Projects / Russia · Operating
Akademik Lomonosov floating NPP
Floating heat-and-power plant at Pevek with two KLT-40S reactor units.
Current status
- How current
- General record check . Bounded evidence review . 4 of 10 listed sources have a publication or document date recorded here; the newest is 19 Aug 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- 22 May 2020 · Commercial operation: Akademik Lomonosov commercial operation (both units). The project field commercial_operation already holds this date; the record has no event row for it. Source: IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026. Updates entry
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage (reviewed: source unavailable; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Pressurized water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
IAEA PRIS lists each unit at 150 MWth, 35 MWe gross and 32 MWe net, with construction start on 15 April 2007, first grid connection on 19 December 2019 and commercial operation on 22 May 2020, and names Concern Rosenergoatom as operator and owner. The 70 MWe gross and 300 MWth recorded here are the two units combined. NucNet reported on 27 June 2019, relaying Rosatom, that Rosenergoatom had received a ten-year Rostekhnadzor license to operate the plant, valid until 2029; the license document has not been reviewed, and its exact issue date and number remain unconfirmed. IAEA PRIS lists 9 November 2018 as the latest operating-license date for both units, which differs from the June 2019 report; neither date is confirmed by an opened license document.
Key facts
- Design
- KLT-40S (SMR)
- Technology
- Pressurized water reactor (PWR) · light water. The IAEA's 2018 SMR booklet describes a four-loop primary circuit, so no integral layout is recorded.
- Reactor vessel of this design
- 4.8 m tall, 2 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 147.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Rosenergoatom
- Vendor for linked design
- Rosatom
- Location
- Pevek floating NPP berth · Russia · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the Akademik Lomonosov floating units at Pevek (CC BY 4.0, derived from GEM's tracker); berth-area point. Replaces an earlier hand-rounded point. - Coordinates
- 69.7086, 170.3011 · site-area point (approximate)
- Electrical capacity
- 70 MWe (gross) · scope: plant
- Thermal capacity
- 300 MWth (nameplate; basis unspecified)
- Purpose
- Power plant
- Construction start
- 15 Apr 2007Akademik Lomonosov construction start (both units, IAEA PRIS)
- Inclusion basis
- SMR by design class
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Akademik Lomonosov floating NPP is recorded at Pevek floating NPP berth, Chukotka, Russia. Operator: Rosenergoatom. Recorded vendor: Rosatom. Stage: Operating. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'akademik-lomonosov-nuclear-power-plant-1' (69.7086, 170.3011)
Recorded electrical output is 70 MWe (gross), scope plant. Modules planned: 2. Recorded thermal output is 300 MWth (nameplate; basis unspecified). The linked design record states 35 MWe (gross); the project figure is kept separate.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorRosenergoatom
- Reactor supplier
- Vendor for the linked designRosatom
- Customer or offtaker
Source-backed project statement On 27 June 2019 NucNet, relaying Rosatom, reported that coastal work was underway in Pevek to attach Akademik Lomonosov to city power and heating grids and that supply of energy to Pevek was scheduled for December. The 19 August 2026 Rosatom corporate article says the station keeps operating during staggered refueling and that consumers have no break in energy supply. Neither text names a utility, a contract, or a separate heat buyer. NucNet: Regulator Grants Operating Licence For Russia's First Floating Nuclear Station; Strana Rosatom: Rosatom delivers fresh nuclear fuel for the floating nuclear plant (19 August 2026)
- Contractor
- Construction contractorBaltic Shipyard (Baltiysky Zavod) · sourceBuilt the floating power unit after Rosatom moved the contract from Sevmash in August 2008; the vessel left the yard on 28 April 2018.
Source-backed project statement
World Nuclear News reported on 21 May 2018 that Rosatom transferred the Akademik Lomonosov construction contract from Sevmash to Baltic Shipyard in August 2008. This supports the recorded Baltic Shipyard construction role; the contract instrument was not reviewed. WNN: Floating plant arrives at Murmansk for fuelling
- Fuel
- Fuel supplier named for this projectTVEL (Rosatom Fuel Division) · sourceDelivered a fresh core for the starboard reactor to Pevek, reported 19 August 2026; fabricated at the Machine-Building Plant in Elektrostal.
Source-backed project statement
On 19 August 2026 a Rosatom corporate article reported that the fuel division had delivered nuclear fuel to Pevek for one of the two Akademik Lomonosov units, and that the core for the starboard reactor was made at the Machine-Building Plant in Elektrostal. The article says the starboard unit was first refueled at the end of 2023 and the port unit in 2024. The new delivery is to Pevek, and the article does not say that core has been loaded. Strana Rosatom: Rosatom delivers fresh nuclear fuel for the floating nuclear plant (19 August 2026)
- Programs and agreements naming the project
- Feasibility or siting study; status not establishedRosatom early study of an additional modernised floating power unit for Pevek (Chukotka request)
- National plan; activeRosatom small nuclear power plant program (62 small reactors by 2039, four more floating plants)
- Comparable schedule revision
Source-backed project statement Rosenergoatom's annual report for 2013 planned commissioning of the Pevek floating station in 2018; its report for 2014 planned the same milestone for 2019. The reports document a changed historical target, but the dates on which those forecasts were issued and the reason for the change are not established by the saved evidence. Report years and board preapproval years are not used as forecast statement dates. Delivery of the floating unit, station commissioning, grid connection and commercial operation are distinct milestones. PRIS achieved dates are not further forecasts. NucNet: Regulator Grants Operating Licence For Russia's First Floating Nuclear Station; IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026; Rosenergoatom annual report for 2013: Pevek commissioning target; Rosenergoatom annual report for 2014: Pevek commissioning target
Not found in the sources we checked (1): Funding and government decisions
- Funding and government decisions
The 27 June 2019 NucNet report, the IAEA PRIS rows for the two Akademik Lomonosov units at Pevek, and the 19 August 2026 Rosatom fuel article describe a reported operating license, plant operation, and a fuel delivery. They do not state a project cost or an amount paid for the plant. NucNet: Regulator Grants Operating Licence For Russia's First Floating Nuclear Station; IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026; Strana Rosatom: Rosatom delivers fresh nuclear fuel for the floating nuclear plant (19 August 2026)
Not recorded in SMRMap's reviewed evidence (2): Project proposer or applicant; Site host or owner
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Site host or owner
Timeline
Recorded developments
- · Commercial operation
Akademik Lomonosov commercial operation (both units) - · Grid connection
Akademik Lomonosov grid connection (both units) - · Regulatory step
NucNet reports receipt of Akademik Lomonosov operating license - · First criticality
Akademik Lomonosov Unit 2 first criticality - · First criticality
Akademik Lomonosov Unit 1 first criticality
Earlier developments (1)
- · Construction start
Akademik Lomonosov construction start (both units, IAEA PRIS)
Dates on the project record: Commercial operation: 22 May 2020.
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. Akademik Lomonosov is a floating nuclear power station at Pevek in Chukotka with two KLT-40S reactor units. NucNet (27 June 2019) describes a 21,000-tonne vessel whose units each generate 35 MW of electricity. It was the first of a proposed fleet supplying energy, heat and desalinated water to remote areas. IAEA PRIS (read 19 October 2026) lists AKADEMIK LOMONOSOV-1 and -2 as operational at PEVEK. Each unit is rated 150 MWt, 35 MWe gross and 32 MWe net (30 MWe design net). Both units have a construction date of 15 April 2007, a grid connection on 19 December 2019 and commercial operation on 22 May 2020. Criticality came on 2 November 2018 for unit 1 and 8 November 2018 for unit 2. Criticality, grid connection and commercial service are separate milestones. PRIS names Joint Stock Company 'Concern Rosenergoatom' as operator and owner. NucNet, relaying Rosatom, reports that Rostekhnadzor issued Rosenergoatom a ten-year license to operate the plant until 2029. The license document was not opened, and Rosatom's site timed out when checked. PRIS gives 9 November 2018 as the latest operating-license date for both units, earlier than the June 2019 report. The two dates are kept apart, and neither is confirmed by an opened license. Shore-side work at Pevek to connect the plant to the town's power and heat grids is described in 2019. That is separate from building the reactor units. No opened source states a plant total. The stored 70 MWe gross and 300 MWth are the per-unit ratings added together; see the proposed changes. Rosatom's newspaper Strana Rosatom (19 August 2026) reports operations. The starboard reactor was first refuelled at the end of 2023 and the port reactor in 2024, so both completed their first core campaign. Rosatom's fuel division has delivered a new core to Pevek for the starboard reactor. The port reactor's reload is planned for 2027. The plant keeps operating because the reactors are refuelled one at a time. These are refuelling outages within operation. They are not new licensing steps. No opened source describes a pending regulatory decision. Last checked 19 Oct 2026. NucNet: Regulator Grants Operating Licence For Russia's First Floating Nuclear Station; IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026; Akademik Lomonosov floating NPP; Strana Rosatom: Rosatom delivers fresh nuclear fuel for the floating nuclear plant (19 August 2026)
What would change this
A Rosatom or Rosenergoatom notice of the starboard reactor's second core reload and restart, a readable Rostekhnadzor register entry for the operating license, or a license renewal notice before 2029. Next scheduled check: 19 Jan 2027.
- Permission evidence appropriate to stage: Source unavailable. NucNet (27 June 2019), relaying Rosatom, reports that Rostekhnadzor issued Rosenergoatom a ten-year license to operate Akademik Lomonosov until 2029. IAEA PRIS gives 9 November 2018 as the latest operating-license date for both units. The license instrument, number and issue date are unopened. Rosatom's site timed out when checked, and no regulator register was readable. The press report and the PRIS date differ, and neither is a license document. So no regulatory action is stored, and the June 2019 report stays an undated-instrument event. Last checked 19 Oct 2026. NucNet: Regulator Grants Operating Licence For Russia's First Floating Nuclear Station; IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026; Akademik Lomonosov floating NPP
What would change this
A readable Rosatom or Rosenergoatom release, or a Rostekhnadzor register entry, naming the license number, issue date and expiry; or a renewal notice before 2029. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The 19 August 2026 Rosatom article says refueling of the port-side reactor is planned for 2027. The same article reports delivery of fresh fuel to Pevek for one unit and manufacture of the starboard core, and it does not say that core has been loaded. Last checked 23 Oct 2026. Strana Rosatom: Rosatom delivers fresh nuclear fuel for the floating nuclear plant (19 August 2026)
What would change this
A report that the 2027 port-side refueling was done, or that the fresh starboard core was loaded. Next scheduled check: 21 Jan 2027.
- Permissions and public process. On 27 June 2019 NucNet, relaying Rosatom, reported that Rostekhnadzor had issued Rosenergoatom a 10-year license to operate Akademik Lomonosov until 2029. The article states no license number and no issue date. IAEA PRIS lists 9 November 2018 as the latest operating-license date for both units. The license document was not among these texts, so the dates are not reconciled in this answer. Last checked 23 Oct 2026. NucNet: Regulator Grants Operating Licence For Russia's First Floating Nuclear Station; IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026
What would change this
The Rostekhnadzor operating-license instrument, including its number and issue date. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). IAEA PRIS places both Akademik Lomonosov units at Pevek and records grid connection on 19 December 2019. On 27 June 2019 NucNet reported that coastal infrastructure to attach the plant to city power and heating grids was still underway. The 19 August 2026 Rosatom article places the operating plant in Chaunskaya Bay at Pevek and does not state a land title, a grid agreement, or a water right. Last checked 23 Oct 2026. IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026; NucNet: Regulator Grants Operating Licence For Russia's First Floating Nuclear Station; Strana Rosatom: Rosatom delivers fresh nuclear fuel for the floating nuclear plant (19 August 2026)
What would change this
A berth agreement, grid-connection contract, or water right for the Pevek mooring. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. Rosatom's November 2023 newsletter reports that, during the first reactor's refuelling, the removed core had been placed in spent-fuel-assembly storage on the floating plant. This establishes company-reported onboard storage at that time. It does not establish subsequent transfers, the location of fuel removed in later refuellings, a final disposal route or closure arrangements. The August 2026 fuel report does not resolve those later questions. Last checked 28 Oct 2026. Strana Rosatom: Rosatom delivers fresh nuclear fuel for the floating nuclear plant (19 August 2026); Rosatom Newsletter: Akademik Lomonosov refuelling (issue 271, November 2023)
What would change this
An operator or regulator record of later spent-core storage or transfer, final disposition, or closure arrangements for Akademik Lomonosov. Next scheduled check: 21 Jan 2027.
Evidence dates
(4 of 10 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(10)
- Akademik Lomonosov floating NPP (company, accessed 1 Oct 2026)
- IAEA Power Reactor Information System (PRIS) (IAEA/NEA, accessed 1 Oct 2026)
- IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026 (IAEA/NEA, accessed 18 Oct 2026)
- IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026) (IAEA/NEA, accessed 9 Oct 2026)
- NucNet: Regulator Grants Operating Licence For Russia's First Floating Nuclear Station (news report, published 27 Jun 2019, accessed 16 Oct 2026)
- Strana Rosatom: Rosatom delivers fresh nuclear fuel for the floating nuclear plant (19 August 2026) (company, published 19 Aug 2026, accessed 19 Oct 2026)
- WNN: Floating plant arrives at Murmansk for fuelling (news report, published 21 May 2018, accessed 21 Oct 2026)
- Rosenergoatom annual report for 2013: Pevek commissioning target (company, accessed 24 Oct 2026)
- Rosenergoatom annual report for 2014: Pevek commissioning target (company, accessed 24 Oct 2026)
- Rosatom Newsletter: Akademik Lomonosov refuelling (issue 271, November 2023) (company, published Nov 2023, accessed 28 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Akademik Lomonosov floating NPP — https://smrmap.com/projects/akademik-lomonosov/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Akademik Lomonosov floating NPP”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/akademik-lomonosov/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.