RITM-200N
Land-based derivative of the RITM-200 marine PWR. For the Uzbekistan deployment, the nuclear regulator's 4 June 2026 announcement records a decision to issue a construction license for a unit using RITM-200N. That site-specific licensing step does not establish the start of nuclear construction or permission to operate.
- Reactor type
- Integral pressurized water reactor. How it works, with a 3D view.
- Projects
- Construction: RITM-200N Jizzakh. Furthest recorded stage of 3 using this design.
- Evidence
- 3 sources; first primary source: Uzbekistan regulator: RITM-200N construction-licence decision, 4 June 2026. Record reviewed 1 Oct 2026.
Key facts · Tracked projects · Agreements · Sources · Evidence · Regulatory actions · Its projects in the table · Compare with other designs
Key facts
- Class
- SMR
- Technology
- Integral pressurized water reactor (iPWR)
- Coolant
- Light water
- Spectrum
- Thermal
- Developer / vendor(s)
- Rosatom
- Module electrical
- 55 MWe (gross)
- Module thermal
- 190 MWth (nameplate; basis unspecified)
- Reactor vessel
- 7.5 m tall, 3.4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 71.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.All vessels to scale10 m bar; a person 1.8 m tallRITM-200N
7.5 m tall, 3.4 m across - Inclusion basis
- SMR by design class
- Confidence
- low
- Record reviewed
- 1 Oct 2026 (record review date, not proof of current availability or a deployment)
Tracked deployment projects
- RITM-200N Jizzakh — Construction · Uzbekistan
- Yakutia land-based RITM-200N (Ust-Kuyga) — Licensing · Russia
- Myanmar 110 MW SMR project (two RITM-200N; site not named) — Announced · Myanmar
Agreements naming this design (1)
Agreements, plans, studies and government programs whose sources name this design. They are not deployment projects.
- Kyrgyzstan and Rosatom small nuclear power plant memorandum and RITM-200N pre-feasibility work — Cooperation agreement or MOU · Active · announced 2022
Concerns Kyrgyzstan
Design sources
(3)
- Nuclear News Network — SMRs explained (news report, accessed 1 Oct 2026)
- World Nuclear Association — Small Nuclear Power Reactors (directory or tracker, accessed 1 Oct 2026)
- Uzbekistan regulator: RITM-200N construction-licence decision, 4 June 2026 (regulator, published 4 Jun 2026, accessed 14 Oct 2026)
Evidence and open questions
(1 note)
- Evidence review. Nuclear News Network's secondary explainer (9 July 2026, status table dated September 2026) lists Rosatom as developer of the KLT-40S, RITM-200N and BREST-OD-300 with outputs 35 MWe x2, 55 MWe and 300 MWe respectively, and reports RITM-200N civil works in Yakutia and at Jizzakh, Uzbekistan, the first export RITM-200N; it gives no reactor type, coolant, spectrum, thermal rating or gross/net basis. Uzbekistan's nuclear and radiation safety committee announced on 2026-06-04 that its Council decided to issue a license to construct an NPP power unit with the RITM-200N reactor installation, after a site-use permission issued on 23 March 2026; these are site-specific licensing steps for the Jizzakh project, not a design certification and not permission to operate. Deployment links supported: Jizzakh (regulator and NNN) and Yakutia (NNN, secondary); no opened source names the Myanmar project. The WNA SMR page (updated 1 October 2026) no longer names the RITM-200N. Stored vendor and 55 MWe stay supported (basis unspecified in sources); the stored iPWR family, light-water coolant, thermal spectrum, 'gross' basis and 190 MWth are not stated by any opened source and rest on earlier evidence. Last checked 19 Oct 2026. Nuclear News Network — SMRs explained; Uzbekistan regulator: RITM-200N construction-licence decision, 4 June 2026
What would change this
A primary Rosatom or IAEA design description of RITM-200N (for example the next IAEA SMR catalog edition or an ARIS record) to re-support the integral PWR, light-water, thermal-spectrum, 190 MWth and gross-basis fields; or Uzbek regulator notice of first nuclear concrete at Jizzakh. Next scheduled check: 19 Jan 2027.
Regulatory actions
Compare reviews and approvals across designs
Site applications and decisions
- Permit to use the site for nuclear installations (Farish district NPP site) — RITM-200N Jizzakh
Site permission · Issued / approved · Committee for Industrial, Radiation and Nuclear Safety under the Cabinet of Ministers of the Republic of Uzbekistan · decided 23 Mar 2026
Regulator's own news item dated 4 June 2026 states the permit was issued on 23 March 'of the current year'. The notice reports permission to use the site designated for nuclear installations for NPP construction. It does not give a permit number.
Sources: Uzbekistan regulator: RITM-200N construction-licence decision, 4 June 2026
Construction applications and decisions
- License for construction of an NPP power unit with a RITM-200N reactor — RITM-200N Jizzakh
Construction permission · Issued / approved · Committee for Industrial, Radiation and Nuclear Safety under the Cabinet of Ministers of the Republic of Uzbekistan · decided 4 Jun 2026
Council of the Committee decided 'today' (item dated 2026-06-04) to issue the license for construction of one power unit (singular 'энергоблока'); the Committee's notice states no license number or holder. Uzatom states that the license was issued to the state institution Directorate for the Construction of the Nuclear Power Plant; the license number is not published.
Sources: Uzbekistan regulator: RITM-200N construction-licence decision, 4 June 2026; Uzatom: Historic start - construction of the integrated nuclear power plant begins in Uzbekistan (4 June 2026)