CNEC / Zheneng Sanmen HTGR power station

In 2017 a CNEC HTR Holdings and Zheneng joint venture obtained site-selection and land pre-review replies for an HTGR power station in Sanmen county, China.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . None of the 4 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • No map pin is shown for this record.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
High-temperature gas-cooled reactor. How it works, with a 3D view.
Schematic of HTR-PM, this type's example. On the left, a tall reactor vessel holds a bed of fuel spheres inside a graphite reflector, with fuel tubes above and below.
Schematic of HTR-PM, this type's example.

Description

Its pre-feasibility study passed review, and Chinergy named Sanmen among HTR-PM600 feasibility sites. A November 2024 county plan still lists a long-term planned HTGR station, but current status is only planning-level.

Key facts

Design
HTR-PM600 (SMR)
Technology
High-temperature gas-cooled reactor (HTGR) · helium
Operator(s)
Not recorded
Vendor for linked design
Chinergy / CNNC Energy Technology
Location
Sanmen HTGR site · China · precision: town or locality only
The sources name this place but publish no coordinate for it, so no pin is shown.
Coordinates
Town named, no map pin
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
SMR by design class
Confidence
medium
Record reviewed
2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

CNEC / Zheneng Sanmen HTGR power station is recorded at Sanmen HTGR site, Zhejiang, China. Operator: No operator is recorded. Recorded vendor: Chinergy / CNNC Energy Technology. Stage: Siting. Location precision: town or locality only; town named, no map pin.

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Reactor supplier
Funding and government decisions

Source-backed project statement The 21 August 2017 report says the joint venture was to be formed with registered capital of 30 million yuan. The high-temperature-reactor holding company subscribed 15.3 million yuan for 51 percent, and Zheneng Power subscribed 14.7 million yuan for 49 percent. Later increases were to follow state approval of the project investment. This is formation capital, not a statement that plant construction costs were paid. China Energy News: CNEC Zhejiang Sanmen HTGR station preparatory work

Not found in the sources we checked (4): Customer or offtaker; Contractor; Fuel; Comparable schedule revision
Customer or offtaker

The 21 August 2017 China Energy News report of Zheneng Power's 11 August board resolution says the joint venture's business includes building and operating a station, desalination and heat supply, and selling electricity and related products. No buyer is named. The 22 November 2017 account of the preliminary-feasibility review also names no customer. China Energy News: CNEC Zhejiang Sanmen HTGR station preparatory work

Contractor

The 2017 reports name Zheneng Power and the nuclear-construction group's high-temperature-reactor holding company as shareholders of the project company. The November review says an unnamed design organization prepared the preliminary feasibility report. No engineering or construction contractor is named, and no construction award is stated. China Energy News: CNEC Zhejiang Sanmen HTGR station preparatory work; The Paper: CNEC Zhejiang Sanmen HTGR pre-feasibility study passes review

Fuel
No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.

China Energy News of 21 August 2017, World Nuclear News of 19 September 2017 and The Paper of 22 November 2017 describe the Sanmen HTGR joint venture, its site replies and its pre-feasibility review, and the pebble-bed technology platform, but none names a fuel manufacturer, quantity or delivery for the Sanmen station. The graphite-sphere loading in the 2017 report concerns the separate HTR-PM demonstration. China Energy News: CNEC Zhejiang Sanmen HTGR station preparatory work; WNN: China plans further high-temperature reactor innovation

Comparable schedule revision

Comparable schedule revision not established. China Energy News of 21 August 2017 and The Paper of 22 November 2017 date the 2017 preparatory steps, site-selection and land pre-review replies and a pre-feasibility review on 16 and 17 November 2017, and The Paper says the project was still far from realisation. None gives a construction or operation target for the Sanmen station, so no schedule revision is shown. China Energy News: CNEC Zhejiang Sanmen HTGR station preparatory work; The Paper: CNEC Zhejiang Sanmen HTGR pre-feasibility study passes review; WNN: China plans further high-temperature reactor innovation

Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Operator or intended licensed owner
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(5 notes, 1 not yet reviewed)
  • Evidence review. Zheneng Electric Power (浙能电力) announced on 11 August 2017 a board resolution to form Zhejiang Sanmen HTR Power Station Co. (浙江三门高温堆电站有限公司) with CNEC HTR Holdings (核建高温堆控股有限公司), owned 51% by CNEC HTR Holdings and 49% by Zheneng, to jointly invest in, develop, build and operate a high-temperature gas-cooled reactor nuclear power station in the Taizhou area; China Energy News reported this on 21 August 2017 (sources in Chinese). The same report says the company in preparation had obtained replies on the site-selection opinion and the land-use pre-review, and The Paper reports that the pre-feasibility study report passed a review held on 16 and 17 November 2017, while warning that the project was still a long way from realisation. World Nuclear News (19 September 2017) reports HTR-PM600 feasibility studies under way for Sanmen among other sites; no opened source gives a reactor count or output for Sanmen, and Chinergy is linked only through its chief executive's remarks. None of the opened sources names the exact site within Sanmen county, and the only later source, the county's November 2024 heating plan, could not be opened when checked (the connection timed out), so the stored claim that the 2024 plan still lists the station could not be re-read. The stored HTR-PM600 design, Chinergy vendor, empty operator list, unstored capacity and siting stage stay, on 2017 evidence only. The next documentary decision would be a project approval or a national nuclear safety siting review for a named Sanmen site. Last checked 19 Oct 2026. China Energy News: CNEC Zhejiang Sanmen HTGR station preparatory work; The Paper: CNEC Zhejiang Sanmen HTGR pre-feasibility study passes review; WNN: China plans further high-temperature reactor innovation
    What would change this

    A National Development and Reform Commission project approval, an NNSA siting review, or a CNEC or Zheneng announcement naming the Sanmen HTGR site, or a readable copy of the 2024 Sanmen county heating plan, would change this record. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed: Not disclosed in the reviewed evidence. The opened sources place the project in Sanmen county (Taizhou area, Zhejiang) and report site-selection replies, but none names or locates the site. Their hints differ: a China Energy News subheading links the HTGR to the Sanmen nuclear power site, which also hosts the AP1000 units, while CNEC, as quoted by The Paper, presents the project as a step towards using coal-fired plant sites for HTGRs. The 2024 county plan, which the stored notes say names a planned HTGR station, could not be opened when checked. Last checked 19 Oct 2026. China Energy News: CNEC Zhejiang Sanmen HTGR station preparatory work; The Paper: CNEC Zhejiang Sanmen HTGR pre-feasibility study passes review; Sanmen County: combined heat and power plan 2024-2030
    What would change this

    A siting document (NNSA site review, NDRC approval or the readable Sanmen county heating plan) naming the HTGR site would settle whether it is the Sanmen nuclear site, a coal-plant site or another location. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. After describing the November 2017 preliminary-feasibility review, the same account says that before a construction permit and first concrete a project still has to complete site comparison, the preliminary study, site preparation, a project application, a full feasibility study and project approval. No later approval or cancellation was in the sources read. Last checked 23 Oct 2026. The Paper: CNEC Zhejiang Sanmen HTGR pre-feasibility study passes review
    What would change this

    A project-approval decision, a construction permit, or a cancellation of the Sanmen high-temperature reactor station. Next scheduled check: 21 Jan 2027.

  • Permissions and public process. A company message reported on 21 August 2017 says replies had been received on a site-selection opinion and a land pre-review that constrain preparatory work. On 16 and 17 November 2017 the Electric Power Planning and Engineering Institute reviewed the preliminary feasibility report and found no factor that would overturn construction. World Nuclear News reported on 19 September 2017 that HTR-PM600 feasibility studies were underway at Sanmen and at several other sites. None of these is a construction permit. Last checked 23 Oct 2026. China Energy News: CNEC Zhejiang Sanmen HTGR station preparatory work; The Paper: CNEC Zhejiang Sanmen HTGR pre-feasibility study passes review; WNN: China plans further high-temperature reactor innovation
    What would change this

    A project-approval or construction-permit decision for the Sanmen high-temperature reactor station. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water). The August 2017 replies cover a site-selection opinion and a land pre-review only. The November 2017 review examined site, transport, seismic, water and environmental topics inside the preliminary study and found no overturning factor. No construction-land approval, water right or grid connection is stated. Last checked 23 Oct 2026. China Energy News: CNEC Zhejiang Sanmen HTGR station preparatory work; The Paper: CNEC Zhejiang Sanmen HTGR pre-feasibility study passes review
    What would change this

    A construction-land approval, water right or grid connection for this station. Next scheduled check: 21 Jan 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(0 of 4 sources with a publication or document date)
Latest dated listed source publication: no date recorded.Latest dated recorded event: no date recorded.4 of 4 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(4)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: CNEC / Zheneng Sanmen HTGR power station — https://smrmap.com/projects/sanmen-htgr/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “CNEC / Zheneng Sanmen HTGR power station”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/sanmen-htgr/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.