Projects / Sweden · Siting

Videberg Kraft Rolls-Royce SMR plant on the Värö peninsula (Ringhals)

Videberg Kraft selected Rolls-Royce SMR in June 2026 as supplier for three 470 MW reactors on the Värö peninsula next to Ringhals; detailed planning has begun.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . None of the 4 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
25 Jun 2026 · Recorded development: Swedish Government decides to take a 60% stake in Videberg Kraft. The Government decided that the state will own 60% of Videberg Kraft, with Vattenfall and Industrikraft at 20% each; formal transfer is expected in the second half of 2027 and the negotiated support terms go to the European Commission for state-aid review. Source: Government of Sweden: the state becomes a part-owner of Videberg Kraft. Updates entry
More on this development

Not an investment decision, permit or construction start.

Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Thermal output is not recorded on this project.
  • The mapped point is not an exact surveyed coordinate.
Same design
6 tracked: 5 siting. Separately: 1 suspended. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Pressurized water reactor. How it works, with a 3D view.
Schematic of Rolls-Royce SMR. On the left, a reactor vessel holds a core of fuel assemblies, with control rod drives above its head.
Schematic of Rolls-Royce SMR.

Description

Its December 2025 state-support application describes about 1,500 MW in total, and on 25 June 2026 the Government decided the state will own 60% of the company (formal transfer expected in the second half of 2027; an EU state-aid decision is expected in autumn 2027). The Government's 2 October 2026 status page lists no approval application for this site. Rolls-Royce SMR is included with SMRMap's capacity-check note. No government approval or construction is established. The 25 June release reports parliamentary authorization to purchase the state’s 60% stake for at most SEK 1.8 billion. This is an acquisition ceiling, not a paid amount or reactor construction cost.

Key facts

Design
Rolls-Royce SMR (SMR)
Technology
Pressurized water reactor (PWR) · light water. The 2024 SMR Technology Catalogue describes a three-loop pressurized water reactor, so no integral layout is recorded.
Reactor vessel of this design
7.82 m tall, 4.2 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 79.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Operator(s)
Videberg Kraft
Vendor for linked design
Rolls-Royce SMR
Design origin
United Kingdom: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
Location
Värö peninsula next to Ringhals · Sweden · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain sites export point for 'Värö Peninsula nuclear power plant' (CC BY 4.0; position marked approximate). Peninsula-area point next to Ringhals.
Coordinates
57.232748, 12.117376 · site-area point (approximate)
Electrical capacity
1410 MWe (gross/net unspecified) · scope: plant
Thermal capacity
Not recorded
Modules planned
3
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
10 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes

Videberg Kraft Rolls-Royce SMR plant on the Värö peninsula (Ringhals) is recorded at Värö peninsula next to Ringhals, Halland, Sweden. Operator: Videberg Kraft. Recorded vendor: Rolls-Royce SMR. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: NuclearChain data downloads (CC BY 4.0), NuclearChain sites.csv row 'varo-peninsula-nuclear-power-plant' (57.232748, 12.117376)

Recorded electrical output is 1410 MWe (gross/net unspecified), scope plant. Modules planned: 3. Thermal output is not recorded on this project. The linked design record states 1358 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project. The linked design record states 470 MWe (net); the project figure is kept separate.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Operator or intended licensed owner
Reactor supplier
Funding and government decisions

Source-backed project statement Sweden’s 25 June 2026 release reports Parliament’s 9 June authorization to acquire 60% of Videberg Kraft for at most SEK 1.8 billion. That is a share-purchase ceiling, not payment or reactor construction cost. Formal transfer was expected in the second half of 2027. Separate support terms involved loans, two-way contracts for difference and risk/profit sharing; European Commission review remained ahead. Government of Sweden: the state becomes a part-owner of Videberg Kraft; Government of Sweden: Videberg Kraft applies for state support

Fuel
  • Fuel form stated for Rolls-Royce SMRUO2
No project-specific fuel supply arrangement is recorded as a structured fact.

Videberg Kraft's 15 June 2026 announcement describes a pressurised-water design and names no fuel supplier. The Government's 25 June 2026 release says nuclear-waste management terms were negotiated alongside the support terms, which concerns waste, not fuel supply. No fuel contract for Värö is stated. Videberg Kraft selects Rolls-Royce SMR as supplier for new nuclear power in Sweden; Government of Sweden: the state becomes a part-owner of Videberg Kraft

Not found in the sources we checked (3): Customer or offtaker; Contractor; Comparable schedule revision
Customer or offtaker

Videberg Kraft's 15 June 2026 supplier announcement says three reactors could produce about 12 TWh a year for southern Sweden and support industry's transition, and the Government's 25 June 2026 release describes state loans and two-way contracts for difference. None names a buyer of the power. Industrikraft is a co-owner, not a named offtaker, and a contract for difference with the state is price support, not a sale. Videberg Kraft selects Rolls-Royce SMR as supplier for new nuclear power in Sweden; Government of Sweden: the state becomes a part-owner of Videberg Kraft

Contractor

Videberg Kraft's 15 June 2026 announcement says it selected Rolls-Royce SMR as supplier for three reactors on the Värö peninsula and that detailed planning will now begin. That is the selection of the reactor vendor already recorded, not a signed engineering or construction contract, and no other contractor or the independent reviewer is named. Videberg Kraft selects Rolls-Royce SMR as supplier for new nuclear power in Sweden

Comparable schedule revision

Comparable schedule revision not established. The sources read date separate steps: the state-support application in December 2025, the supplier choice on 15 June 2026, the ownership decision on 25 June 2026 with share transfer expected in the second half of 2027, and an EU state-aid decision expected in autumn 2027. None gives an earlier and a later date for the same construction or operation milestone. Videberg Kraft selects Rolls-Royce SMR as supplier for new nuclear power in Sweden; Government of Sweden: the state becomes a part-owner of Videberg Kraft; Government of Sweden: Government review of new nuclear (status of applications)

Not recorded in SMRMap's reviewed evidence (2): Site host or owner; Programs and agreements naming the project
Site host or owner
Programs and agreements naming the project

Timeline

Recorded developments

Permissions and applications

Assessments of the design (not of this site)

(2)
  • Rolls-Royce SMR Generic Design Assessment — applies to the design, not to a site
    Design assessment sought · Under review · ONR/EA (UK)
    Generic Design Assessment of the Rolls-Royce SMR design by the UK regulators. ONR's page (read 3 October 2026) shows Step 1 from April 2022 to April 2023, Step 2 to July 2024 with published Step 2 statements, and Step 3 under way since July 2024. A GDA assesses the generic design only; it is not permission for any site, construction or operation, and no Step 3 conclusion is recorded here. The reactors index, fetched 5 October 2026, still lists this as the active assessment and does not record a Step 3 conclusion. Re-read on 28 October 2026, ONR's page still describes the assessment as ongoing.
    Sources: ONR Generic Design Assessment: Rolls-Royce SMR

    Status confirmed on against ONR Generic Design Assessment: Rolls-Royce SMR. This confirms the recorded status only; the general record check date remains separate.

  • Rolls-Royce SMR UK Generic Design Assessment, Step 2 — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed 30 Jul 2024
    The UK regulators completed Step 2 of their three-step Generic Design Assessment of the Rolls-Royce SMR on 30 July 2024 and issued Step 2 statements. Step 2 began on 3 April 2023, after Step 1 from April 2022 to April 2023. Step 3, the detailed assessment, began in July 2024 and is recorded separately as under way. Completing Step 2 is not a Design Acceptance Confirmation or permission for any site.
    Sources: Environment Agency: assessing new nuclear reactor designs; ONR Generic Design Assessment: Rolls-Royce SMR; Environment Agency and Natural Resources Wales: GDA Step 2 of the Rolls-Royce SMR

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(5 notes)
  • Evidence review. Videberg Kraft's 15 June 2026 release selected Rolls-Royce as supplier for three reactors at the Värö peninsula, next to Ringhals, and states 470 MW per reactor. It does not state 1,410 MW as a plant total. The stored 1,410 is not changed. Detailed planning is not construction. The December 2025 state-support application says the project is expected to give about 1,500 MW electrical in total. That approximate total is not written over the stored figure. Last checked 20 Oct 2026. Videberg Kraft selects Rolls-Royce SMR as supplier for new nuclear power in Sweden; Government of Sweden: Videberg Kraft applies for state support
    What would change this

    A construction application, or a Videberg notice that states a plant total and whether 470 MW is gross or net. Next scheduled check: 20 Jan 2027.

  • Next decision and prerequisites. The Government said on 25 June 2026 that, with the ownership agreements in place, it will notify the state support to the European Commission, whose decision can be expected in autumn 2027, and that the formal transfer of the state's 60% stake is expected in the second half of 2027. These are expected steps, not completed ones; a separate government approval application for the Värö site is not yet listed. Last checked 23 Oct 2026. Government of Sweden: the state becomes a part-owner of Videberg Kraft
    What would change this

    The EU Commission's state-aid decision, the share transfer, or a Värö approval application. Next scheduled check: 23 Jan 2027.

  • Permissions and public process. The Swedish Government's new-nuclear review page, published 2 October 2026, lists five applications received under the new government-approval process (Barsebäck, Målma, Norrsundet, Studsvik and Untra) and none under the older Environmental Code process; Värö is not among them. The Government's June 2026 decisions concern state ownership and support, which are not permissions. These sources describe no consultation or municipal decision for the Värö reactors. Last checked 23 Oct 2026. Government of Sweden: Government review of new nuclear (status of applications)
    What would change this

    Videberg Kraft's filing of an application for government approval of a nuclear facility on the Värö peninsula. Next scheduled check: 23 Jan 2027.

  • Site dependencies (land, grid, water). The Government's December 2025 release says Videberg Kraft plans reactors on the Värö peninsula at Ringhals 1 and 2, and Vattenfall's June 2026 release says detailed planning has begun for three reactors there, next to the operating Ringhals plant. These sources place the project on Vattenfall's Ringhals site but do not describe a grid connection, cooling-water arrangement or exact plot. Last checked 23 Oct 2026. Government of Sweden: Videberg Kraft applies for state support; Videberg Kraft selects Rolls-Royce SMR as supplier for new nuclear power in Sweden
    What would change this

    A Videberg Kraft application or consultation document describing the Värö site, grid connection and cooling. Next scheduled check: 23 Jan 2027.

  • Spent fuel, waste and closure. The Government's 25 June 2026 release says the share purchase agreement for Videberg Kraft has an annex setting out the main terms for state support and for nuclear-waste management, negotiated between the Government and the company in spring 2026. The release does not publish those waste terms, name a storage or disposal route, or say who bears which costs. Last checked 23 Oct 2026. Government of Sweden: the state becomes a part-owner of Videberg Kraft
    What would change this

    Publication of the waste-management terms, the EU state-aid notification or decision, or a Videberg Kraft application describing spent-fuel handling. Next scheduled check: 23 Jan 2027.

Evidence dates

(0 of 4 sources with a publication or document date)
Latest dated listed source publication: no date recorded.Latest dated recorded event: Swedish Government decides to take a 60% stake in Videberg Kraft: 25 Jun 2026.4 of 4 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(4)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Videberg Kraft Rolls-Royce SMR plant on the Värö peninsula (Ringhals) — https://smrmap.com/projects/videberg-varo-rr-smr/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Videberg Kraft Rolls-Royce SMR plant on the Värö peninsula (Ringhals)”. Record reviewed 10 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/videberg-varo-rr-smr/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.