Projects / United States · Canceled
UAMPS Carbon Free Power Project (canceled)
UAMPS and NuScale announced on 8 November 2023 that they had mutually agreed to terminate the Carbon Free Power Project.
Current status
- How current
- General record check . Bounded evidence review . 3 of 7 listed sources have a publication or document date recorded here; the newest is 8 Nov 2023. A listed page was last updated 7 Oct 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- 8 Nov 2023 · Cancellation: UAMPS CFPP canceled. UAMPS and NuScale announced mutual termination on 8 November 2023. Source: UAMPS and NuScale CFPP termination release (dated 8 Nov 2023); NRC past licensing: Carbon Free Power Project. Updates entry
More on this development
NRC recorded a 10 November 2023 withdrawal letter and suspended its review on 13 November 2023.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 4 tracked: 1 licensing, 1 announced. Separately: 1 canceled, 1 earlier-plan record. 10 tracked at canceled across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Integral pressurized water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
NRC records a 10 November 2023 letter from CFPP LLC and NuScale withdrawing the limited-work authorization, and suspension of that review on 13 November 2023. No combined license was issued. NRC says CFPP LLC, a wholly owned subsidiary of UAMPS, was established to develop, own and operate the project, and that the planned application would reference the NuScale US460 approval for a 77 MWe module. It does not state a module count. The World Nuclear Association USA profile, updated 7 October 2026, calls the project a VOYGR-6 plant and lists VOYGR-6 as 462 MWe. That figure is stored without a gross or net label. A separate profile section says six modules and records an October 2020 Department of Energy cost-share award to the project entity. UAMPS's 2 March 2022 term sheet with Xcel Energy was a step toward a possible operating contract, not a contract or a license, and its 2030 commercial-operation anticipation is not stored. The October project update says Fluor and NuScale supplied inputs to the Class 2 cost estimate. The map point is approximate Idaho National Laboratory context near Idaho Falls, not a surveyed pad.
Key facts
- Design
- NuScale VOYGR (US460 / NPM) (SMR)
- Technology
- Integral pressurized water reactor (iPWR) · light water
- Operator(s)
- Not recorded
- Vendor for linked design
- NuScale Power
- Location
- INL / CFPP proposed NuScale site · United States · precision: town or locality only
UAMPS's 2 March 2022 release proposed the plant at Idaho National Laboratory near Idaho Falls. The pin is the recorded OpenStreetMap point for the laboratory at its Central Facilities Area (43.5306324, −112.94046): a laboratory-wide point, not the surveyed CFPP parcel. - Coordinates
- 43.5306324, -112.94046 · town-level point (approximate)
- Electrical capacity
- 462 MWe (gross/net unspecified) · scope: plant
The WNA USA profile lists VOYGR-6 as 462 MWe and calls this project a VOYGR-6 plant. - Thermal capacity
- Not recorded
- Inclusion basis
- Earlier-plan record (historical SMR program)
- Confidence
- medium
- Record reviewed
- 19 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
UAMPS Carbon Free Power Project (canceled) is recorded at INL / CFPP proposed NuScale site, Idaho, United States. Operator: No operator is recorded. Recorded vendor: NuScale Power. Stage: Canceled. Location precision: town or locality only; town-level point (approximate).
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: 'Idaho National Laboratory, East Ogden Avenue, Central Facilities Area' (amenity=research_institute), 43.5306324, −112.94046
Recorded electrical output is 462 MWe (gross/net unspecified), scope plant. The WNA USA profile lists VOYGR-6 as 462 MWe and calls this project a VOYGR-6 plant. Modules planned: 6. Thermal output is not recorded on this project. The linked design record states 250 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project. The linked design record states 77 MWe (gross); the project figure is kept separate.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Parent companyUtah Associated Municipal Power Systems · source
- Project proposerUtah Associated Municipal Power Systems · source
- Reactor supplier
- Vendor for the linked designNuScale Power
- Customer or offtaker
- Customer / offtakerUtah Associated Municipal Power Systems · source
Source-backed project statement
UAMPS and NuScale's 8 November 2023 release says they ended the Carbon Free Power Project because it appeared unlikely to gain enough subscription, and describes the decision as best for the UAMPS members participating in it. The intended buyers were subscribing UAMPS member utilities. The project is terminated, so no supply will occur. UAMPS and NuScale CFPP termination release
- Contractor
Source-backed project statement UAMPS's October 2023 project update says Fluor and NuScale provided inputs to the project's Class 2 cost estimate, then under review, as preparatory engineering for the commercial-readiness decision. On 8 November 2023 UAMPS and NuScale mutually agreed to terminate the project before any construction contract or combined license, and CFPP LLC, wholly owned by UAMPS, was the development entity. UAMPS CFPP 40th project update; UAMPS and NuScale CFPP termination release
- Funding and government decisions
- Funder or lender named for this projectU.S. Department of Energy · sourceHistorical CFPP cost-share award: UAMPS’s termination account says its future and project-asset disposition were under discussion. No amount is stated here; not current financing for an active plant.
Source-backed project statement
The World Nuclear Association's US profile, updated 7 October 2026, says DOE approved a 1.335 billion dollar cost-share award over ten years in October 2020 to the UAMPS-owned Carbon Free Power Project entity for developing and building the plant. UAMPS's project page says that after termination the entity discussed the award's future and the disposition of project assets with DOE. This is a historical award to a terminated project, not current financing. World Nuclear Association — Nuclear Power in the USA; UAMPS Carbon Free Power Project archive
Not found in the sources we checked (2): Fuel; Comparable schedule revision
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
UAMPS's project archive page and the 8 November 2023 termination release name no fuel supplier, contract or delivery for the Carbon Free Power Project. The archive page's references to the DOE cost-share award and to disposing of project assets such as long-lead equipment do not concern fuel. The project was terminated before licensing. UAMPS Carbon Free Power Project archive; UAMPS and NuScale CFPP termination release
- Comparable schedule revision
Comparable schedule revision not established. UAMPS's 2 March 2022 Xcel Energy term-sheet release says the schedule anticipated the full plant commercially operating in 2030, and the project archive page says the combined license application had been on track for a January 2024 filing before the 8 November 2023 termination. These are different milestones, each stated once in the sources read, so no revision of the same milestone is shown. UAMPS Carbon Free Power Project archive; UAMPS and Xcel Energy CFPP term sheet
Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- · Cancellation
UAMPS CFPP canceled
Dates on the project record: Canceled: 8 Nov 2023.
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Assessments of the design (not of this site)
(1)
- NRC standard design approval for the NuScale US460 — applies to the design, not to a site
Design assessment · Issued / approved · NRC · decided 29 May 2025 · ADAMS ML25129A004, ML25086A073 · 90 FR 23716
The NRC issued a standard design approval to NuScale Power for the US460 small modular reactor design on 29 May 2025, completing its staff technical review. NuScale submitted the application in stages: the first part by letter dated 23 November 2022 and the remaining portions in stages between 29 November and 31 December 2022. The NRC notified NuScale by letter dated 31 July 2023 that the application was acceptable for docketing. The approval lets an applicant reference the design in a construction permit, operating license, combined license or manufacturing license application. It is a design approval only: it grants no permission for any site, construction or operation.
Sources: Federal Register 90 FR 23716 (4 Jun 2025): NuScale US460 standard design approval; Federal Register FR Doc. 2023-05457 (17 Mar 2023): NuScale US460 standard design approval application received; Federal Register FR Doc. 2023-16679 (4 Aug 2023): NuScale US460 standard design approval application accepted for docketing
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes)
- Evidence review. The UAMPS project page says that on 8 November 2023 UAMPS and NuScale announced a mutual agreement to terminate the Carbon Free Power Project, and that the combined license application was on track for a January 2024 filing. The termination release says the parties ended the project because enough subscription looked unlikely, and that the next work was to wind the project down. On 10 November 2023 CFPP LLC and NuScale told the NRC the project was terminated and asked to withdraw the limited-work authorization, an exemption request, and topical reports. The NRC suspended that review effective 13 November 2023. The NRC page says a combined license application was planned and would reference a 77 MWe module design. It does not say a combined license was issued. The World Nuclear Association profile calls the project a six-module VOYGR-6 plant at Idaho National Laboratory and lists VOYGR-6 as 462 MWe. That label does not say gross or net. A separate sentence calls the module design 77 MWe gross. The May 2025 standard design approval is a design approval for up to six modules, and it is later than the termination. A March 2022 term sheet describes Xcel Energy as a potential operator only. The stored six modules and 462 MWe stay. The stored roles stay. No combined-license date is added. Last checked 20 Oct 2026. UAMPS Carbon Free Power Project archive; UAMPS and NuScale CFPP termination release; NRC past licensing: Carbon Free Power Project; World Nuclear Association — Nuclear Power in the USA; UAMPS and Xcel Energy CFPP term sheet; UAMPS CFPP 40th project update
What would change this
A UAMPS, CFPP LLC, or NRC document that reopens this project or states that a combined license was issued. Next scheduled check: 20 Jan 2027.
- Plant capacity (scope qualified). The WNA USA profile lists VOYGR-6 as 462 MWe and calls this project a VOYGR-6 plant. The UAMPS termination pages and the NRC past-licensing page do not restate a plant total. The 462 MWe figure is that profile label. It is not stored as gross or net, because the label does not say which. Last checked 19 Oct 2026. World Nuclear Association — Nuclear Power in the USA; NRC past licensing: Carbon Free Power Project
What would change this
A UAMPS, CFPP LLC, NuScale or NRC document stating gross or net plant output. Next scheduled check: 19 Jan 2027.
- Module/unit count. The same WNA profile calls the project a six-module plant and a VOYGR-6 plant. The NRC page names the 77 MWe US460 module and does not state how many modules were selected. The count kept here is the profile's six-module description. Last checked 19 Oct 2026. World Nuclear Association — Nuclear Power in the USA
What would change this
A UAMPS, CFPP LLC or NRC document stating the selected module count. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites: Not applicable. UAMPS and NuScale terminated the project by mutual agreement on 8 November 2023 and adopted a wind-down schedule, so no project decision is pending. Reuse of its licensing work by other projects would not revive this record. Last checked 23 Oct 2026. UAMPS Carbon Free Power Project archive
What would change this
A UAMPS or NuScale announcement reviving a plant at the same Idaho site. Next scheduled check: 21 Jan 2027.
- Permissions and public process. UAMPS says the combined license application was on track for filing in January 2024 when the project was terminated in November 2023, so it was never filed. The NRC record noted in the summary covers withdrawal of the limited-work authorization request. No NRC license or permit was issued. Last checked 23 Oct 2026. UAMPS Carbon Free Power Project archive
What would change this
None expected for this terminated project; a new application at the site would be a separate record. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. No reactor was built or fueled, so no spent fuel arose. For closure, UAMPS says the project company discussed with DOE the future of the cost-share award and the disposition of project assets, including ownership of long-lead equipment, under a wind-down schedule. The outcome of those discussions is not recorded here. Last checked 23 Oct 2026. UAMPS Carbon Free Power Project archive
What would change this
A DOE or UAMPS document recording the settlement of the cost-share award or the disposition of project equipment. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). A February 2022 release from CFPP LLC, the UAMPS subsidiary, says field investigations at the project site at DOE's Idaho National Laboratory near Idaho Falls ran from August 2021 to January 2022, covering geotechnical and seismic-volcanic hazard work, a groundwater monitoring network to protect the Eastern Snake River Plain Aquifer and an on-site weather station, with results meant for the license application. UAMPS and NuScale terminated the project on 8 November 2023, so no site lease, water right or grid arrangement was completed. Last checked 23 Oct 2026. CFPP LLC: The Carbon Free Power Project completes field work to support site characterization; UAMPS and NuScale CFPP termination release
What would change this
None expected; the project is terminated. Next scheduled check: 23 Apr 2027.
Evidence dates
(3 of 7 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(7)
- UAMPS Carbon Free Power Project archive (company, accessed 19 Oct 2026)
- UAMPS and NuScale CFPP termination release (company, dated 8 Nov 2023, accessed 19 Oct 2026)
- NRC past licensing: Carbon Free Power Project (regulator, accessed 19 Oct 2026)
- World Nuclear Association — Nuclear Power in the USA (directory or tracker, page updated 7 Oct 2026, accessed 19 Oct 2026)
- UAMPS and Xcel Energy CFPP term sheet (company, dated 2 Mar 2022, accessed 19 Oct 2026)
- UAMPS CFPP 40th project update (company, accessed 19 Oct 2026)
- CFPP LLC: The Carbon Free Power Project completes field work to support site characterization (company, published 3 Feb 2022, accessed 23 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: UAMPS Carbon Free Power Project (canceled) — https://smrmap.com/projects/uamps-cfpp-cancelled/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “UAMPS Carbon Free Power Project (cancelled)”. Record reviewed 19 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/uamps-cfpp-cancelled/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.