Projects / United States · Commissioning
Deployable Energy Unity at Idaho National Laboratory
DOE reported a criticality demonstration of Deployable Energy's Unity at INL on 30 Jun 2026, the third DOE-authorized reactor to reach criticality before the goal of 4 July.
Current status
- How current
- General record check . Bounded evidence review . 3 of 7 listed sources have a publication or document date recorded here; the newest is 1 Jul 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: DOE Idaho categorical exclusion CX-271007 for the Unity zero-power test (15 Apr 2026). All permissions and applications
- Latest development
- 30 Jun 2026 · First criticality: Unity criticality demonstration. DOE fact sheet dates the INL demonstration 30 Jun 2026. Source: DOE fact sheet: The Golden Era of American Nuclear Energy Has Arrived. Updates entry
More on this development
Electrical output not stated.
- Next dated milestone
- Planned step: 2026 (target). Unity reactor-physics testing incl. passive shutdown and decay-heat tests (planned). This is not an achieved milestone. Source: DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212).
- Selected limitations
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage; Construction start evidence (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
- Same design
- 3 tracked: 1 commissioning, 1 siting, 1 announced. 5 tracked at commissioning across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Deployable Energy is not one of the ten Reactor Pilot Program companies; it takes part through DOE's Nuclear Energy Launch Pad. The test took place in an existing below-grade room of the Neutron Radiography Reactor (NRAD) facility at INL's Materials and Fuels Complex. DOE describes it as a critical experiment below 1 watt thermal. DOE Idaho categorical exclusion CX-271007, posting DOE-ID-INL-26-011, was approved on 15 Apr 2026 for a zero-power core test. The test bound is 0 MWth and 0 kWe, with light water as moderator and no active heat-transfer system. The same determination describes a future modular 1 MWe configuration with helium cooling; that rating is not stored as this test's output, and the helium system is not installed for the test. Fuel for the test is 4.95 percent U-235 low-enriched uranium dioxide, about 536 kg, with Zircaloy cladding. The exclusion is not an operating license. DOE's Reactor Pilot Program update of July 2026 lists the preliminary documented safety analysis as approved on 22 May 2026 and the documented safety analysis as approved on 11 June 2026.
Key facts
- Design
- Unity (Microreactor)
- Technology
- Other · helium
- Operator(s)
- Deployable Energy
- Vendor for linked design
- Deployable Energy
- Location
- Idaho National Laboratory, Materials and Fuels Complex (reactor pilot demonstrations) · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
DOE categorical exclusions place Aalo-X in the Critical Assembly Facility immediately south of the Materials and Fuels Complex (CX-271002), Mark-0 in building MFC-793 within the complex (CX-035340) and the Unity test in the NRAD facility at the complex (CX-271007). The pin reuses the recorded OpenStreetMap building center of the EBR-II containment at MFC (43.59507, −112.65716): a facility-area point that does not separate the three positions. Replaces an earlier Central Facilities Area point about 24 km to the west. - Coordinates
- 43.59507, -112.65716 · site-area point (approximate)
- Electrical capacity
- thermal only (no MWe) · scope: module
- Thermal capacity
- 0 MWth (zero-power limit)
- Purpose
- Research or test reactor
- Construction start
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Deployable Energy Unity at Idaho National Laboratory is recorded at Idaho National Laboratory, Materials and Fuels Complex (reactor pilot demonstrations), Idaho, United States. Operator: Deployable Energy. Recorded vendor: Deployable Energy. Stage: Commissioning. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Aalo-X at Idaho National Laboratory, Antares Mark-0 at Idaho National Laboratory.
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: building center of the EBR-II containment (DOME) at the Materials and Fuels Complex, 43.59507, −112.65716
This project is recorded as thermal only (no MWe). Modules planned: 1. Recorded thermal output is 0 MWth (zero-power limit).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorDeployable Energy
- Reactor supplier
- Vendor for the linked designDeployable Energy
- Funding and government decisions
- Listed under a government program; not a disbursement; in effectDOE Reactor Pilot Program · sourceDOE lists this reactor's criticality demonstration under the Reactor Pilot Program.
The 15 April 2026 exclusion, the July 2026 program slides, and the 1 July 2026 report describe the test and its criticality. They state no funder, instrument, or amount paid for this Unity test. Participation through the laboratory is not itself a disclosed payment. DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality
- Fuel
- Fuel form stated for UnityUO2 annular pellets, Zircaloy cladding
- Enrichment stated for Unity4.95% U-235 (LEU)
Source-backed project statement
The 15 April 2026 exclusion says about 536 kilograms of uranium dioxide enriched to 4.95 percent uranium-235 will be shipped to Idaho National Laboratory for the test, and that after the test the fuel will be disassembled into approved storage for future use. The July slides describe the same experiment’s fuel as below 5 percent uranium-235. No fuel manufacturer or supplier is named. Criticality on 30 June 2026 shows the test was fueled; the exclusion’s shipment sentence is the plan, not a named delivery receipt. DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality; DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212)
- Site host or owner
- Site hostIdaho National Laboratory · source
Not found in the sources we checked (3): Customer or offtaker; Contractor; Comparable schedule revision
- Customer or offtaker
The Department of Energy exclusion approved on 15 April 2026 says the Unity activity is a zero-power test to confirm the core’s predicted neutronic performance, and that it will not generate electricity or usable heat. The July 2026 program slides call it a critical experiment below 1 watt thermal with no electrical output. Neither those texts nor the 1 July 2026 Nuclear News report names a research user, test beneficiary, or service customer. The developer and the laboratory host are not treated as customers. DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality; DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212)
- Contractor
The 15 April 2026 exclusion says Deployable Energy proposes the zero-power test inside an existing laboratory room. It names no engineering, FEED, or construction contractor, and the 1 July 2026 report does not add one. DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality
- Comparable schedule revision
Comparable schedule revision not established. The July 2026 slides list a preliminary safety analysis on 22 May 2026, the documented safety analysis on 11 June 2026, and criticality on 30 June 2026 as achieved dates. Full-power testing by 4 July 2027 is a later and different milestone. No source reviewed gives two forecasts for the same Unity milestone. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212)
Not recorded in SMRMap's reviewed evidence (2): Project proposer or applicant; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Programs and agreements naming the project
Timeline
Recorded developments
- · First criticality
Unity criticality demonstration - · Recorded development
DOE approves the Unity critical experiment documented safety analysis - · Recorded development
DOE approves the Unity critical experiment preliminary documented safety analysis - · Environmental decision recorded
Environmental decision recorded: DOE Idaho categorical exclusion CX-271007 for the Unity zero-power test
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Unity reactor-physics testing incl. passive shutdown and decay-heat tests (planned)
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Environmental decision
- DOE Idaho categorical exclusion CX-271007 for the Unity zero-power test
Environmental decision · Issued / approved · U.S. Department of Energy, Idaho Operations Office · decided 15 Apr 2026
Approved 15 April 2026 under posting DOE-ID-INL-26-011. Covers a zero-power criticality test bounded at 0 MWth and 0 kWe. It does not authorize the future 1 MWe configuration and is not an operating license.
Sources: DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(8 notes)
- Evidence review. Deployable Energy's Unity critical experiment is a zero-power criticality test of the Unity microreactor core. It was held in an existing below-grade room of the Neutron Radiography Reactor (NRAD) facility at INL's Materials and Fuels Complex (DOE-ID categorical exclusion DOE-ID-INL-26-011, approved 15 April 2026). The exclusion bounds the test at 0 MWth and 0 kWe. The test does not generate electricity, usable heat or sustained power. It uses a temporary water-tank fixture, and fuel assemblies are built onsite. The helium coolant system, turbine and balance of plant are not included. The modular 1 MWe unit is the future design, not this test's output. The exclusion is an environmental decision, not an operating authority. DOE's July 2026 pilot-program slides list the preliminary documented safety analysis as approved on 22 May 2026 and the documented safety analysis on 11 June 2026. They list criticality as achieved on 30 June 2026 and describe the experiment as a below-1-watt thermal, no-electrical-output test. DOE's 24 July 2026 fact sheet and its Aalo-X release count Unity among the DOE-authorized reactors that reached criticality in June. The DOE startup-authorization document itself was not opened. ANS (1 July 2026) notes that Deployable Energy takes part through DOE's Nuclear Energy Launch Pad, not the Reactor Pilot Program. Criticality here is not electricity generation or commercial service. The exclusion expected a test period of about 20 days, after which the temporary fixture would be removed and no permanent reactor installation would remain. DOE's slides plan reactor-physics testing in 2026. Full-power testing by July 2027 belongs to the separate DOME record. No opened source after July 2026 reports the test's completion or the removal of hardware. Stored values (0 MWth zero-power bound, no electrical rating) match the sources. Last checked 19 Oct 2026. DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality; DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); DOE fact sheet: The Golden Era of American Nuclear Energy Has Arrived; ANS Nuclear Newswire: Deployable Energy achieves criticality at INL; DOE: fourth criticality, Aalo-X
What would change this
A DOE, INL or Deployable Energy notice that the NRAD zero-power campaign is complete and the test fixture removed, or of a new Unity phase at NRAD. Next scheduled check: 19 Jan 2027.
- Permission evidence appropriate to stage. DOE's July 2026 slides list the Unity critical experiment's preliminary documented safety analysis as approved on 22 May 2026 and its documented safety analysis on 11 June 2026, before criticality on 30 June 2026. DOE's 1 July 2026 release calls Unity the third DOE-authorized advanced reactor to go critical and says the Nuclear Energy Launch Pad leverages DOE authorization. The DOE approval letters and startup authorization were not found among the sources read, so no operating-authority record is stored. DOE-ID categorical exclusion DOE-ID-INL-26-011 (approved 15 April 2026) is the stored environmental decision and covers the zero-power test only. Last checked 13 Nov 2026. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); DOE: U.S. Department of Energy Meets President Trump's Goal, Delivers Third Advanced Reactor Criticality; DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality
What would change this
DOE publishes the Unity critical-experiment DSA approval or startup authorization. Next scheduled check: 12 Feb 2027.
- Construction start evidence: Not disclosed in the reviewed evidence. The critical experiment uses an existing below-grade NRAD room and a temporary water-tank fixture. Fuel assemblies are built onsite before testing, with short installation and readiness activities beforehand. The fixture is to be removed afterwards. No opened source dates the start of installation or fixture assembly. Last checked 19 Oct 2026. DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality
What would change this
DOE, INL or Deployable Energy dates the installation of the Unity test core. Next scheduled check: 19 Jan 2027.
- Operation or grid target (type stated): Not applicable. This record is a zero-power critical experiment. DOE's exclusion says it will not generate electricity, usable heat or sustained power, so an electricity, grid or commercial-operation target cannot apply. Its operation milestone, first criticality, was achieved on 30 June 2026. DOE plans reactor-physics testing in 2026. Full-power and transient testing by 4 July 2027 belong to the separate DOME record (Deployable Energy Unity full-power test in INL's DOME (2027)). Last checked 19 Oct 2026. DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality; DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212)
What would change this
Completion or removal of the NRAD test hardware, or a DOE notice of a new Unity phase at NRAD. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites: Not disclosed in the reviewed evidence. Criticality was achieved on 30 June 2026. Deployable told Nuclear News that it would enter a phased testing program including full-power operations, and the slides list full-power testing by 4 July 2027. The April exclusion authorizes only the zero-power test and does not set those later tests as an approved next decision. No source reviewed names the next authorization for this experiment and its prerequisites. Last checked 23 Oct 2026. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); ANS Nuclear Newswire: Deployable Energy achieves criticality at INL; DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality
What would change this
A Department authorization for any testing beyond this zero-power experiment, or a schedule for defueling it. Next scheduled check: 21 Jan 2027.
- Permissions and public process. The Idaho office approved categorical exclusion CX-271007 for the Unity zero-power test on 15 April 2026. The July slides list safety-analysis approvals on 22 May and 11 June 2026 before criticality on 30 June 2026. The exclusion is an environmental determination, not an operating license, and the startup authorization instrument is not among the texts reviewed. Last checked 23 Oct 2026. DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality; DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212)
What would change this
Publication of the Department startup authorization for the Unity test. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). The exclusion places the test in an existing below-grade room of the Neutron Radiography Reactor at the Materials and Fuels Complex and says no new permanent utility extensions are required. It sets electrical output at 0 kilowatts-electric, so no export interconnection is involved. Light water is the moderator inside the test vessel. No land lease or separate water contract is stated. Last checked 23 Oct 2026. DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality
What would change this
A land-use instrument, if one exists apart from use of the existing room, or a water contract beyond the moderator inventory. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. The exclusion says that after the test the fuel assemblies will be disassembled and the fuel placed in approved storage at the Materials and Fuels Complex for future use. It also says industrial wastewater will be characterized before a disposal pathway is approved by the site waste service. That is the end-of-test handling in the exclusion, not a final repository or a closure date. Last checked 23 Oct 2026. DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality
What would change this
A later decision on the future use of this fuel, or a disposal site for it. Next scheduled check: 21 Jan 2027.
Evidence dates
(3 of 7 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(7)
- DOE fact sheet: The Golden Era of American Nuclear Energy Has Arrived (government, accessed 1 Oct 2026)
- DOE EM note on four Reactor Pilot criticality reviews (government, accessed 1 Oct 2026)
- DOE Idaho categorical exclusion CX-271007 PDF: Unity zero-power criticality (government, dated 15 Apr 2026, accessed 4 Oct 2026)
- DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212) (government, accessed 15 Oct 2026)
- ANS Nuclear Newswire: Deployable Energy achieves criticality at INL (news report, published 1 Jul 2026, accessed 18 Oct 2026)
- DOE: fourth criticality, Aalo-X (government, accessed 1 Oct 2026)
- DOE: U.S. Department of Energy Meets President Trump's Goal, Delivers Third Advanced Reactor Criticality (government, published 1 Jul 2026, accessed 28 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Deployable Energy Unity at Idaho National Laboratory — https://smrmap.com/projects/deployable-energy-unity-inl/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Deployable Energy Unity at Idaho National Laboratory”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/deployable-energy-unity-inl/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.