Rolls-Royce SMR Tušimice candidate location

Tušimice in Czechia is a named candidate location in the ČEZ / Rolls-Royce SMR partnership, at the siting stage.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . 2 of 8 listed sources have a publication or document date recorded here; the newest is 22 Dec 2025. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
Announced 21 Jul 2026 · Announcement: Rolls-Royce SMR Tušimice candidate location proposal documented. Named location under study in the ČEZ / Rolls-Royce SMR partnership. Source: ČEZ additional Czech SMR locations. Updates entry
More on this development

Site selection studies and a proposal do not establish construction or a committed unit count.

Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • The mapped point is not an exact surveyed coordinate.
  • State or province is not recorded.
Same design
6 tracked: 5 siting. Separately: 1 suspended. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Pressurized water reactor. How it works, with a 3D view.
Schematic of Rolls-Royce SMR. On the left, a reactor vessel holds a core of fuel assemblies, with control rod drives above its head.
Schematic of Rolls-Royce SMR.

Description

On 6 May 2025 the Ministry of the Environment received an environmental-assessment notification filed by ČEZ for one to six light-water SMRs with planned net output of up to 1,500 MWe inside and beside the grounds of the Tušimice coal power station, which is due to close. The ministry's screening conclusion of 22 December 2025 sets what ČEZ's environmental-impact documentation must cover, including a justification of the site against alternatives in the region; Czech law requires a full assessment for every nuclear plant. The ministry's conclusion says the supplier is not chosen and shows Rolls-Royce SMR's design as one of four reference designs, with the BWRX-300, NUWARD and AP300, and records construction after 2034 and operation after 2038 as planned timing. In April 2026 ČEZ said it was also developing a project at Tušimice, and a July 2026 memorandum between the industry ministry, ČEZ and Rolls-Royce SMR names Tušimice and Dětmarovice as sites being assessed; up to six Rolls-Royce SMR units are stated for three Czech sites together, not for Tušimice alone. Read on 28 October 2026, the environmental-assessment register showed no documentation or opinion after the screening conclusion. The assessment and site studies do not establish construction or a committed unit count.

Key facts

Design
Rolls-Royce SMR (SMR)
Technology
Pressurized water reactor (PWR) · light water. The 2024 SMR Technology Catalogue describes a three-loop pressurized water reactor, so no integral layout is recorded.
Reactor vessel of this design
7.82 m tall, 4.2 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 79.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Operator(s)
Not recorded
Vendor for linked design
Rolls-Royce SMR
Design origin
United Kingdom: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
Location
Tušimice candidate location · Czechia · precision: site area (named plant, laboratory, base, port, campus or parcel)
Approximate coordinates for the named Tušimice candidate location from the NuclearChain reactors export (CC BY 4.0; derived from GEM's tracker).
Coordinates
50.3809, 13.3347 · site-area point (approximate)
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
28 Oct 2026
Site and capacity notes

Rolls-Royce SMR Tušimice candidate location is recorded at Tušimice candidate location, state or province not recorded, Czechia. Operator: No operator is recorded. Recorded vendor: Rolls-Royce SMR. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'tusimice-nuclear-power-plant' (50.3809498, 13.3347381)

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project. The linked design record states 1358 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Reactor supplier
Fuel
  • Fuel form stated for Rolls-Royce SMRUO2
No project-specific fuel supply arrangement is recorded as a structured fact.

The reviewed sources do not establish a project-specific fuel supplier commitment or delivery. General supply-market plans and reactor-design fuel requirements are kept separate. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. CENIA EIA MZP531: Nový jaderný zdroj SMR v lokalitě Tušimice; MPO: Czech Republic will develop further SMR sites; ČEZ: Temelín SMR project advances to next phase

Programs and agreements naming the project
Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
Customer or offtaker

The reviewed sources do not establish a named project-specific power or heat purchaser, contractual quantity or completed offtake. Intended uses, host municipalities and general company customer plans are not buyer commitments. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. MPO: Czech Republic will develop further SMR sites; ČEZ additional Czech SMR locations; ČEZ: Temelín SMR project advances to next phase; CENIA EIA MZP531: Nový jaderný zdroj SMR v lokalitě Tušimice

Contractor

The reviewed sources do not establish an additional project-specific engineering, preparatory-work or construction assignment. A supplier’s general capabilities or an industry-wide agreement do not establish a contract for this site. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. MPO: Czech Republic will develop further SMR sites; ČEZ additional Czech SMR locations; CENIA EIA MZP531: Nový jaderný zdroj SMR v lokalitě Tušimice; World Nuclear News: ČEZ submits EIA documentation for the Temelín Rolls-Royce SMR to the Ministry of the Environment

Funding and government decisions

The reviewed sources do not establish a project-specific financing commitment or amount. General company backing, ownership and policy support do not by themselves establish allocated or paid project funding. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. MPO: Czech Republic will develop further SMR sites; ČEZ additional Czech SMR locations; CENIA EIA MZP531: Nový jaderný zdroj SMR v lokalitě Tušimice

Comparable schedule revision

Comparable schedule revision not established. The reviewed sources do not establish two dated statements revising the same project milestone. A single target, a fleet-level ambition or a different project’s timetable is not a schedule revision. This finding is confined to the cited sources reviewed on 21 October 2026; it is not evidence that no arrangement exists elsewhere. CENIA EIA MZP531: Nový jaderný zdroj SMR v lokalitě Tušimice; MPO: Czech Republic will develop further SMR sites

Not recorded in SMRMap's reviewed evidence (2): Operator or intended licensed owner; Site host or owner
Operator or intended licensed owner
Reviewed 20 Oct 2026: not disclosed in the reviewed evidence.
Site host or owner

Timeline

Recorded developments

Permissions and applications

Assessments of the design (not of this site)

(2)
  • Rolls-Royce SMR Generic Design Assessment — applies to the design, not to a site
    Design assessment sought · Under review · ONR/EA (UK)
    Generic Design Assessment of the Rolls-Royce SMR design by the UK regulators. ONR's page (read 3 October 2026) shows Step 1 from April 2022 to April 2023, Step 2 to July 2024 with published Step 2 statements, and Step 3 under way since July 2024. A GDA assesses the generic design only; it is not permission for any site, construction or operation, and no Step 3 conclusion is recorded here. The reactors index, fetched 5 October 2026, still lists this as the active assessment and does not record a Step 3 conclusion. Re-read on 28 October 2026, ONR's page still describes the assessment as ongoing.
    Sources: ONR Generic Design Assessment: Rolls-Royce SMR

    Status confirmed on against ONR Generic Design Assessment: Rolls-Royce SMR. This confirms the recorded status only; the general record check date remains separate.

  • Rolls-Royce SMR UK Generic Design Assessment, Step 2 — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed 30 Jul 2024
    The UK regulators completed Step 2 of their three-step Generic Design Assessment of the Rolls-Royce SMR on 30 July 2024 and issued Step 2 statements. Step 2 began on 3 April 2023, after Step 1 from April 2022 to April 2023. Step 3, the detailed assessment, began in July 2024 and is recorded separately as under way. Completing Step 2 is not a Design Acceptance Confirmation or permission for any site.
    Sources: Environment Agency: assessing new nuclear reactor designs; ONR Generic Design Assessment: Rolls-Royce SMR; Environment Agency and Natural Resources Wales: GDA Step 2 of the Rolls-Royce SMR

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)
  • Evidence review. The Ministry of the Environment's screening conclusion of 22 December 2025 describes ČEZ's notification as one to six light-water Generation III+ SMRs with planned net output of up to 1,500 MWe inside and beside the Tušimice coal-plant grounds. It says the supplier will be chosen later and is not part of the assessment, shows four reference designs, and requires the documentation to justify the site against alternatives in the region. The ministry received the notification on 6 May 2025. Czech law makes a full assessment mandatory for this category, so the screening did not decide that one was needed. The register page states no unit count or capacity and, read on 28 October 2026, listed no documentation or opinion after the screening conclusion. ČEZ said in February 2023 that exploration of the Tušimice and Dětmarovice power-plant sites had begun, and its 24 April 2026 Czech release says it is also developing a project at Tušimice. The 21 July 2026 industry-ministry release names Tušimice and Dětmarovice as sites being assessed under a memorandum with ČEZ and Rolls-Royce SMR; up to six reactors and up to 3 GW are stated for three Czech sites together. The stage is Siting because the named site is being evaluated: ČEZ began site exploration in February 2023 and filed a formal environmental-impact notification as notifier, now past screening; no nuclear license application is recorded. A reactor operator is not assigned from the proposer, parent or memorandum relationships. Last checked 28 Oct 2026. Závěr zjišťovacího řízení: Nový jaderný zdroj SMR v lokalitě Tušimice (Č. j. MZP/2025/710/3747); CENIA EIA MZP531: Nový jaderný zdroj SMR v lokalitě Tušimice; ČEZ: After preliminary assessment ČEZ has identified two preferred construction sites for small modular reactors, in addition to the Temelín pilot location, in Dětmarovice and Tušimice; ČEZ: Temelín SMR project advances to next phase; MPO: Czech Republic will develop further SMR sites
    What would change this

    ČEZ's environmental-impact documentation for Tušimice, the ministry's final opinion, or a nuclear-regulator siting application. Next scheduled check: 28 Jan 2027.

  • Operator or intended licensed owner: Not disclosed in the reviewed evidence. The reviewed sources establish other participant roles, but do not appoint the recorded party as this reactor’s operator. The operator remains unassigned; this does not assert that no operator exists. Last checked 20 Oct 2026. CENIA EIA MZP531: Nový jaderný zdroj SMR v lokalitě Tušimice; MPO: Czech Republic will develop further SMR sites
    What would change this

    A project-specific filing, operating agreement or developer statement explicitly names the proposed reactor operator. Next scheduled check: 20 Jan 2027.

  • Next decision and prerequisites. After the December 2025 screening conclusion, the next environmental step is ČEZ's EIA documentation for Tušimice, which the EIA record did not yet show. The July 2026 ministry release says the government will decide in 2028 on the schedule and construction of further units, without saying whether that covers an SMR at Tušimice. Last checked 23 Oct 2026. Závěr zjišťovacího řízení: Nový jaderný zdroj SMR v lokalitě Tušimice (Č. j. MZP/2025/710/3747); MPO: Czech Republic will develop further SMR sites
    What would change this

    Publication of ČEZ's Tušimice EIA documentation, or the 2028 government decision on further SMR units. Next scheduled check: 23 Apr 2027.

  • Permissions and public process. The national EIA information system shows ČEZ's environmental notification for a new SMR nuclear source at Tušimice, published on the regional notice board on 14 May 2025 with comments due by 13 June 2025, and a screening conclusion issued on 22 December 2025. Screening is a stage of environmental review, not a permit; the record shows no EIA documentation yet, and no nuclear or building permit is shown in the sources reviewed. Last checked 23 Oct 2026. CENIA EIA MZP531: Nový jaderný zdroj SMR v lokalitě Tušimice
    What would change this

    Submission or publication of ČEZ's EIA documentation for Tušimice, or the ministry's final EIA opinion. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). The Ministry of the Environment's December 2025 screening conclusion says the Tušimice SMR would be built within the grounds of the existing Tušimice coal power station, due to close and be demolished, and adjacent land, chosen mainly for available space and links to water supply, waste-water discharge, power export and backup supply via the Hradec substation. It describes a planned 400 kV overhead line for power export. These are planned arrangements in a notification under assessment, and the EIA record notes that effects on Natura 2000 sites could not be ruled out. Last checked 23 Oct 2026. Závěr zjišťovacího řízení: Nový jaderný zdroj SMR v lokalitě Tušimice (Č. j. MZP/2025/710/3747); CENIA EIA MZP531: Nový jaderný zdroj SMR v lokalitě Tušimice
    What would change this

    ČEZ's EIA documentation or the ministry's final EIA opinion setting conditions on site, water and grid. Next scheduled check: 23 Apr 2027.

  • Spent fuel, waste and closure. The December 2025 screening conclusion requires ČEZ's EIA documentation to describe radioactive waste management and the spent fuel management concept for the specific SMR type, and to show that safe disposal capacity for all operational waste will exist, including repository capacity and a disposal strategy. It notes the reactor supplier will be chosen later. The spent fuel and waste arrangement for Tušimice is therefore still to be defined. Last checked 23 Oct 2026. Závěr zjišťovacího řízení: Nový jaderný zdroj SMR v lokalitě Tušimice (Č. j. MZP/2025/710/3747)
    What would change this

    ČEZ's EIA documentation for Tušimice setting out the waste and spent fuel concept, or the ministry's EIA opinion on it. Next scheduled check: 23 Apr 2027.

Evidence dates

(2 of 8 sources with a publication or document date)
Latest dated listed source publication: Závěr zjišťovacího řízení: Nový jaderný zdroj SMR v lokalitě Tušimice (Č. j. MZP/2025/710/3747): 22 Dec 2025.Latest dated recorded event: Rolls-Royce SMR Tušimice candidate location proposal documented: 21 Jul 2026.6 of 8 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(8)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Rolls-Royce SMR Tušimice candidate location — https://smrmap.com/projects/rr-tusimice/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Rolls-Royce SMR Tušimice candidate location”. Record reviewed 28 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/rr-tusimice/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.