SINAP small modular thorium molten-salt research reactor (10 MWe), Minqin
The Shanghai Institute of Applied Physics' thorium molten-salt research reactor in Minqin county, China, is a research facility, not a commercial power plant, at the siting stage.
Current status
- How current
- Record checked · Evidence reviewed · Next recheck due
Development and review dates
Newest recorded development . 1 of 5 listed sources has a publication or document date recorded here: 12 Mar 2026. Status not rechecked since the record check; this project is not covered by the nightly status check. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Jan 2026 · Recorded development: SINAP small modular thorium molten-salt research reactor: siting-stage assessment resubmitted. January 2026 resubmission of the siting-stage environmental impact report (30 MWt, 10 MWe), posted by the ecology ministry on 12 March 2026. Source: MEE: siting-stage environmental impact report (January 2026 resubmission), SINAP small modular thorium molten-salt reactor research facility. Updates entry
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- The mapped point is not an exact surveyed coordinate.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Molten salt reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The siting-stage environmental assessments published by China's ecology ministry (July 2024 edition posted November 2024; January 2026 resubmission posted March 2026) describe a 10 MWe small modular thorium molten-salt research reactor at the Shanghai Institute of Applied Physics campus in Minqin county next to TMSR-LF1, with groundbreaking targeted within 2026 and first criticality in 2030. The thermal rating was revised from 60 MWt to 30 MWt between editions. The National Energy Administration's July 2026 report says preliminary design is under way. No regulator siting opinion or construction license has been found; targets are not achieved milestones.
Key facts
- Technology
- Molten salt reactor (MSR) · molten salt
- Operator(s)
- Shanghai Institute of Applied Physics
- Vendor for linked design
- Shanghai Institute of Applied Physics
- Location
- SINAP Wuwei campus, Hongshagang zone, Minqin county · China · precision: site area (named plant, laboratory, base, port, campus or parcel)
Coordinates converted from the degrees, minutes and seconds given in the January 2026 siting-stage environmental assessment (38°57′31″ N, 102°36′55″ E); rounded to four decimals and labeled approximate. - Coordinates
- 38.9586, 102.6153 · site-area point (approximate)
- Electrical capacity
- 10 MWe (gross/net unspecified) · scope: plant
- Thermal capacity
- 30 MWth (nameplate; basis unspecified)
- Record reviewed
- 6 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
SINAP small modular thorium molten-salt research reactor (10 MWe), Minqin is recorded at SINAP Wuwei campus, Hongshagang zone, Minqin county, Gansu, China. Operator: Shanghai Institute of Applied Physics. Recorded vendor: Shanghai Institute of Applied Physics. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: MEE: siting-stage environmental impact report (January 2026 resubmission), SINAP small modular thorium molten-salt reactor research facility, January 2026 siting-stage environmental assessment: 38°57′31″ N, 102°36′55″ E
Recorded electrical output is 10 MWe (gross/net unspecified), scope plant. Modules planned: 1. Recorded thermal output is 30 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerShanghai Institute of Applied Physics · source
- Application filing entityShanghai Institute of Applied Physics · source
- Operator or intended licensed owner
- Reactor supplier
- Vendor for the linked designShanghai Institute of Applied Physics
- Contractor
Source-backed project statement The July 2024 siting-stage environmental report names Shanghai Nuclear Engineering Research and Design Institute as the organization that prepared the report for SINAP, a preparatory licensing role. SINAP itself is named as both construction and operating unit. No construction contractor is named, and no siting approval or construction license is recorded. MEE: siting-stage environmental impact report (July 2024), SINAP small modular thorium molten-salt reactor research facility
- Funding and government decisions
Source-backed project statement The January 2026 siting-stage environmental report says the facility, a 14th Five-Year national major science and technology infrastructure project, is funded by central government and enterprise support, with total investment of about 3.93 billion yuan. The July 2024 edition said central and local government support. These are funding sources and an estimate stated in a filing, not a recorded appropriation or disbursement. MEE: siting-stage environmental impact report (January 2026 resubmission), SINAP small modular thorium molten-salt reactor research facility; MEE: siting-stage environmental impact report (July 2024), SINAP small modular thorium molten-salt reactor research facility
- Programs and agreements naming the project
- Research program; activeSINAP thorium molten-salt reactor program: 100 MWt prototype targeted by 2035
- Comparable schedule revision
Source-backed project statement The July 2024 siting-stage environmental report targeted groundbreaking within 2025 and first criticality in 2030, and the January 2026 resubmission targets groundbreaking within 2026 with first criticality still in 2030. That is a one-year postponement of the same groundbreaking milestone. The July 2024 edition also printed 2029 for first criticality in one passage. Neither date is an achieved milestone. MEE: siting-stage environmental impact report (July 2024), SINAP small modular thorium molten-salt reactor research facility; MEE: siting-stage environmental impact report (January 2026 resubmission), SINAP small modular thorium molten-salt reactor research facility
Not found in the sources we checked (2): Customer or offtaker; Fuel
- Customer or offtaker
The siting-stage environmental reports of July 2024 and January 2026 describe the 10 MWe thorium molten-salt research reactor with an experimental power-generation system and a 35 kV step-up station at SINAP's Minqin campus, but name no buyer or user of its electricity or heat. It is a national research facility rather than a commercial supply project. MEE: siting-stage environmental impact report (January 2026 resubmission), SINAP small modular thorium molten-salt reactor research facility
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
The January 2026 siting-stage environmental report says the reactor would start up on thorium with low-enriched uranium and add LEU online, that the project includes its own thorium fuel-salt research and processing system, and that off-site transport of fuel raw materials is the unnamed supplier's responsibility. No fuel supplier, contract or delivery is named. MEE: siting-stage environmental impact report (January 2026 resubmission), SINAP small modular thorium molten-salt reactor research facility
Not recorded in SMRMap's reviewed evidence (1): Site host or owner
- Site host or owner
Timeline
Recorded developments
- · Recorded development
SINAP small modular thorium molten-salt research reactor: siting-stage assessment resubmitted
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(5 notes)
- Evidence review. The Shanghai Institute of Applied Physics (SINAP) of the Chinese Academy of Sciences proposes a small modular thorium molten-salt reactor research facility: a 10 MWe research reactor, 30 MWt in the January 2026 siting-stage environmental impact report, with a thorium fuel-salt research system, at its Wuwei campus in Hongshagang town, Minqin county, Gansu, beside the operating 2 MWt TMSR-LF1 (sources in Chinese). That report names SINAP as both the construction unit and the operating unit and targets groundbreaking within 2026 and first criticality in 2030. The July 2024 edition gave a 60 MWt design maximum, reached after a first step at 30 MWt, with groundbreaking targeted in 2025, and SINAP's notice of 12 December 2025 restarted public participation for the siting-stage assessment. The National Energy Administration's 2026 China Nuclear Power Development Report says preliminary design of the 10 MWe reactor is under way. A siting-stage environmental report is a filing, not a siting approval or construction license, and no opened source records a regulator decision or the targeted 2026 groundbreaking. The stored 10 MWe and 30 MWt for one unit, SINAP as operator and vendor, and the siting stage stay. The next documentary decision is the regulator's approval of the siting-stage report and a construction license application. Last checked 19 Oct 2026. MEE: siting-stage environmental impact report (January 2026 resubmission), SINAP small modular thorium molten-salt reactor research facility; MEE: siting-stage environmental impact report (July 2024), SINAP small modular thorium molten-salt reactor research facility; National Energy Administration: China Nuclear Power Development Report 2026 (July 2026)
What would change this
An ecology ministry (NNSA) approval of the siting-stage environmental impact report, a construction-stage report or construction license, or a groundbreaking notice would change this record. Next recheck due .
- Next decision and prerequisites. The January 2026 siting-stage report says work is proceeding toward breaking ground within 2026 and first criticality in 2030. Breaking ground would follow approval of the siting-stage environmental report and NNSA siting review, neither of which is shown in the sources reviewed; both dates are targets, not achieved events. Last checked 23 Oct 2026. MEE: siting-stage environmental impact report (January 2026 resubmission), SINAP small modular thorium molten-salt reactor research facility
What would change this
MEE approval of the environmental report, an NNSA siting opinion or construction license, or a groundbreaking announcement. Next recheck due .
- Permissions and public process. SINAP's 12 December 2025 notice opened the first public-participation round for the siting-stage environmental assessment of the small modular thorium molten-salt research facility, inviting comments while the draft report was prepared. The ecology ministry accepted the January 2026 siting-stage report for review on 12 March 2026. These are environmental-review steps, not permissions; no NNSA siting opinion or construction license was found in the sources reviewed. Last checked 23 Oct 2026. SINAP: public-participation notice for the small modular thorium molten-salt reactor research facility (12 December 2025); 生态环境部关于2026年3月12日建设项目环境影响评价文件受理情况的公示(核与辐射)
What would change this
MEE approval of the siting-stage environmental report or an NNSA siting opinion for the Minqin research reactor. Next recheck due .
- Site dependencies (land, grid, water). The January 2026 siting-stage report places the research reactor on SINAP's existing Wuwei campus, which SINAP's December 2025 notice locates in the Hongshagang energy and chemical industrial zone in Minqin, Gansu. The report uses direct air cooling, so no cooling-water supply is needed, and lists a 2017 reply finding the site outside the Liangucheng nature reserve. Grid or heat-use arrangements are not described in the passages reviewed. Last checked 23 Oct 2026. MEE: siting-stage environmental impact report (January 2026 resubmission), SINAP small modular thorium molten-salt reactor research facility; SINAP: public-participation notice for the small modular thorium molten-salt reactor research facility (12 December 2025)
What would change this
An approved environmental report or construction-stage document describing grid and utility connections at the Wuwei campus. Next recheck due .
- Spent fuel, waste and closure. The January 2026 siting-stage report plans for spent fuel salt to be drained from the core to a drain tank, cooled, and then piped to spent-fuel-salt storage tanks in an on-site temporary storage room with ventilation cooling and monitoring. It also sets out preliminary decommissioning ideas including waste management and decommissioning funding. These are planned arrangements in a siting report; a long-term disposal route for the spent fuel salt is not set out in the passages reviewed. Last checked 23 Oct 2026. MEE: siting-stage environmental impact report (January 2026 resubmission), SINAP small modular thorium molten-salt reactor research facility
What would change this
A construction-stage environmental report or license condition setting the spent fuel salt management route. Next recheck due .
Evidence dates
(1 of 5 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(5)
- MEE: siting-stage environmental impact report (January 2026 resubmission), SINAP small modular thorium molten-salt reactor research facility (government, accessed 6 Oct 2026)
- MEE: siting-stage environmental impact report (July 2024), SINAP small modular thorium molten-salt reactor research facility (government, accessed 6 Oct 2026)
- SINAP: public-participation notice for the small modular thorium molten-salt reactor research facility (12 December 2025) (company, accessed 6 Oct 2026)
- National Energy Administration: China Nuclear Power Development Report 2026 (July 2026) (government, accessed 6 Oct 2026)
- 生态环境部关于2026年3月12日建设项目环境影响评价文件受理情况的公示(核与辐射) (government, published 12 Mar 2026, accessed 23 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: SINAP small modular thorium molten-salt research reactor (10 MWe), Minqin — https://smrmap.com/projects/sinap-minqin-small-modular-tmsr/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “SINAP small modular thorium molten-salt research reactor (10 MWe), Minqin”. Record reviewed 6 Oct 2026. https://smrmap.com/projects/sinap-minqin-small-modular-tmsr/ (accessed [date]).
“Record reviewed” is the record review date; the evidence review, individual sources and later additions keep their own dates. Add the date you read the page; save a PDF if you need a copy of it.
Record details
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence (as stored in the record)
- medium
Data fingerprint 0153352d9753fff813ac32edec0a3ffbf1d8b7c7ee6420defec355f03d9ef915; build 2026-11-24. It identifies the underlying data collections, not an archived page or a download checksum. The build date is not a source review date.