Projects / United States · Commissioning
Aalo-X at Idaho National Laboratory
Aalo Atomics' Aalo-X is a DOE Reactor Pilot Program test reactor at Idaho National Laboratory, a critical assembly in commissioning after zero-power criticality on 4 Jul 2026.
Current status
- How current
- General record check . Bounded evidence review . 5 of 13 listed sources have a publication or document date recorded here; the newest is 30 Jul 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: DOE Idaho categorical exclusion CX-271002 for the Aalo-X critical assembly (14 Apr 2026). All permissions and applications
- Latest development
- 4 Jul 2026 · First criticality: Aalo-X zero-power criticality. Zero-power fueled criticality at INL. Source: DOE: fourth criticality, Aalo-X. Updates entry
More on this development
Not the RELLIS commercial proposal.
- Next dated milestone
- Planned step: 2027 (target). Aalo-X full-power test (30 MWth, ~10 MWe) planned. This is not an achieved milestone. Source: DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212).
- Selected limitations
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Zero-power fueled criticality was completed at INL on 4 Jul 2026. DOE Idaho categorical exclusion CX-271002, posting DOE-ID-INL-26-013, was approved on 14 Apr 2026 for a graphite-moderated dry critical assembly in the existing Critical Assembly Facility. Steady-state operation is not to exceed 10 watts thermal, and the assembly does not generate electricity. Fuel is low-enriched uranium dioxide below 20 percent U-235. The exclusion does not authorize a later power reactor. A separate determination, CX-271012, covers limited power-supply construction at the Aalo site. Not the commercial Aalo pod proposal at Texas A&M. DOE's Reactor Pilot Program update of July 2026 lists the preliminary documented safety analysis as approved on 3 March 2026 and the documented safety analysis as approved on 30 April 2026. Project Ascension is recorded separately as an announced second power-reactor proposal on the Aalo-X campus. Its planned 10 MWe output and 2027 data-center target do not change this critical assembly's 10-watt thermal limit or establish power-reactor permission. Its wider relationship to the seven-unit Idaho Falls fleet proposal remains unconfirmed. DOE's July 2026 update gives the fuel as 4.95 percent enriched uranium dioxide, supplied as Aalo-owned fuel pins. Aalo says the test reactor building, formerly the Critical Assembly Facility, stands on INL land leased from DOE and was built and is operated almost entirely by Aalo and its subcontractors. Aalo describes a separate 10 MWe Aalo-X power reactor being built next door; DOE's 2027 full-power test (30 MWth, about 10 MWe) refers to that power reactor, not to this 10-watt critical assembly.
Key facts
- Design
- Aalo-X (Microreactor)
- Technology
- Other · other
- Operator(s)
- Aalo Atomics
- Vendor for linked design
- Aalo Atomics
- Location
- Idaho National Laboratory, Materials and Fuels Complex (reactor pilot demonstrations) · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
DOE categorical exclusions place Aalo-X in the Critical Assembly Facility immediately south of the Materials and Fuels Complex (CX-271002), Mark-0 in building MFC-793 within the complex (CX-035340) and the Unity test in the NRAD facility at the complex (CX-271007). The pin reuses the recorded OpenStreetMap building center of the EBR-II containment at MFC (43.59507, −112.65716): a facility-area point that does not separate the three positions. Replaces an earlier Central Facilities Area point about 24 km to the west. - Coordinates
- 43.59507, -112.65716 · site-area point (approximate)
- Electrical capacity
- thermal only (no MWe) · scope: module
- Thermal capacity
- 10 watts thermal (zero-power limit)
- Purpose
- Research or test reactor
- Construction start
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Could not be confirmed on . Attempted official source: DOE: fourth criticality, Aalo-X. This is an access or status observation only; the record review date is unchanged.
Site and capacity notes
Aalo-X at Idaho National Laboratory is recorded at Idaho National Laboratory, Materials and Fuels Complex (reactor pilot demonstrations), Idaho, United States. Operator: Aalo Atomics. Recorded vendor: Aalo Atomics. Stage: Commissioning. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Antares Mark-0 at Idaho National Laboratory, Deployable Energy Unity at Idaho National Laboratory.
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: building center of the EBR-II containment (DOME) at the Materials and Fuels Complex, 43.59507, −112.65716
This project is recorded as thermal only (no MWe). Modules planned: 1. Recorded thermal output is 10 watts thermal (zero-power limit).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerAalo Atomics · source
- Operator or intended licensed owner
- OperatorAalo Atomics
- Reactor supplier
- Vendor for the linked designAalo Atomics
- Funding and government decisions
- Listed under a government program; not a disbursement; in effectDOE Reactor Pilot Program · sourceDOE lists this reactor's criticality demonstration under the Reactor Pilot Program.
Nuclear Engineering International's 7 July 2026 report mentions Aalo's US$100 million Series B round in 2025, which is company financing, and DOE's determination and pilot-program update state no funding for the critical assembly. No amount or funder specific to Aalo-X is stated in the sources read. NEI: Fourth reactor meets US criticality deadline
- Fuel
- Fuel supplier named for this projectGlobal Nuclear Fuel-Americas, LLC · sourceFabricated the fuel rods used for the 4 July 2026 criticality (reported 7 July 2026).
- Fuel supplier named for this projectUrenco · sourceWith GE Vernova's Global Nuclear Fuel, refined and manufactured the LEU fuel rods used for the 4 July 2026 criticality, per NEI (7 July 2026); Urenco's exact share not stated.
- Fuel form stated for Aalo-XSponsor-owned low-enriched uranium dioxide (UO2) fuel pins
- Enrichment stated for Aalo-X4.95% enriched UO2
Source-backed project statement
Nuclear Engineering International reported on 7 July 2026 that Aalo commissioned GE Vernova's Global Nuclear Fuel to fabricate the Aalo-X fuel rods and that Urenco USA and GNF refined and manufactured the LEU rods used for the 4 July 2026 criticality. DOE's determination describes the fuel as sponsor-owned low-enriched uranium dioxide pins, and DOE's July 2026 update gives 4.95% enrichment. The fuel was delivered and used. Urenco's exact share is not stated. NEI: Fourth reactor meets US criticality deadline; DOE Idaho categorical exclusion CX-271002 PDF: Aalo-X critical assembly
- Site host or owner
- Site hostIdaho National Laboratory · source
- Programs and agreements naming the project
- Government program; activeDOE Reactor Pilot Program (DOE-authorized advanced test reactors)
Not found in the sources we checked (3): Customer or offtaker; Contractor; Comparable schedule revision
- Customer or offtaker
The Department of Energy exclusion approved on 14 April 2026 limits this Aalo-X assembly to zero-power physics tests at no more than 10 watts thermal, with no electrical generation. Aalo’s 5 May 2026 post says the critical test reactor validates Aalo’s own models, and its 4 July and 30 July 2026 posts name data-center electricity and Crusoe only for a later power reactor. Those sources do not name a research user, test beneficiary, or service customer for this assembly. The developer, the Department as authorizer, and the laboratory as site host are not treated as customers. DOE Idaho categorical exclusion CX-271002 PDF: Aalo-X critical assembly; Aalo: DOE-Idaho Approves Aalo's Documented Safety Analysis for the Aalo-X Critical Test Reactor; Aalo: first criticality post, including Project Ascension (4 July 2026); Aalo: Crusoe partnership (30 July 2026)
- Contractor
Aalo's 5 May 2026 post says the Critical Test Reactor building, on INL land leased from DOE, is built, managed and operated almost exclusively by Aalo and its subcontractors, none of whom is named. INL is the recorded site host. No engineering or construction contractor for the critical assembly is named in the sources read. Aalo: DOE-Idaho Approves Aalo's Documented Safety Analysis for the Aalo-X Critical Test Reactor
- Comparable schedule revision
Comparable schedule revision not established. DOE's July 2026 pilot-program update lists the Aalo-X safety approvals in March and April 2026 and criticality on 4 July 2026, which met Aalo's earlier target of criticality by 4 July 2026. The 2027 full-power test concerns the separate power reactor. The record's events contain no revises or supersedes pair, and no revised date is stated. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212)
Timeline
Recorded developments
- · First criticality
Aalo-X zero-power criticality - · Recorded development
DOE approves the Aalo-X documented safety analysis - · Environmental decision recorded
Environmental decision recorded: DOE Idaho categorical exclusion CX-271002 for the Aalo-X critical assembly - · Recorded development
DOE approves the Aalo-X preliminary documented safety analysis - Reported · Groundbreaking
Aalo breaks ground for Aalo-X next to INL's Materials and Fuels Complex
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Aalo-X full-power test (30 MWth, ~10 MWe) planned
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Environmental decision
- DOE Idaho categorical exclusion CX-271002 for the Aalo-X critical assembly
Environmental decision · Issued / approved · U.S. Department of Energy, Idaho Operations Office · decided 14 Apr 2026
Approved 14 April 2026 under posting DOE-ID-INL-26-013. Covers installation and zero-power operation of the critical assembly at no more than 10 watts thermal. It is an environmental categorical exclusion, not a construction permit or operating license, and it does not authorize a later power reactor.
Sources: DOE Idaho categorical exclusion CX-271002 PDF: Aalo-X critical assembly
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(8 notes)
- Evidence review. DOE says Aalo Atomics' test reactor Aalo-X completed a zero-power fueled criticality demonstration at Idaho National Laboratory (DOE page dated 6 July 2026), and Aalo dates criticality to 4 July 2026 at 12:20 a.m. MT. DOE Idaho categorical exclusion CX-271002 (posting DOE-ID-INL-26-013, approved 14 April 2026) describes Aalo's proposal to install and operate a dry, graphite-moderated, zero-power critical assembly in the existing Critical Assembly Facility immediately south of INL's Materials and Fuels Complex, limited to 10 watts thermal with no electrical generation, thermal energy production or power conversion; it is an environmental determination, not a construction or operating permission. DOE's July 2026 slides list the preliminary documented safety analysis as approved on 3 March 2026 and the documented safety analysis on 30 April 2026; Aalo's post of 5 May 2026 says the DSA approval moved it into the Operational Readiness Review, and DOE's note of 14 July 2026 says readiness assessments were needed for DOE to authorize startup, but the startup authorization itself is not published. Aalo says the building stands on INL land leased from DOE, that its construction, management and operation are almost exclusively by Aalo and its subcontractors, and that it is authorized under DOE rather than the NRC. Site work is kept apart from nuclear installation: World Nuclear News reported groundbreaking on 29 August 2025 and DOE determination CX-271012 (27 January 2026) covers a transformer and 14 power poles for the Aalo site, while no date is published for installing the critical assembly itself; Aalo's statement that the Critical Test Reactor went from groundbreaking to criticality in less than eight months does not fit the August 2025 report. Aalo's August 2025 target of criticality by 4 July 2026 was met. No fuel-loading date is given; the assembly produces no electricity, so there is no generation, grid connection or commercial service, and no source after July 2026 states its current operating status. The 2027 full-power test (30 MWth, about 10 MWe) and Project Ascension belong to the separate 10 MWe power reactor next door. Stored values (one module limited to 10 watts thermal, Aalo as operator, INL site) match the sources; the stored participant roles omit Aalo as the proposer named in CX-271002. Last checked 19 Oct 2026. DOE: fourth criticality, Aalo-X; World Nuclear News: Aalo breaks ground for experimental reactor; DOE Idaho NEPA determination CX-271002: Aalo-X Critical Assembly Facility; DOE Idaho categorical exclusion CX-271002 PDF: Aalo-X critical assembly; DOE Idaho NEPA determination CX-271012: Aalo site limited construction activities (Revision 2); DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); Aalo: DOE-Idaho Approves Aalo's Documented Safety Analysis for the Aalo-X Critical Test Reactor; DOE EM note on four Reactor Pilot criticality reviews; Aalo: first criticality post, including Project Ascension (4 July 2026)
What would change this
DOE or Aalo publishes the Aalo-X startup authorization, or a DOE notice ending or changing zero-power testing in the Critical Assembly Facility. Next scheduled check: 19 Jan 2027.
- Permission evidence appropriate to stage: Not disclosed in the reviewed evidence. The operating authority for this DOE-authorized critical assembly is DOE's startup authorization after the readiness review, and no opened source publishes that instrument or its date. DOE's July 2026 slides list the preliminary documented safety analysis as approved on 3 March 2026 and the documented safety analysis on 30 April 2026, and Aalo's post of 5 May 2026 says the DSA approval moved it into the Operational Readiness Review; DOE's note of 14 July 2026 says the readiness assessments were needed for DOE to authorize startup. DOE calls Aalo-X a DOE-authorized reactor. The stored permission is the CX-271002 environmental exclusion of 14 April 2026, which is not an operating authority. This is DOE authorization, not an NRC license. Last checked 19 Oct 2026. DOE: fourth criticality, Aalo-X; DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); Aalo: DOE-Idaho Approves Aalo's Documented Safety Analysis for the Aalo-X Critical Test Reactor; DOE EM note on four Reactor Pilot criticality reviews
What would change this
DOE publishes the Aalo-X startup authorization or readiness-review closure, or a new DOE authorization for the 10 MWe power reactor. Next scheduled check: 19 Jan 2027.
- Construction start evidence: Sources conflict. World Nuclear News reported on 29 August 2025 that Aalo had broken ground at the Aalo-X site next to INL's Materials and Fuels Complex. Aalo and DOE quote Aalo saying the Critical Test Reactor went from groundbreaking to criticality in less than eight months (or 'just eight months'), which points to a start no earlier than about November 2025. No dated groundbreaking for the test reactor building itself has been published. Last checked 18 Oct 2026. World Nuclear News: Aalo breaks ground for experimental reactor; Aalo: first criticality post, including Project Ascension (4 July 2026)
What would change this
Aalo, DOE or INL publishes a dated construction start for the Critical Test Reactor building. Next scheduled check: 18 Jan 2027.
- Operation or grid target (type stated): Not applicable. First criticality, the operation milestone for this zero-power non-power reactor, was achieved on 4 July 2026, so no further target applies. The 2027 full-power test (30 MWth, about 10 MWe) belongs to the separate 10 MWe Aalo-X power reactor that Aalo says is being built next door. Last checked 19 Oct 2026. DOE: fourth criticality, Aalo-X; Aalo: DOE-Idaho Approves Aalo's Documented Safety Analysis for the Aalo-X Critical Test Reactor; Aalo: first criticality post, including Project Ascension (4 July 2026)
What would change this
DOE or Aalo publishes a new phase for the Critical Test Reactor, distinct from the adjacent 10 MWe power reactor. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites: Not disclosed in the reviewed evidence. Criticality of this zero-power assembly occurred on 4 July 2026, as the Department of Energy slides and Aalo’s post record. The slides’ plans after that date are a 2027 full-power test and later commercial pods, which Aalo’s 4 July post assigns to a second reactor, Project Ascension. The exclusion says decommissioning of this assembly would need a separate authorization, but no source names that, or any other step, as the next decision with prerequisites. Last checked 23 Oct 2026. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); Aalo: first criticality post, including Project Ascension (4 July 2026); DOE Idaho categorical exclusion CX-271002 PDF: Aalo-X critical assembly
What would change this
A Department schedule naming the next authorization for this 10-watt assembly, such as defueling or decommissioning, and its prerequisites. Next scheduled check: 21 Jan 2027.
- Permissions and public process. The Department of Energy Idaho Operations Office approved categorical exclusion CX-271002 for this critical assembly on 14 April 2026. That is an environmental exclusion, not an operating license. Aalo said on 5 May 2026 that the Idaho office approved the documented safety analysis on 30 April 2026 and that the assembly is authorized under the Department framework rather than the Nuclear Regulatory Commission. The Department texts reviewed do not include the later startup authorization. Last checked 23 Oct 2026. DOE Idaho categorical exclusion CX-271002 PDF: Aalo-X critical assembly; Aalo: DOE-Idaho Approves Aalo's Documented Safety Analysis for the Aalo-X Critical Test Reactor; DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212)
What would change this
Publication of the Department startup authorization for this assembly, or any Nuclear Regulatory Commission application for it. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). Aalo said on 5 May 2026 that the critical-test building stands at Idaho National Laboratory on land leased from the Department of Energy. The 14 April 2026 exclusion places the assembly in the existing Critical Assembly Facility and says potable, fire, sanitary, and industrial-wastewater lines will tie into existing site utilities, with no process-water use. It also says the assembly does not generate electricity, so no export interconnection is stated. Last checked 23 Oct 2026. Aalo: DOE-Idaho Approves Aalo's Documented Safety Analysis for the Aalo-X Critical Test Reactor; DOE Idaho categorical exclusion CX-271002 PDF: Aalo-X critical assembly
What would change this
The lease or land-use instrument for the critical-test building, or a water-service agreement beyond the utility tie-in described in the exclusion. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. The 14 April 2026 exclusion says the sponsor keeps ownership of the fuel, Idaho National Laboratory assumes none, and used fuel will be returned to transport containers after testing, with no reprocessing, long-term storage, or disposal in this scope. Some fuel may stay for possible reuse in a future Aalo-X reactor, and offsite shipment waits until the sponsor’s facility is authorized to receive it. The exclusion also expects only small quantities of low-level waste and says decommissioning needs a separate authorization. Last checked 23 Oct 2026. DOE Idaho categorical exclusion CX-271002 PDF: Aalo-X critical assembly
What would change this
A later authorization for shipment of this fuel to the sponsor’s facility, or a disposal or decommissioning decision for the assembly. Next scheduled check: 21 Jan 2027.
Evidence dates
(5 of 13 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(13)
- DOE: fourth criticality, Aalo-X (government, accessed 1 Oct 2026)
- DOE fact sheet: The Golden Era of American Nuclear Energy Has Arrived (government, accessed 1 Oct 2026)
- DOE EM note on four Reactor Pilot criticality reviews (government, accessed 1 Oct 2026)
- DOE Idaho NEPA determination CX-271002: Aalo-X Critical Assembly Facility (government, accessed 3 Oct 2026)
- DOE Idaho NEPA determination CX-271012: Aalo site limited construction activities (Revision 2) (government, accessed 3 Oct 2026)
- DOE Idaho categorical exclusion CX-271002 PDF: Aalo-X critical assembly (government, accessed 4 Oct 2026)
- DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212) (government, accessed 15 Oct 2026)
- Aalo: first criticality post, including Project Ascension (4 July 2026) (company, published 4 Jul 2026, accessed 15 Oct 2026)
- Aalo: Crusoe partnership (30 July 2026) (company, published 30 Jul 2026, accessed 15 Oct 2026)
- Aalo: DOE-Idaho Approves Aalo's Documented Safety Analysis for the Aalo-X Critical Test Reactor (company, accessed 18 Oct 2026)
- World Nuclear News: Aalo breaks ground for experimental reactor (news report, published 29 Aug 2025, accessed 18 Oct 2026)
- NEI: Fourth reactor meets US criticality deadline (news report, published 7 Jul 2026, accessed 21 Oct 2026)
- NEI: Fourth reactor meets US criticality deadline (news report, published 7 Jul 2026, accessed 21 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Aalo-X at Idaho National Laboratory — https://smrmap.com/projects/aalo-x-inl/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Aalo-X at Idaho National Laboratory”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/aalo-x-inl/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.