Projects / United States · Commissioning

Antares Mark-0 at Idaho National Laboratory

First DOE Reactor Pilot Program reactor to reach criticality.

Current status

Stage
Commissioning
How current
General record check . Bounded evidence review . 4 of 12 listed sources have a publication or document date recorded here; the newest is 23 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Recorded: DOE Idaho categorical exclusion CX-035340 for the Antares Mark-0 experiment (26 Jan 2026). All permissions and applications
Latest development
4 Jun 2026 · First criticality: Antares Mark-0 zero-power criticality. Zero-power fueled criticality at INL. Source: DOE: first advanced reactor criticality, Antares Mark-0. Updates entry
More on this development

Not grid connection.

Next dated milestone
No next milestone date is recorded.
Selected limitations
  • The mapped point is not an exact surveyed coordinate.
  • Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions); Construction start evidence (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

Zero-power demonstration at INL on 4 Jun 2026. DOE Idaho categorical exclusion CX-035340, posting DOE-ID-INL-25-037, was approved on 26 Jan 2026 for a high-temperature heat-pipe reactor configured for zero-power criticality only. The determination says this version has no power conversion or heat removal and will not produce measurable thermal output. DOE's July 2026 update describes Mark-0 as a critical assembly below 100 watts thermal; that zero-power limit is stored and is not a power rating. Fuel is HALEU TRISO below 20 percent enrichment, in an amount below 120 kg. The reactor is in building MFC-793, named both Sodium Components Maintenance Shop and Sodium Cleaning and Maintenance Shop. Mark-1 is a different later reactor. This environmental exclusion is not an operating license. The project remains at the INL reactor-pilot site. DOE's Reactor Pilot Program update of July 2026 lists the preliminary documented safety analysis as approved in January 2026 and the documented safety analysis as approved in April 2026. DOE made a conditional HALEU commitment to Antares on 26 August 2025 for the reactor that was to reach criticality by 4 July 2026, and its Mark-0 determination refers to a HALEU agreement between Antares and DOE. Antares says BWXT fabricated the TRISO fuel, the same fuel used for Project Pele.

Key facts

Design
Antares Mark-0 (Microreactor)
Technology
Other · other
Operator(s)
Antares Nuclear
Vendor for linked design
Antares Nuclear
Location
Idaho National Laboratory, Materials and Fuels Complex (reactor pilot demonstrations) · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
DOE categorical exclusions place Aalo-X in the Critical Assembly Facility immediately south of the Materials and Fuels Complex (CX-271002), Mark-0 in building MFC-793 within the complex (CX-035340) and the Unity test in the NRAD facility at the complex (CX-271007). The pin reuses the recorded OpenStreetMap building center of the EBR-II containment at MFC (43.59507, −112.65716): a facility-area point that does not separate the three positions. Replaces an earlier Central Facilities Area point about 24 km to the west.
Coordinates
43.59507, -112.65716 · site-area point (approximate)
Electrical capacity
thermal only (no MWe) · scope: module
DOE describes Mark-0 as a critical assembly below 100 watts thermal.
Thermal capacity
100 watts thermal (zero-power limit)
Modules planned
1
Purpose
Research or test reactor
Construction start
Not recorded
Inclusion basis
Labeled microreactor
Confidence
medium
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.

Could not be confirmed on . Attempted official source: DOE: U.S. Department of Energy to Distribute Next Round of HALEU to U.S. Nuclear Industry. This is an access or status observation only; the record review date is unchanged.

Site and capacity notes

Antares Mark-0 at Idaho National Laboratory is recorded at Idaho National Laboratory, Materials and Fuels Complex (reactor pilot demonstrations), Idaho, United States. Operator: Antares Nuclear. Recorded vendor: Antares Nuclear. Stage: Commissioning. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Aalo-X at Idaho National Laboratory, Deployable Energy Unity at Idaho National Laboratory.

Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: building center of the EBR-II containment (DOME) at the Materials and Fuels Complex, 43.59507, −112.65716

This project is recorded as thermal only (no MWe). DOE describes Mark-0 as a critical assembly below 100 watts thermal. Modules planned: 1. Recorded thermal output is 100 watts thermal (zero-power limit).

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Operator or intended licensed owner
Reactor supplier
Customer or offtaker

Source-backed project statement Antares said on 4 June 2026 that the Mark-0 test contributes verification and validation data to the Department of War’s Project Pele, while describing the Army as a future end user. The same release places electricity and a military installation after this test, and the 26 January 2026 exclusion says Mark-0 is not anticipated to produce electricity. No terms are stated for the Project Pele data contribution, and no buyer of Mark-0 heat or electricity is named. The developer and the laboratory host are not treated as customers. Antares: Antares Achieves Criticality of Mark-0 Reactor; DOE Idaho categorical exclusion CX-035340 PDF: Antares R1 Mark-0

Funding and government decisions
  • Listed under a government program; not a disbursement; in effectDOE Reactor Pilot Program · sourceDOE lists this reactor's criticality demonstration under the Reactor Pilot Program.

Antares said on 22 September 2025 that it had executed its agreement with DOE to take a reactor critical by 4 July 2026, and DOE Idaho's categorical exclusion refers to an Other Transaction Agreement and a HALEU agreement between Antares and DOE. Neither source publishes the agreements' financial terms, and no funder or amount for Mark-0 is stated. Antares: Antares executes agreement with DOE to take reactor critical by July 2026; DOE Idaho categorical exclusion CX-035340 PDF: Antares R1 Mark-0

Fuel
  • Fuel supplier named for this projectBWX Technologies · sourceFabricated and delivered the TRISO fuel used for the Mark-0 criticality (announced 4 June 2026).
  • Fuel supplier named for this projectU.S. Department of Energy · sourceConditional commitment (26 Aug 2025) to provide HALEU for this pilot reactor under DOE's HALEU allocation; delivery not stated in this source.
  • Fuel form stated for Antares Mark-0TRISO
  • Enrichment stated for Antares Mark-019.75 wt%
Source-backed project statement

Antares' 4 June 2026 release says BWXT fabricated the TRISO fuel used for Mark-0's criticality, the same fuel as Project Pele, and DOE committed HALEU to Antares for this reactor on 26 August 2025. DOE Idaho's categorical exclusion says Mark-0 uses HALEU TRISO under a HALEU agreement in which the material is leased from DOE, and that the fuel will be kept in storage after Mark-0. The fuel was delivered and loaded, since the reactor reached criticality on 4 June 2026. Antares: Antares Achieves Criticality of Mark-0 Reactor; DOE: U.S. Department of Energy to Distribute Next Round of HALEU to U.S. Nuclear Industry; DOE Idaho categorical exclusion CX-035340 PDF: Antares R1 Mark-0

Site host or owner
Programs and agreements naming the project
Not found in the sources we checked (2): Contractor; Comparable schedule revision
Contractor

Antares' 4 June 2026 release says the Mark-0 demonstration was conducted in partnership with DOE, INL and BWXT, with the US Army observing, and that INL and DOE Idaho provided design, regulatory and facilities support. INL is the host and DOE the authorizing agency, and BWXT's role was fuel fabrication. No engineering or construction contractor is named for Mark-0. Antares: Antares Achieves Criticality of Mark-0 Reactor

Comparable schedule revision

Comparable schedule revision not established. Antares' September 2025 agreement with DOE set a goal of criticality by 4 July 2026, and Mark-0 reached criticality on 4 June 2026, ahead of that goal. No source read gives an earlier and later target for the same Mark-0 milestone, and the record's events contain no revision pair. Antares: Antares executes agreement with DOE to take reactor critical by July 2026; Antares: Antares Achieves Criticality of Mark-0 Reactor

Timeline

Recorded developments

Earlier developments (2)

Permissions and applications

Environmental decision

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(9 notes)
  • Evidence review. DOE says Antares Nuclear's Mark-0 completed a zero-power fueled criticality demonstration at Idaho National Laboratory (DOE page dated 4 June 2026), the first under the Reactor Pilot Program. DOE Idaho categorical exclusion CX-035340 (posting DOE-ID-INL-25-037, approved 26 January 2026) describes deploying and operating the Antares R1 Mark-0, a small high-temperature heat-pipe reactor configured for zero-power criticality testing, in building MFC-793 at INL's Materials and Fuels Complex; it is an environmental determination under the small-scale research category, not a construction or operating permission. DOE's July 2026 slides describe Mark-0 as a dry critical assembly below 100 watts thermal, while CX-035340 says it is not anticipated to produce thermal energy or electricity and has no power conversion or heat removal. The same slides list the preliminary documented safety analysis as approved in January 2026 and the documented safety analysis in April 2026 (months only); Antares says Mark-0 reached criticality under DOE authorization, and DOE's note of 14 July 2026 says readiness assessments were needed for DOE to authorize startup, but the startup authorization itself is not published. Preparatory work and nuclear installation are distinct: CX-035340 says structural modifications to MFC-793 are needed and that the reactor goes into a pit below grade (elsewhere in the same document, on grade) in the high bay, but no installation or modification dates are published. Antares' 22 September 2025 agreement with DOE targeted criticality by 4 July 2026, and CX-035340 planned operation by July 2026; criticality on 4 June 2026 met both. CX-035340 planned commissioning of under six months, an operational phase of under one month and then decommissioning of under six months; no fuel-loading date is given, the assembly produces no electricity, so generation, grid connection and commercial service do not apply, and no source after July 2026 states whether Mark-0 is still operating or has been decommissioned. The 2027 electricity test is the separate Mark-1 in the same facility with the same fuel batch. Stored values (one module, a 100-watt thermal zero-power limit, MFC-793 at INL) match the sources; no opened source names the organization that operates Mark-0, so the stored operator Antares rests on its role as developer, and the stored participant roles omit Antares as proposer. Last checked 19 Oct 2026. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); DOE Idaho categorical exclusion CX-035340 PDF: Antares R1 Mark-0; DOE: first advanced reactor criticality, Antares Mark-0; Antares: Antares Achieves Criticality of Mark-0 Reactor; DOE EM note on four Reactor Pilot criticality reviews; Antares: Antares executes agreement with DOE to take reactor critical by July 2026; Antares: From neutrons to electrons, our path to power
    What would change this

    DOE or Antares publishes the Mark-0 startup authorization, a notice that Mark-0 operation has ended or decommissioning has begun, or the Mark-1 authorization for the same facility. Next scheduled check: 19 Jan 2027.

  • Plant capacity (scope qualified). DOE describes Mark-0 as a critical assembly below 100 watts thermal. It has no power conversion or heat removal and no electrical output. The figure is a zero-power upper limit, not a rating. The 200-300 kWe on DOE's selection slide and the 1 MWth (about 270 kWe) figure describe the later Mark-1 or commercial R1, not Mark-0. Last checked 18 Oct 2026. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); DOE Idaho categorical exclusion CX-035340 PDF: Antares R1 Mark-0
    What would change this

    DOE or Antares publishes a measured Mark-0 power level. Next scheduled check: 18 Jan 2027.

  • Permission evidence appropriate to stage: Not disclosed in the reviewed evidence. The operating authority for Mark-0 is DOE's startup authorization after the readiness review, and no opened source publishes that instrument or its date. DOE's July 2026 slides list the preliminary documented safety analysis as approved in January 2026 and the documented safety analysis in April 2026 (months only); Antares says Mark-0 was authorized by DOE under the Reactor Pilot Program, and DOE's note of 14 July 2026 says readiness assessments were needed for DOE to authorize startup. The stored permission is the CX-035340 environmental exclusion of 26 January 2026, which is not an operating authority. This is DOE authorization, not an NRC license. Last checked 19 Oct 2026. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); Antares: Antares Achieves Criticality of Mark-0 Reactor; DOE EM note on four Reactor Pilot criticality reviews
    What would change this

    DOE publishes the Mark-0 DSA approval, startup authorization or readiness-review closure. Next scheduled check: 19 Jan 2027.

  • Construction start evidence: Not disclosed in the reviewed evidence. Mark-0 was installed in the existing INL building MFC-793 under a contract to build and demonstrate the reactor in an existing INL facility, and CX-035340 says structural modifications to the building are needed. No installation, modification or construction start date is published. CX-035340 places the reactor both below grade in a pit and on grade in the high bay. Last checked 19 Oct 2026. DOE Idaho categorical exclusion CX-035340 PDF: Antares R1 Mark-0; Antares: partnership with INL on facilities for testing and operating reactors (30 July 2025)
    What would change this

    Antares, INL or DOE dates the start of Mark-0 installation or the MFC-793 modifications. Next scheduled check: 19 Jan 2027.

  • Operation or grid target (type stated): Not applicable. First criticality, the operation milestone for this zero-power reactor, was achieved on 4 June 2026. No further operating milestone is planned for Mark-0; the electricity-producing test in 2027 is Mark-1, recorded separately, which uses the same facility and fuel batch. Last checked 19 Oct 2026. DOE: first advanced reactor criticality, Antares Mark-0; Antares: From neutrons to electrons, our path to power
    What would change this

    DOE or Antares reports Mark-0 decommissioning or a further Mark-0 test phase. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites: Not disclosed in the reviewed evidence. Mark-0 reached criticality on 4 June 2026. Antares and the July program slides next describe a Mark-1 electricity-producing test in 2027 in the same facility, and an Army speaker on 4 June 2026 called full-power electricity the next step before an Army installation. Those statements are about the later reactor, not a further decision for this zero-power assembly. The exclusion does not name a dated next authorization for Mark-0. Last checked 23 Oct 2026. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); Antares: Antares Achieves Criticality of Mark-0 Reactor
    What would change this

    A Department schedule for defueling, storage, or decommissioning of Mark-0, separate from the Mark-1 electricity test. Next scheduled check: 21 Jan 2027.

  • Permissions and public process. The Department of Energy Idaho office approved categorical exclusion CX-035340 for the Mark-0 experiment on 26 January 2026. The July 2026 program slides list a preliminary safety analysis approved in January 2026 and the documented safety analysis in April 2026, as months rather than days. Antares said on 4 June 2026 that criticality was under Department authorization. The exclusion is not an operating license, and the authorization instrument is not among the texts reviewed. Last checked 23 Oct 2026. DOE Idaho categorical exclusion CX-035340 PDF: Antares R1 Mark-0; DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); Antares: Antares Achieves Criticality of Mark-0 Reactor
    What would change this

    Publication of the Department startup authorization for Mark-0, or a day-dated copy of the documented safety analysis approval. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water). The 26 January 2026 exclusion places Mark-0 in the existing Sodium Components Maintenance Shop, building MFC-793, at Idaho National Laboratory, and says that building can deliver 10 gallons per minute at 40 psig. The same text both puts the reactor below grade in a pit and on grade in the high bay, so the position inside the building is not settled. It says Mark-0 is not anticipated to produce electricity, and it states no land lease and no export interconnection. Last checked 23 Oct 2026. DOE Idaho categorical exclusion CX-035340 PDF: Antares R1 Mark-0
    What would change this

    A land-use instrument for Mark-0, a correction of the pit versus on-grade description, or an export interconnection if one is ever proposed. Next scheduled check: 21 Jan 2027.

  • Spent fuel, waste and closure. The 26 January 2026 exclusion says that after Mark-0 the fuel will be kept in storage and that Mark-1 is planned to use the same fuel. It quotes the Other Transaction Agreement making Antares responsible for hazardous waste and for used-fuel removal and management until a final disposition pathway exists or the Department assumes ownership. That is a responsibility statement in the exclusion, not a named disposal site. No closure date is stated. Last checked 23 Oct 2026. DOE Idaho categorical exclusion CX-035340 PDF: Antares R1 Mark-0
    What would change this

    A disposition pathway, a Department decision to take title to Mark-0 used fuel, or a closure authorization. Next scheduled check: 21 Jan 2027.

Evidence dates

(4 of 12 sources with a publication or document date)
Latest dated listed source publication: Antares: first DOE authorization gate for Mark-1 (23 October 2026): 23 Oct 2026.Latest dated recorded event: Antares Mark-0 zero-power criticality: 4 Jun 2026.8 of 12 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(12)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Antares Mark-0 at Idaho National Laboratory — https://smrmap.com/projects/antares-mark-0-inl/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Antares Mark-0 at Idaho National Laboratory”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/antares-mark-0-inl/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.