Projects / United States · Siting

BlueCore BC-15 floating plant proposal at the Port of Long Beach

BlueCore Energy's BC-15 is a floating unit proposed for the Port of Long Beach in the United States, at the siting stage.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . 2 of 4 listed sources have a publication or document date recorded here; the newest is 13 Oct 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • No operator is recorded.
  • No map pin is shown for this record.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Pressurized water reactor. How it works, with a 3D view.
Schematic of Rolls-Royce SMR, this type's example. On the left, a reactor vessel holds a core of fuel assemblies, with control rod drives above its head.
Schematic of Rolls-Royce SMR, this type's example.

Description

BlueCore proposed a full-power demonstration of its barge-mounted reactor (45 MWt, about 15 MWe gross) at the Port of Long Beach and names the port as the plant's operating location in NRC pre-application documents. This is a siting-stage proposal, not a permit or nuclear construction start. DOE did not select the demonstration in the current Launch Pad round, and the port's current lease covers only non-nuclear prototype work without nuclear fuel. On 13 October 2026 BlueCore announced a purchase of 4.95%-enriched uranium hexafluoride held at a US fuel facility outside California. The company describes its Long Beach hardware as a non-fueled prototype and says future operating sites and configurations remain to be determined. The purchase does not establish fuel loading or resolve the earlier full-power site proposal. The October release names WMC as seller of the enriched uranium for first-system development; it gives no quantity or storage-facility name. NRC/Coast Guard engagement and ABS classification activity are separate from construction contracting.

Key facts

Design
BlueCore BC-15 (SMR)
Technology
Pressurized water reactor (PWR) · light water. The NRC's pre-application page says BlueCore is developing a 45 MWt pressurized water reactor, at pre-application stage.
Operator(s)
Not recorded
Vendor for linked design
BlueCore Energy
Location
Port of Long Beach · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
The sources name this place but publish no coordinate for it, so no pin is shown.
Coordinates
Named site, no map pin
Electrical capacity
15 MWe (gross) · scope: module
Thermal capacity
45 MWth (nameplate; basis unspecified)
Modules planned
1
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
low
Record reviewed
9 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

BlueCore BC-15 floating plant proposal at the Port of Long Beach is recorded at Port of Long Beach, California, United States. Operator: No operator is recorded. Recorded vendor: BlueCore Energy. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); named site, no map pin.

Recorded electrical output is 15 MWe (gross), scope module. Modules planned: 1. Recorded thermal output is 45 MWth (nameplate; basis unspecified).

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Reactor supplier
Fuel
Project fuel information is described in the source-backed statement below.

Source-backed project statement Bluecore reported on 13 October 2026 that it purchased uranium hexafluoride enriched to 4.95% uranium-235 from WMC for development of its first system. It said the material was held at an unnamed US fuel facility outside California. This is company/first-system procurement context, not fuel fabrication, loading or storage at Long Beach, whose prototype is described as non-fueled. BlueCore Energy secures low-enriched uranium; NRC: BlueCore Energy (pre-application); Port of Long Beach: CEQA notice of exemption, BlueCore lease

Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
Customer or offtaker

The NRC's BlueCore pre-application page names the Port of Long Beach as the reference operating location, which is a site, not a buyer. BlueCore's 13 October 2026 release says future systems could support ports, AI data centers and coastal infrastructure and that future sites will be determined later. Neither names a buyer, quantity or agreement for power or heat. NRC: BlueCore Energy (pre-application); BlueCore Energy secures low-enriched uranium

Contractor

Bluecore’s October 2026 release describes NRC and Coast Guard engagement and an ABS maritime-classification pathway. These are regulatory and classification relationships, not construction-contractor awards. The port notice’s planned INL testing does not establish a full-power operating site or an issued reactor license. NRC: BlueCore Energy (pre-application); Port of Long Beach: CEQA notice of exemption, BlueCore lease; BlueCore Energy secures low-enriched uranium

Funding and government decisions

BlueCore's 13 October 2026 release refers to the company's $50 million seed financing announced weeks earlier. That is company financing, not money committed to the Long Beach demonstration. The Port of Long Beach's July 2026 lease notice states areas and a lease term but no rent or project cost. BlueCore Energy secures low-enriched uranium; Port of Long Beach: CEQA notice of exemption, BlueCore lease

Comparable schedule revision

Comparable schedule revision not established. The NRC page dates BlueCore's pre-application engagement from July 2026, the port's lease notice was posted 17 July 2026, and BlueCore's 13 October 2026 release says future sites and configurations will be determined later. None of these states an earlier and a later date for the same Long Beach construction or operation milestone. NRC: BlueCore Energy (pre-application); Port of Long Beach: CEQA notice of exemption, BlueCore lease; BlueCore Energy secures low-enriched uranium

Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Operator or intended licensed owner
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)
  • Evidence review. The NRC's pre-application page (last updated 2 October 2026) says BlueCore has been in pre-application engagement since July 2026 towards a future 10 CFR Part 50 application for its Nautilus floating nuclear power plant, a 45 MWt pressurized water reactor on a non-self-propelled barge using the BC-15 reactor, and that the reference operating location is the Port of Long Beach, California. The page lists BlueCore's letter of intent (ML26223A527) and a September 2026 regulatory engagement plan (ML26261A477); those documents were not opened here. The Port of Long Beach's notice of exemption, posted on 17 July 2026, covers lease TR-26-06 for part of the D48 Warehouse at Pier D, Berth D48 and submerged land for mooring a barge, for a non-nuclear prototype module with no nuclear fuel used. BlueCore's release of 13 October 2026 says it holds 4.95%-enriched UF6 at a fuel facility outside California, operates no reactor and stores no fuel at its Long Beach headquarters, and that future sites and operating configurations will be determined through federal regulatory, maritime, environmental, security and safety processes. The 45 MWt, the BC-15 design, BlueCore as vendor and the siting stage stay; the next documentary decision is the Part 50 application or a filing fixing the operating location. The stored 15 MWe gross figure and the DOE Launch Pad statement are not in any opened text and rest on the unopened ADAMS documents. Last checked 19 Oct 2026. NRC: BlueCore Energy (pre-application); Port of Long Beach: CEQA notice of exemption, BlueCore lease; BlueCore Energy secures low-enriched uranium
    What would change this

    BlueCore's 10 CFR Part 50 application, or the ADAMS letter ML26223A527 and engagement plan ML26261A477 opened and checked for the operating location and electrical rating. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed: Sources conflict. The NRC page names the Port of Long Beach as the reference operating location for the floating plant, but BlueCore's later release of 13 October 2026 says future sites and operating configurations will be determined through federal regulatory, maritime, environmental, security and safety processes. The only parcel named in the opened sources, Pier D, Berth D48, is leased for a non-nuclear prototype without nuclear fuel, so it is not the plant site. Because the regulator's reference location and the company's latest statement diverge, the site precision is left unchanged. Last checked 19 Oct 2026. NRC: BlueCore Energy (pre-application); BlueCore Energy secures low-enriched uranium; Port of Long Beach: CEQA notice of exemption, BlueCore lease
    What would change this

    BlueCore's Part 50 application or an NRC/Coast Guard document fixing the plant's operating berth, or a BlueCore statement withdrawing Long Beach as the operating location. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. BlueCore's September 2026 regulatory engagement plan lays out pre-application phases from August to December 2026 and January to May 2027, then an application submittal, followed by a post-application phase in the second half of 2027 through 2028. Under its preferred route the first application would be for a construction permit. These are BlueCore's planned phases; the NRC notes no review was requested of the plan. Last checked 23 Oct 2026. Nautilus Floating Nuclear Power Plant Regulatory Engagement Plan, BLU-PLAN-000001 Revision 0 (non-proprietary)
    What would change this

    BlueCore's construction permit application filing, or a revised engagement plan schedule. Next scheduled check: 23 Apr 2027.

  • Permissions and public process. The NRC says it has been in pre-application activities with BlueCore since July 2026, and names the Port of Long Beach as the reference operating location for its barge-mounted BC-15. BlueCore's September 2026 regulatory engagement plan prefers the two-step construction permit and operating license route under 10 CFR Part 50, alongside marine classification and U.S. Coast Guard vessel authorization. The Port's California environmental notice covers only a two-year lease for a non-fueled prototype. No NRC application or permit exists yet. Last checked 23 Oct 2026. NRC: BlueCore Energy (pre-application); Nautilus Floating Nuclear Power Plant Regulatory Engagement Plan, BLU-PLAN-000001 Revision 0 (non-proprietary); Port of Long Beach: CEQA notice of exemption, BlueCore lease
    What would change this

    A BlueCore construction permit application to the NRC, or a Port of Long Beach approval for a fueled reactor. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). The Port of Long Beach's 2026 California environmental notice describes lease TR-26-06 giving BlueCore about 10,000 square feet of the D48 warehouse, adjacent paved land and about 6,000 square feet of submerged land for mooring a barge, for two years with a three-year option. The lease is for building and testing a non-fueled prototype module, with nuclear testing at Idaho National Laboratory. No site arrangement for an operating reactor, or any grid or shore-power connection, is stated. Last checked 23 Oct 2026. Port of Long Beach: CEQA notice of exemption, BlueCore lease
    What would change this

    A Port lease, permit or agreement covering a fueled BC-15 or its grid connection. Next scheduled check: 23 Apr 2027.

  • Spent fuel, waste and closure: Not disclosed in the reviewed evidence. BlueCore's September 2026 regulatory engagement plan submitted to the NRC has a section on spent fuel management and refuelling operations, but its public version withholds that section's content as proprietary. The NRC pre-application page and the Port's lease notice do not address spent fuel. No public spent-fuel arrangement is available from these sources. Last checked 23 Oct 2026. Nautilus Floating Nuclear Power Plant Regulatory Engagement Plan, BLU-PLAN-000001 Revision 0 (non-proprietary)
    What would change this

    A public NRC filing or BlueCore statement describing spent-fuel storage or removal for the BC-15. Next scheduled check: 23 Apr 2027.

Evidence dates

(2 of 4 sources with a publication or document date)
Latest dated listed source publication: BlueCore Energy secures low-enriched uranium: 13 Oct 2026.Latest dated recorded event: no date recorded.2 of 4 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(4)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: BlueCore BC-15 floating plant proposal at the Port of Long Beach — https://smrmap.com/projects/bluecore-long-beach/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “BlueCore BC-15 floating plant proposal at the Port of Long Beach”. Record reviewed 9 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/bluecore-long-beach/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.