Projects / Uzbekistan · Construction

RITM-200N Jizzakh

Revised March 2026 program combines two 55 MWe RITM-200N units with separate large VVER units.

Current status

Stage
Construction
How current
General record check . Bounded evidence review . 5 of 11 listed sources have a publication or document date recorded here; the newest is 5 Jun 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Recorded: License for construction of an NPP power unit with a RITM-200N reactor (4 Jun 2026); Permit to use the site for nuclear installations (Farish district NPP site) (23 Mar 2026). No operating license or other operating authority is recorded as issued. All permissions and applications
Latest development
4 Jun 2026 · First concrete: First concrete poured for Uzbekistan's first RITM-200N unit. Uzbekistan's atomic energy agency says first concrete was poured into the first SMR unit's foundation on 4 June 2026, after the regulator decided to license its construction. Source: Uzatom: Historic start - construction of the integrated nuclear power plant begins in Uzbekistan (4 June 2026) (published 4 Jun 2026); World Nuclear News: Ceremony to mark first concrete for Uzbekistan SMR (5 June 2026) (published 5 Jun 2026). Updates entry
More on this development

This covers the first SMR unit only; the second unit has no reported construction license.

Next dated milestone
First criticality: 2029 (target). First criticality of first RITM-200N unit (expected late 2029). This is not an achieved milestone. Source: WNA: Nuclear power in Uzbekistan.
Selected limitations
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • The mapped point is not an exact surveyed coordinate.
  • Expected for this stage but not recorded as a structured fact: Operation or grid target (type stated) (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
Same design
3 tracked: 1 construction, 1 licensing, 1 announced. 13 tracked at construction across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Integral pressurized water reactor. How it works, with a 3D view.
Schematic of CAREM-25, this type's example. A single pressure vessel holds the core below helical steam generators, with a steam dome at the top.
Schematic of CAREM-25, this type's example.

Description

This row covers the SMR component only. A September 2025 agreement confirmed two RITM-200N units (alongside two large VVER-1000 units, which are outside scope). The supplementary agreement of 24 March 2026 fixes two 1,000 MW units and two 55 MW small units at the Farish district site, following the placement scheme approved in May 2025. Uzbekistan's regulator names a state construction directorate as the submitter of the project documentation; Rosatom is the vendor. The regulator issued site permission on 23 March 2026 and decided on 4 June 2026 to issue a construction license for one RITM-200N unit; its notice gives no license number or holder. Uzatom says the license was issued to the state institution Directorate for the Construction of the Nuclear Power Plant, while World Nuclear News says it went to the general contractor. Concrete bedding under the reactor building in March and April 2026 was preparatory work. At a ceremony on 4 June 2026, Uzatom reports, first concrete (133 cubic metres at the initial stage) was poured for the foundation of the first unit. The recorded stage is construction for the first RITM-200N unit; the second has no reported construction license. No source names the future operator.

Key facts

Design
RITM-200N (SMR)
Technology
Integral pressurized water reactor (iPWR) · light water
Reactor vessel of this design
7.5 m tall, 3.4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 71.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Operator(s)
Not recorded
Vendor for linked design
Rosatom
Design origin
Russia: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
Location
Jizzakh RITM-200N site · Uzbekistan · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for Jizzakh unit 1 (RITM-200N, construction) in Farish district (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); plant-area point, not a surveyed plot. Replaces an earlier Jizzakh city-center point about 87 km away.
Coordinates
40.708423, 67.158426 · site-area point (approximate)
Electrical capacity
55 MWe (gross/net unspecified) · scope: module
Thermal capacity
Not recorded
Modules planned
2
Purpose
Power plant
Construction start
4 Jun 2026First concrete poured for the foundation of the first RITM-200N unit (Uzatom)
Inclusion basis
SMR by design class
Confidence
medium
Record reviewed
18 Oct 2026Evidence review 20 Oct 2026. How current names both.

Could not be confirmed on . Attempted official source: Uzatom: First concrete works begin at the site of the first NPP (24 March 2026). This is an access or status observation only; the record review date is unchanged.

Site and capacity notes

RITM-200N Jizzakh is recorded at Jizzakh RITM-200N site, Jizzakh Region, Uzbekistan. Operator: No operator is recorded. Recorded vendor: Rosatom. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'jizzakh-nuclear-power-plant-1' (40.708423, 67.158426)

Recorded electrical output is 55 MWe (gross/net unspecified), scope module. Modules planned: 2. Thermal output is not recorded on this project. The linked design record states 190 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Reactor supplier
  • Vendor for the linked designRosatom
Contractor
  • Construction contractorAtomstroyexport · sourceConstruction contract signed 27 May 2024 with Uzatom's Directorate for the Construction of Nuclear Power Plants; Rosatom named general contractor.
Source-backed project statement

Uzatom's 24 March 2026 account says the Directorate and Atomstroyexport, Rosatom's engineering division, signed a contract on 27 May 2024 to build a small nuclear plant in Jizzakh region. The same account says a later agreement sets two RITM-200N units of 55 MW each beside two large units. The 2024 contract is a construction contract for the small-plant project, and the page does not restate its price after the configuration change. Uzatom: First concrete works begin at the site of the first NPP (24 March 2026)

Funding and government decisions

Source-backed project statement World Nuclear News on 5 June 2026 reported President Putin's statement that Russia would provide a preferential export loan for the plant and support it through its lifecycle. That is an announced commitment at the first-unit ceremony, not a record of money paid. The report does not limit the loan to the RITM-200N units. World Nuclear News: Ceremony to mark first concrete for Uzbekistan SMR (5 June 2026)

Fuel
Project fuel information is described in the source-backed statement below.

Source-backed project statement World Nuclear News on 5 June 2026 reported a Russian commitment, stated at the ceremony, to long-term reactor fuel supplies for the plant. The Uzatom and regulator pages reviewed do not name a fuel manufacturer, a delivery, or a loading for the RITM-200N unit. The reported commitment is not shown as a signed fuel contract. World Nuclear News: Ceremony to mark first concrete for Uzbekistan SMR (5 June 2026); Uzatom: Historic start - construction of the integrated nuclear power plant begins in Uzbekistan (4 June 2026)

Not found in the sources we checked (2): Customer or offtaker; Comparable schedule revision
Customer or offtaker

The Uzatom accounts of 24 March 2026 and 4 June 2026 describe the Farish plant as an integrated nuclear station and name no electricity buyer for the RITM-200N units. A national-supply purpose for the combined station is not an offtake. The two large units named in the March agreement are outside this row. Uzatom: First concrete works begin at the site of the first NPP (24 March 2026); Uzatom: Historic start - construction of the integrated nuclear power plant begins in Uzbekistan (4 June 2026)

Comparable schedule revision

Comparable schedule revision not established. World Nuclear News on 5 June 2026 recalls that the first unit of the original six-unit RITM-200N plan was scheduled to go critical in late 2029. Uzatom's 24 March 2026 configuration text states two RITM-200N units and two large units and does not restate a criticality date. The texts do not contain two forecasts of the same milestone for the same unit. World Nuclear News: Ceremony to mark first concrete for Uzbekistan SMR (5 June 2026); Uzatom: First concrete works begin at the site of the first NPP (24 March 2026)

Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
Operator or intended licensed owner
Reviewed 20 Oct 2026: not disclosed in the reviewed evidence.
Site host or owner
Programs and agreements naming the project

Timeline

Recorded developments

Targets

Planned, target and estimated dates are not achievements or commitments.

Permissions and applications

Site applications and decisions

Construction applications and decisions

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(8 notes)
  • Evidence review. Rosatom describes two RITM-200N SMR units of 55 MW each in the Jizzakh project alongside two VVER-1000 units that are outside this record. Uzbekistan’s regulator announced a construction-license decision for a RITM-200N unit on 4 June 2026. Uzatom and press coverage report first concrete for the first SMR unit; March concrete works were preparatory. The reported construction-license holder differs between Uzatom’s statement and WNN’s account, so that role remains unresolved. The supplied sources do not identify the future operator. The 55 MW source does not state electrical/thermal or gross/net basis. The accepted historical schedule review remains: late 2029 is a first-criticality expectation, not a commercial-operation or grid-connection date. Last checked 20 Oct 2026. Rosatom March 2026 Uzbekistan configuration; Uzbekistan regulator: RITM-200N construction-licence decision, 4 June 2026; World Nuclear News: Ceremony to mark first concrete for Uzbekistan SMR (5 June 2026); WNA: Nuclear power in Uzbekistan
    What would change this

    A copy of the issued construction license naming its holder, or a regulator notice for the second unit or an operating license. Next scheduled check: 20 Jan 2027.

  • Plant capacity (scope qualified): Not disclosed in the reviewed evidence. Rosatom's 27 May 2024 announcement identifies the RITM-200N design rating as 55 MW electrical and 190 MW thermal per reactor, without a gross/net basis. Its six-reactor, 330 MW proposal predates the recorded two-unit SMR configuration and does not establish that configuration's plant total. The recorded 55 MWe remains a per-module rating; no plant total is calculated. Last checked 26 Oct 2026. Atom Media: Russian Federation and Uzbekistan sign contract for small nuclear power plant construction; Rosatom March 2026 Uzbekistan configuration
    What would change this

    A project or regulator document stating the current two-unit SMR plant total and its electrical/thermal and gross/net basis. Next scheduled check: 20 Jan 2027.

  • Operator or intended licensed owner: Not disclosed in the reviewed evidence. The attached project and license accounts name a construction-document submitter and contractor but do not identify the future reactor operator. Last checked 20 Oct 2026. Uzbekistan regulator: RITM-200N construction-licence decision, 4 June 2026
    What would change this

    A regulator license or project statement naming the reactor operator. Next scheduled check: 20 Jan 2027.

  • Operation or grid target (type stated): Not disclosed in the reviewed evidence. The World Nuclear Association Uzbekistan profile expects first criticality of the first RITM-200N unit in late 2029, and it gives 2033 and 2035 as commissioning years for the two VVER-1000 units, which are outside this row. World Nuclear News on 5 June 2026 says the first unit of the earlier six-unit plan was scheduled to go critical in late 2029, with units commissioned one by one, and states no year for commercial operation or grid connection. The late-2029 criticality target is already stored. No commercial-operation or grid-connection date is stored. Last checked 19 Oct 2026. WNA: Nuclear power in Uzbekistan; World Nuclear News: Ceremony to mark first concrete for Uzbekistan SMR (5 June 2026)
    What would change this

    A Uzatom, Rosatom or regulator statement giving a dated commercial-operation or grid-connection target for a RITM-200N unit. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. The 4 June 2026 license and first-concrete ceremony are described for one RITM-200N unit. Uzatom's March account sets the small-plant configuration at two RITM-200N units, and these pages do not report a construction license for the second unit. The March concrete preparation is a separate, earlier bedding step and is not the June foundation pour. Last checked 23 Oct 2026. Uzatom: Historic start - construction of the integrated nuclear power plant begins in Uzbekistan (4 June 2026); Uzatom: First concrete works begin at the site of the first NPP (24 March 2026)
    What would change this

    A regulator decision on a construction license for the second Farish RITM-200N unit. Next scheduled check: 21 Jan 2027.

  • Permissions and public process: Sources conflict. Uzatom's 4 June 2026 government account names the state Directorate for nuclear plant construction as holder of the construction license for one RITM-200N unit. World Nuclear News on 5 June instead names the general contractor. The regulator's notice confirms a decision to issue the one-unit license but does not name its holder. The government account is the stronger attribution; the press discrepancy concerns the holder, not whether the regulator announced the license decision. The license instrument itself has not been examined. Last checked 23 Oct 2026. Uzatom: Historic start - construction of the integrated nuclear power plant begins in Uzbekistan (4 June 2026); Uzbekistan regulator: RITM-200N construction-licence decision, 4 June 2026; World Nuclear News: Ceremony to mark first concrete for Uzbekistan SMR (5 June 2026)
    What would change this

    The construction-license instrument naming its holder and number for the first RITM-200N unit. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water). Uzatom's 24 March 2026 account says the Directorate received permission to use the site for two RITM-200N units in Farish district, and the 4 June account says a site-use permission was issued on 23 March. Those are siting permissions, not a land title. The pages do not state a grid-connection agreement or a water right. Last checked 23 Oct 2026. Uzatom: First concrete works begin at the site of the first NPP (24 March 2026); Uzatom: Historic start - construction of the integrated nuclear power plant begins in Uzbekistan (4 June 2026)
    What would change this

    A land title, grid agreement, or water right for the Farish site. Next scheduled check: 21 Jan 2027.

  • Spent fuel, waste and closure. World Nuclear News on 5 June 2026 reported a Russian commitment, stated at the ceremony, to spent nuclear material management as part of lifecycle support. The Uzatom and regulator pages do not name a store, a contract, or a closure plan for the RITM-200N unit. The reported commitment is not a reviewed waste contract. Last checked 23 Oct 2026. World Nuclear News: Ceremony to mark first concrete for Uzbekistan SMR (5 June 2026)
    What would change this

    A contract or regulator document naming spent-fuel storage or disposal for the RITM-200N unit. Next scheduled check: 21 Jan 2027.

Evidence dates

(5 of 11 sources with a publication or document date)
Latest dated listed source publication: World Nuclear News: Ceremony to mark first concrete for Uzbekistan SMR (5 June 2026): 5 Jun 2026.Latest dated recorded event: First concrete poured for the foundation of the first RITM-200N unit (Uzatom): 4 Jun 2026.6 of 11 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(11)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: RITM-200N Jizzakh — https://smrmap.com/projects/ritm-200n-jizzakh/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “RITM-200N Jizzakh”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/ritm-200n-jizzakh/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.