipated in the summer. INL’s 30 September 2026 release, in the text KIFI reproduced, reports that Radiant completed the first DOME test. It supplies no completion day, achieved power or scope of completion. Radiant said on 29 October 2026 that DOE had approved its Documented Safety Analysis and that DOE's Readiness Review is the next step before nuclear operations can begin, with fuel loading and a five-phase test campaign, from first criticality to at least 150 hours at full power, to follow a successful review. That is Radiant's account, the DOE approval document was not opened, and the release gives no date for the review, fuel loading or criticality. Read with Radiant's statement, the campaign DOE said had started in April 2026 and the test INL said was completed in September 2026 came before any fuel loading or criticality; neither source states what those steps covered. No final DOE experiment authorization or dated startup or criticality evidence was established; Commissioning is retained. DOE's DOME pages use the word commercial for later licensing of developers' reactors. They do not give Kaleidos a commercial-operation date. DOE's 23 July 2026 HALEU announcement says Radiant previously received HALEU to support the Kaleidos demonstration reactor. Radiant says DOE's earlier HALEU allocation supports the Kaleidos Development Unit test and that Standard Nuclear fabricated the TRISO fuel in Oak Ridge. DOE says applicants fund their own DOME test campaigns. Radiant's earlier target of a 150-hour full-power run in the third quarter of 2026 has passed; its 29 October release still places that run at the end of the campaign and gives no new date.
Key facts
- Design
- Kaleidos (Microreactor)
- Technology
- High-temperature gas-cooled reactor (HTGR) · helium
- Operator(s)
- Not recorded
- Vendor for linked design
- Radiant Industries
- Location
- DOME test bed, Idaho National Laboratory · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
DOE identifies DOME as the repurposed EBR-II containment. This reuses the recorded OpenStreetMap building center 43.59507,−112.65716. The shared facility point is approximate and does not separate reactor positions or establish permission. - Coordinates
- 43.59507, -112.65716 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: module
DOE's July 2026 update lists the Kaleidos Development Unit at 3.5 MWt. - Thermal capacity
- 3.5 MWth (nameplate; basis unspecified)
- Purpose
- Research or test reactor
- Construction start
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Could not be confirmed on . Attempted official source: DOE: Energy Department to Distribute Third Round of HALEU to NASA and Radiant. This is an access or status observation only; the record review date is unchanged.
Site and capacity notes
Radiant Kaleidos demonstration at INL DOME is recorded at DOME test bed, Idaho National Laboratory, Idaho, United States. Operator: No operator is recorded. Recorded vendor: Radiant Industries. Stage: Commissioning. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: building center of the EBR-II containment (DOME) at the Materials and Fuels Complex, 43.59507, −112.65716
Electrical output is not recorded on this project. DOE's July 2026 update lists the Kaleidos Development Unit at 3.5 MWt. Modules planned: 1. Recorded thermal output is 3.5 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Reactor supplier
- Vendor for the linked designRadiant Industries
- Funding and government decisions
Source-backed project statement DOE's 1 July 2025 article says DOME testing campaigns are self-funded by the applicants, and its 8 April 2026 article lists the ability to self-fund as a sequencing criterion. Radiant is therefore stated to fund its own Kaleidos test campaign. No amount is given. DOE: Energy Department Announces First Microreactor Experiments in DOME Test Bed
- Fuel
- Fuel supplier named for this projectStandard Nuclear · sourceFabricated the TRISO fuel to Radiant's specifications; first tranche received at DOME on 1 July 2026.
- Fuel supplier named for this projectU.S. Department of Energy · sourceDOE says Radiant previously received HALEU to support Kaleidos (stated 23 July 2026).
- Fuel form stated for KaleidosTRISO
- Enrichment stated for Kaleidos19.75%
Source-backed project statement
Radiant's 1 July 2026 release says it received its first tranche of TRISO fuel at the DOME facility, fabricated by Standard Nuclear in Oak Ridge to Radiant's specifications for the Kaleidos reactor. DOE said on 23 July 2026 that Radiant had previously received HALEU to support Kaleidos. Fuel loading is not confirmed in the sources read. radiantnuclear.com: Radiant receives first TRISO fuel tranche at INL's DOME facility; DOE: Energy Department to Distribute Third Round of HALEU to NASA and Radiant
- Site host or owner
- Site hostIdaho National Laboratory · source
- Programs and agreements naming the project
- Customer agreement; status not establishedIdaho Strategic Resources and Radiant memorandum on Kaleidos microreactors at a mine site (2024)
- Government program; activeDOE Reactor Pilot Program (DOE-authorized advanced test reactors)
Not found in the sources we checked (3): Customer or offtaker; Contractor; Comparable schedule revision
- Customer or offtaker
DOE's July 2025 and April 2026 articles describe the Kaleidos Demonstration Unit as a self-funded test campaign in DOE's DOME test bed at Idaho National Laboratory. They name no buyer of its electricity or heat, and DOE's pages use the word commercial only for later licensing of developers' reactors. DOE: World's First Microreactor Test Bed Now Open for Business
- Contractor
DOE's July 2025 selection article and April 2026 opening article describe Radiant testing its Kaleidos unit in DOME, a DOE test bed at Idaho National Laboratory. They name no engineering or construction contractor for the Kaleidos demonstration, and INL is recorded as the site host. DOE: Energy Department Announces First Microreactor Experiments in DOME Test Bed
- Comparable schedule revision
Comparable schedule revision not established. DOE said on 1 July 2025 that DOME's first fueled reactor experiment would start as early as spring 2026, without naming which developer, and on 8 April 2026 that Kaleidos's initial startup was anticipated in the summer. The 2025 statement is an earliest date, not a target that the 2026 statement moves, and the record's events hold no revision pair. DOE: Energy Department Announces First Microreactor Experiments in DOME Test Bed; DOE: World's First Microreactor Test Bed Now Open for Business
Not recorded in SMRMap's reviewed evidence (2): Project proposer or applicant; Operator or intended licensed owner
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Operator or intended licensed owner
- Reviewed 19 Oct 2026: not disclosed in the reviewed evidence.
Timeline
Recorded developments
- Announced · Announcement
Radiant says DOE approved its Kaleidos safety analysis - Published · Announcement
INL reports Radiant completed the first DOME test - · Recorded development
Radiant's Kaleidos reactor ships from El Segundo to INL - · Recorded development
Radiant receives first TRISO fuel tranche at INL's DOME facility - · Recorded development
DOME test bed complete; Radiant begins its test campaign
Earlier developments (2)
- Announced · Announcement
Radiant announces DOE approval of the Kaleidos authorization request (DARK) - · Recorded development
DOE conditionally selects Radiant for the first DOME tests
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step · Date passed; not recorded as met
Radiant target: 150-hour continuous full-power run at DOME
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(11 notes)
- Evidence review. Radiant's Kaleidos Development Unit is a test reactor in DOE's DOME test bed at Idaho National Laboratory. DOE's July 2026 pilot-program slides list it as a 3.5 MWt micro high-temperature gas reactor. NRIC's March 2026 slides give 3.5 MW(th) under DOE authorization. DOE's 1 July 2025 announcement says the test is meant to advance Radiant's commercial 1.2 MWe design, and Radiant calls Kaleidos a 1 MWe microreactor. Those are design descriptions, not achieved or authorized test output. DOE made Radiant a conditional selection on 1 July 2025 and said it was working through DOE's multi-phase authorization process. On 9 February 2026 Radiant announced DOE approval of its authorization request, written to meet the intent of a preliminary documented safety analysis. It said the final safety analysis, readiness review, authorization and startup would follow. DOE reported on 8 April 2026 that the DOME test bed was complete and Radiant had started a year-long campaign, with startup expected in the summer. Radiant received its first fuel tranche at DOME on 1 July 2026, which is fuel receipt, not fuel loading. The reactor left El Segundo for INL on 12 to 13 August 2026, with fuel to be loaded under DOE and INL oversight. Radiant's plan is zero-power criticality, then 1 MWt, then full power, then a 150-hour full-power run targeted for the third quarter of 2026. INL's 30 September 2026 release, reproduced by KIFI, says Radiant completed the first-ever DOME test. It gives no date, power level, criticality or scope. No opened source shows the final DOE authorization, fuel loading, criticality, full power or the 150-hour run. No source names who operates the reactor. NRIC operates the DOME facility. The summer startup and third-quarter targets have passed without a published result. The stored 3.5 MWth and empty operator list match the sources. Last checked 19 Oct 2026. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); NRIC presentation on DOME and reactor demonstrations (5 March 2026); DOE: Energy Department Announces First Microreactor Experiments in DOME Test Bed; Radiant (9 Feb 2026): Radiant receives DOE approval of Preliminary Documented Safety Analysis; DOE: World's First Microreactor Test Bed Now Open for Business; radiantnuclear.com: Radiant receives first TRISO fuel tranche at INL's DOME facility; radiantnuclear.com: Kaleidos reactor ships from El Segundo to INL; KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME; INL: Deployable Energy selected to test its nuclear battery at DOME
What would change this
A DOE, INL or Radiant statement dating Kaleidos fuel loading, criticality or full-power operation, or publishing the DOE startup authorization. Next scheduled check: 19 Jan 2027.
- Plant capacity (scope qualified). DOE's July 2026 update lists the Kaleidos Development Unit at 3.5 MWt. It is one test unit, so the unit rating is the project figure. The 1.2 MWe value is DOE's description of Radiant's commercial design, not an achieved or authorized test output. Last checked 18 Oct 2026. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212)
What would change this
DOE, INL or Radiant reports the power reached in the DOME test. Next scheduled check: 18 Jan 2027.
- Module/unit count. One Kaleidos test unit was shipped to INL's DOME for the test campaign. Last checked 18 Oct 2026. radiantnuclear.com: Kaleidos reactor ships from El Segundo to INL
What would change this
A second Kaleidos unit is announced for DOME. Next scheduled check: 18 Jan 2027.
- Permission evidence appropriate to stage: Not disclosed in the reviewed evidence. Kaleidos is tested under DOE authorization, not an NRC license. DOE said on 1 July 2025 that Radiant was working through the multi-phase DOE authorization process. Radiant announced on 9 February 2026 that DOE approved its authorization request, written to meet the intent of a preliminary documented safety analysis. It said a final safety analysis, readiness review and authorization would precede startup. Radiant said on 29 October 2026 that DOE approved its Documented Safety Analysis and that DOE's Readiness Review comes next, before nuclear operations can begin. No opened DOE or INL document shows that approval or an authorization for fuel loading, startup or criticality. INL's 30 September 2026 report that Radiant completed the first DOME test does not identify the authorization. Direct reads of the INL release returned an access refusal (HTTP 403) or a block page, a browser read on 13 October 2026 kept no copy, and the retained text is KIFI's reproduction. Last checked 3 Nov 2026. DOE: Energy Department Announces First Microreactor Experiments in DOME Test Bed; Radiant (9 Feb 2026): Radiant receives DOE approval of Preliminary Documented Safety Analysis; KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME; INL: Deployable Energy selected to test its nuclear battery at DOME; Radiant (29 Oct 2026): DOE approval of the Kaleidos Documented Safety Analysis
What would change this
DOE or INL publishes the Kaleidos final safety analysis approval, or DOE, INL or Radiant reports the Readiness Review result or a startup authorization. Next scheduled check: 19 Jan 2027.
- Operator or intended licensed owner: Not disclosed in the reviewed evidence. DOE gave Radiant use of DOME for the test campaign, and NRIC operates the DOME facility. Radiant says fuel will be loaded under DOE and INL oversight. No opened source names who operates the Kaleidos reactor during the DOME test, so operator_ids stays empty. INL is stored as site host. Last checked 19 Oct 2026. radiantnuclear.com: Kaleidos reactor ships from El Segundo to INL; DOE: World's First Microreactor Test Bed Now Open for Business; DOE: Energy Department Announces First Microreactor Experiments in DOME Test Bed
What would change this
A DOE, INL or Radiant document names the Kaleidos operator in DOME. Next scheduled check: 19 Jan 2027.
- Construction start evidence: Not disclosed in the reviewed evidence. Kaleidos was factory-built in El Segundo and left for INL around 12 to 13 August 2026. DOE reported the DOME test bed complete on 8 April 2026. That is facility readiness, not reactor construction. No opened source dates the start of reactor fabrication or the installation of Kaleidos in DOME. Last checked 19 Oct 2026. radiantnuclear.com: Kaleidos reactor ships from El Segundo to INL; DOE: World's First Microreactor Test Bed Now Open for Business
What would change this
Radiant or INL dates the installation of Kaleidos in DOME. Next scheduled check: 19 Jan 2027.
- Operation or grid target (type stated): Not disclosed in the reviewed evidence. DOE expected initial startup in summer 2026. Radiant expected startup that summer and targeted a 150-hour continuous full-power run in the third quarter of 2026. Both dates have passed with no published startup, criticality or full-power result. INL reported on 30 September 2026 that Radiant completed the first DOME test, with no date, power or scope. Radiant's 29 October 2026 release places fuel loading after a DOE Readiness Review still to come, so by its account the reactor had not started up by then, and says the campaign will end with at least 150 hours at full power; it gives no date for either. No current dated target is published. Last checked 3 Nov 2026. radiantnuclear.com: Kaleidos reactor ships from El Segundo to INL; DOE: World's First Microreactor Test Bed Now Open for Business; KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME; Radiant (29 Oct 2026): DOE approval of the Kaleidos Documented Safety Analysis
What would change this
DOE, INL or Radiant reports Kaleidos criticality, full power or the 150-hour run, or gives a new target. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The September 2026 INL release, as carried by KIFI, says Deployable Energy will be the second company to test in DOME after the first test completed by Radiant, without giving a date, power level or scope. Radiant's July 2026 plan was a five-phase campaign ending in at least 150 hours at full power without operator intervention. These sources do not show that the full-power run happened; the next public step is Radiant or DOE reporting the campaign result and the reactor's removal. Last checked 23 Oct 2026. KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME; radiantnuclear.com: Radiant receives first TRISO fuel tranche at INL's DOME facility
What would change this
A Radiant, INL or DOE report of the Kaleidos full-power run result or of the unit's defuelling and removal from DOME. Next scheduled check: 23 Jan 2027.
- Permissions and public process. The Kaleidos test runs under DOE authorization, not an NRC license: a March 2026 NRIC presentation lists its license authority as DOE Authorization, and Radiant said on 9 February 2026 that DOE approved its DOE Authorization Request for Kaleidos, meant to meet the intent of a preliminary documented safety analysis. The same presentation lists the final safety analysis as due to DOE-Idaho on 31 March 2026, but the read sources do not show its approval or any public comment process. Last checked 23 Oct 2026. NRIC presentation on DOME and reactor demonstrations (5 March 2026); Radiant (9 Feb 2026): Radiant receives DOE approval of Preliminary Documented Safety Analysis
What would change this
A DOE or INL document confirming approval of the Kaleidos documented safety analysis or authorization to operate. Next scheduled check: 23 Jan 2027.
- Site dependencies (land, grid, water). The test bed is DOE's DOME facility at Idaho National Laboratory, which a March 2026 NRIC presentation says repurposes the former EBR-II reactor structure for microreactor experiments up to 20 MWth. DOE said on 8 April 2026 that DOME construction was complete and that it would open first to Radiant. These sources describe the host building, not any grid export, water supply or land arrangement specific to the Kaleidos unit. Last checked 23 Oct 2026. NRIC presentation on DOME and reactor demonstrations (5 March 2026); DOE: World's First Microreactor Test Bed Now Open for Business
What would change this
DOE or INL publication describing Kaleidos's power output use or site services at DOME. Next scheduled check: 23 Jan 2027.
- Spent fuel, waste and closure. A March 2026 NRIC presentation on the DOME test bed shows the planned end-of-test path: after shutdown the reactor goes to a future cooldown pad labeled RSWF, is defuelled and disposed of, and used fuel is stored at RSWF and then in INL facility CPP-651. This is the test bed's planned process shown beside the Kaleidos slide, not a signed Radiant contract, and the presentation does not say who funds disposal. Last checked 23 Oct 2026. NRIC presentation on DOME and reactor demonstrations (5 March 2026)
What would change this
A DOE or Radiant statement that Kaleidos has been defuelled and its used fuel transferred, or a document assigning those costs. Next scheduled check: 23 Jan 2027.
Evidence dates
(6 of 14 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(14)
- KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME (news report, accessed 2 Oct 2026)
- DOE: Energy Department Announces First Microreactor Experiments in DOME Test Bed (government, accessed 5 Oct 2026)
- DOE: World's First Microreactor Test Bed Now Open for Business (government, accessed 5 Oct 2026)
- DOE: One Year After Executive Orders, U.S. Nuclear Energy Renaissance Is in Full Swing (government, accessed 5 Oct 2026)
- NRIC presentation on DOME and reactor demonstrations (5 March 2026) (government, accessed 9 Oct 2026)
- Radiant (9 Feb 2026): Radiant receives DOE approval of Preliminary Documented Safety Analysis (company, accessed 8 Oct 2026)
- INL: Deployable Energy selected to test its nuclear battery at DOME (government, published 30 Sep 2026, accessed 13 Oct 2026)
- DOE: Energy Department to Distribute Third Round of HALEU to NASA and Radiant (government, published 23 Jul 2026, accessed 30 Oct 2026)
- Radiant: DOE Selects Radiant for Second HALEU Allocation (company, published 23 Jul 2026, accessed 18 Oct 2026)
- radiantnuclear.com: Radiant receives first TRISO fuel tranche at INL's DOME facility (company, published 1 Jul 2026, accessed 14 Oct 2026)
- DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212) (government, accessed 15 Oct 2026)
- radiantnuclear.com: Kaleidos reactor ships from El Segundo to INL (company, published 12 Aug 2026, accessed 14 Oct 2026)
- Radiant: News index (company, accessed 18 Oct 2026)
- Radiant (29 Oct 2026): DOE approval of the Kaleidos Documented Safety Analysis (company, published 29 Oct 2026, accessed 2 Nov 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Radiant Kaleidos demonstration at INL DOME — https://smrmap.com/projects/radiant-kaleidos-inl/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Radiant Kaleidos demonstration at INL DOME”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-15. https://smrmap.com/projects/radiant-kaleidos-inl/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.