Projects / Canada · Construction

Darlington BWRX-300 Unit 1

Ontario Power Generation's BWRX-300 Unit 1 at the Darlington New Nuclear Project site.

Current status

Stage
Construction
How current
General record check . Bounded evidence review . 14 of 19 listed sources have a publication or document date recorded here; the newest is 11 Nov 2026. Stage (construction) confirmed against CNSC Darlington New Nuclear Project.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Recorded: CNSC consent to remove Regulatory Hold Point 1 (reactor building foundation) (30 Mar 2026); OPG license to construct BWRX-300 (4 Apr 2025); Renewal of Darlington New Nuclear Project site preparation license (PRSL 18.00/2031) (12 Oct 2021). Under review: OPG license to operate application. An application under review is not a permit. 1 other recorded action, such as a withdrawn, denied or superseded step. No operating license or other operating authority is recorded as issued. All permissions and applications
Latest development
Announced 10 Nov 2026 · Recorded development: OPG: Darlington Unit 1 no longer expected to meet its October 2030 target or C$7.7 billion estimate. OPG said on 10 November 2026 that the first Darlington BWRX-300 is no longer expected to meet its previously disclosed October 2030 commercial-operation target or C$7.7 billion estimate; its assessment should be substantially complete by mid-2027. Source: Ontario Power Generation: OPG Reports 2026 Third Quarter Financial Results (10 November 2026), OPG release as republished by Cantech Letter (published 10 Nov 2026); Ontario Power Generation: 2025 annual Management's Discussion and Analysis (OEB-filed copy, 12 March 2026) (dated 12 Mar 2026); Ontario Power Generation: 2026 first-quarter results release and MD&A (OEB-filed copy, 5 May 2026) (published 5 May 2026); World Nuclear News: OPG set to revise timeline and cost of first SMR unit (published 11 Nov 2026). Updates entry
More on this development

Read as republished by Cantech Letter; OPG's own copy and Q3 MD&A not opened. No new date or cost given. Company outlook, not a CNSC decision; does not itself replace the end-2030 grid target.

Next dated milestone
Grid connection: 2030 (target). OPG target: connect Darlington BWRX-300 Unit 1 to the grid by the end of 2030. This is not a commitment and is not an achieved milestone. Source: World Nuclear News: OPG secures government equity financing for SMR project (published 24 Oct 2025).
Selected limitations
  • The mapped point is not an exact surveyed coordinate.
Same design
18 tracked: 1 construction, 4 licensing, 10 siting, 3 announced. 13 tracked at construction across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Boiling water reactor. How it works, with a 3D view.
Schematic of BWRX-300. A tall reactor vessel with, from bottom to top, control rods and drives, the core, a tall chimney, steam separators and a steam dryer.
Schematic of BWRX-300.

Description

The CNSC license to construct, PRCL 32.00/2035, was issued on 4 April 2025 on an application received on 31 October 2022, and covers this one unit. IAEA PRIS records a physical construction start on 22 April 2026, separately from that license. OPG applied on 25 March 2026 for a license to operate; the Commission will decide after a public hearing that has not yet been scheduled, and the application is not an operating license. The CNSC lists the project as one unit under construction and removed the first regulatory hold point, for the reactor building foundation, on 30 March 2026. In October 2025 the Canada Growth Fund and Building Ontario Fund committed up to C$2 billion and C$1 billion in equity to the four-unit Darlington New Nuclear Project, with a first tranche for this unit; OPG remains majority owner and operator. On 23 June 2026 the Williams Treaties First Nations announced a C$700 million investment, structured as a loan to Darlington New Nuclear Project LP for construction of this first unit, to convert to equity once all four units are built, backed by federal and Ontario loan guarantees; no ownership percentage is published. Proposed Units 2–4 are a separate record and do not have a license to construct. On 10 November 2026 OPG said in its third-quarter results release (read as republished) that Unit 1 is no longer expected to achieve its previously disclosed commercial operation date target of October 2030 or be completed within its previously disclosed estimated cost of C$7.7 billion (which includes required systems and services common to all planned SMRs); the release gives no replacement date or cost, and OPG said its comprehensive cost and schedule assessment is currently expected to be substantially completed by mid-2027. The record's 2030 grid-connection target comes from OPG's earlier statements; the release does not mention grid connection.

Key facts

Design
BWRX-300 (SMR)
Technology
Boiling water reactor (BWR) · light water
Reactor vessel of this design
27 m tall, 4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 25.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Intended operator(s)
Ontario Power Generation
Vendor for linked design
GE Vernova Hitachi Nuclear Energy
Design origin
United States: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
Location
Darlington New Nuclear Project site · Canada · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the Darlington New Nuclear Project unit 1 (BWRX-300) (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); plant-area point on the existing Darlington campus, not a surveyed plot. Replaces an earlier hand-placed point about 1 km away that recorded no coordinate source.
Coordinates
43.8733, -78.7057 · site-area point (approximate)
Electrical capacity
300 MWe (net) · scope: module
Thermal capacity
870 MWth (nameplate; basis unspecified)
Modules planned
1
Purpose
Power plant
Construction start
22 Apr 2026IAEA PRIS records construction start for Darlington SMR1
Inclusion basis
SMR by design class
Confidence
high
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.

Status confirmed on against CNSC Darlington New Nuclear Project. This confirms the recorded status only; the general record check date remains separate.

Site and capacity notes

Darlington BWRX-300 Unit 1 is recorded at Darlington New Nuclear Project site, Ontario, Canada. Intended operator: Ontario Power Generation. Recorded vendor: GE Vernova Hitachi Nuclear Energy. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Darlington BWRX-300 Units 2-4.

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'darlington-new-nuclear-power-plant-1' (43.8733, -78.7057)

Recorded electrical output is 300 MWe (net), scope module. Modules planned: 1. Recorded thermal output is 870 MWth (nameplate; basis unspecified).

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
  • Application filing entityOntario Power Generation · sourceCNSC identifies OPG as the applicant for this unit's construction and operating licenses. An application is separate from the Commission's decision.
Operator or intended licensed owner
Reactor supplier
Contractor
  • Construction contractorAecon Kiewit Nuclear Partners · sourceAwarded the execution-phase construction contract (reported 9 May 2025) under an integrated project delivery model.
Source-backed project statement

World Nuclear News reported on 9 May 2025 that Aecon Kiewit Nuclear Partners was awarded the execution-phase construction contract for OPG's Darlington BWRX-300 under an integrated project delivery model with GE Vernova Hitachi and AtkinsRéalis. This records the award and its scope; the award announcement alone does not establish physical construction progress. WNN: Construction contract awarded for Darlington SMR

Funding and government decisions
  • Funder or lender named for this projectCanada Infrastructure Bank · sourceAgreement finalized 25 Oct 2022 committing C$970 million to Phase 1 (design, site preparation, long-lead equipment); amount disbursed not stated.
  • Funder or lender named for this projectCanada Growth Fund Inc. · sourceCommitted up to C$2 billion for 15% of the four-unit project (Oct 2025), subject to conditions; the first tranche funds this first unit.
  • Funder or lender named for this projectBuilding Ontario Fund · sourceWill invest C$1 billion for 7.5% of the four-unit project (Oct 2025), subject to conditions; the first tranche funds this first unit.
  • Loan-guarantee program managerCanada Indigenous Loan Guarantee Corporation · sourceManages the federal program providing half the guarantee supporting the Williams Treaties First Nations' investment; Ontario provides the other half (June 2026). The release does not identify CILGC as the direct lender.
  • Funder or lender named for this projectWilliams Treaties First Nations · sourceTo eventually own a significant minority interest in the four-unit project through guaranteed financing (announced 23 June 2026); percentage not stated.
Source-backed project statement

The Canada Infrastructure Bank finalized an agreement in October 2022 committing C$970 million to Phase 1 of the first Darlington SMR. In October 2025 the Canada Growth Fund committed up to C$2 billion and the Building Ontario Fund C$1 billion in equity in the four-unit project, subject to conditions, with the first tranche funding this first unit. On 23 June 2026 the Williams Treaties First Nations announced a C$700 million loan to the project partnership for building the first unit, converting to equity later and backed by federal and Ontario loan guarantees. Disbursed amounts are not stated. Canada Infrastructure Bank: CIB commits $970 million towards Canada's first small modular reactor; World Nuclear News: OPG secures government equity financing for SMR project; World Nuclear News: First Nations group takes stake in Ontario nuclear plant; Department of Finance Canada: Government announces largest Indigenous loan guarantee in Canadian history to support Darlington New Nuclear Project

Fuel
  • Fuel supplier named for this projectCameco · sourceSelected in November 2023 to supply natural uranium hexafluoride for this first unit ('will be contracted').
  • Fuel supplier named for this projectUrenco · sourceUrenco USA selected in November 2023 for enrichment services for this first unit; Urenco called it its first long-term SMR fuel supply agreement.
  • Fuel supplier named for this projectOrano · sourceSelected in November 2023 to provide additional enriched uranium product for this first unit.
  • Fuel supplier named for this projectGlobal Nuclear Fuel-Americas, LLC · sourceSelected in November 2023 for fuel fabrication, related technical services and fuel assemblies for this first unit.
Source-backed project statement

World Nuclear News reported on 30 November 2023 that OPG selected Cameco to be contracted for natural uranium hexafluoride, Urenco USA for enrichment, Orano for additional enriched uranium product and Global Nuclear Fuel-Americas for fabrication and fuel assemblies, to secure fuel for the first Darlington BWRX-300. Urenco called it the first long-term SMR fuel supply agreement. No delivery or fuel loading is reported. WNN: SMR fuel supply chain grows as agreements signed

Site host or owner
Comparable schedule revision
A documented comparable revision is recorded. It is not a completed source review.

Source-backed project statement World Nuclear News reported on 30 November 2023 that OPG planned to have the first Darlington BWRX-300 online by the end of 2029, and on 24 October 2025 that OPG expects to connect it to the grid by the end of 2030. The grid-connection target has moved from end-2029 to end-2030. These are company targets, and the record already stores the pair. OPG's 2025 annual MD&A (12 March 2026) still gave grid connection by the end of 2030, and its first-quarter 2026 MD&A (5 May 2026) an expected in-service year of 2030, both with a C$7.7 billion approved budget. On 10 November 2026 OPG's third-quarter release (read as republished by Cantech Letter) said Unit 1 is no longer expected to meet its previously disclosed October 2030 commercial-operation target or C$7.7 billion estimate; the release gives no replacement date or cost and does not mention grid connection, so no new pair is recorded. OPG's third-quarter MD&A was not read. WNN: SMR fuel supply chain grows as agreements signed; World Nuclear News: OPG secures government equity financing for SMR project; Ontario Power Generation: OPG Reports 2026 Third Quarter Financial Results (10 November 2026), OPG release as republished by Cantech Letter; Ontario Power Generation: 2025 annual Management's Discussion and Analysis (OEB-filed copy, 12 March 2026); Ontario Power Generation: 2026 first-quarter results release and MD&A (OEB-filed copy, 5 May 2026)

Not found in the sources we checked (1): Customer or offtaker
Customer or offtaker

No buyer of the station's output, offtake contract or payment amount is named in the sources read. Ontario's regulatory registry decision posted on 16 January 2026 says O. Reg. 53/05, the regulation on payments under section 78.1 of the Ontario Energy Board Act, was amended effective 1 January 2026 to prescribe DNNP GP Inc., acting for the DNNP LP partnership, as a rate-regulated generator for the DNNP Nuclear Generating Station, which remains subject to OEB rate-setting; the regulation previously prescribed OPG. This is a station-wide regulated payment framework, not a sale contract with a named buyer. World Nuclear News: OPG secures government equity financing for SMR project; ERO 025-0501: Regulatory amendments to support financing for OPG's major nuclear projects (decision)

Not recorded in SMRMap's reviewed evidence (1): Programs and agreements naming the project
Programs and agreements naming the project

Timeline

Recorded developments

Earlier developments (13)

Targets

Planned, target and estimated dates are not achievements or commitments.

Schedule changes

The same milestone as stated at two dates. A revised target is still a target; the earlier target is kept for comparison and no longer counts as upcoming.

Dates on the project record: Planned grid connection: 2030 (planned); Construction license: 4 Apr 2025.

Permissions and applications

Site applications and decisions

Construction applications and decisions

Operating-license applications and decisions

Assessments of the design (not of this site)

(2)
  • BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
    The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
    Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs
  • CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
    CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(5 notes)
  • Evidence review. The CNSC project page (opened 19 October 2026) places the Darlington New Nuclear Project at the existing Darlington site in the Municipality of Clarington, Ontario, says one unit is under construction, and says OPG applied in October 2022 for a license to construct one BWRX-300 and was granted it in April 2025. The Commission's record of decision dated 4 April 2025 issued construction license PRCL 32.00/2035 to Ontario Power Generation, valid from 4 April 2025 to 31 March 2035, on an application received on 31 October 2022; OPG also holds a site preparation license valid until 2031. The license covers one unit only and carries three regulatory hold points; the first, for installation of the reactor building foundation, was removed on 30 March 2026. Site preparation is kept apart from nuclear construction: in October 2025 World Nuclear News reported excavation of the reactor building shaft and site grading for three further units, IAEA PRIS records the construction start of Darlington SMR1 on 22 April 2026, and in April 2026 the 953-tonne basemat module was lifted into the reactor building shaft. In March 2026 OPG applied for a 20-year license to operate the unit, which the Commission will decide after a public hearing not yet scheduled; the application is not an operating license. OPG said in October 2025 that it expects to complete construction by the end of the decade and connect the unit to the grid by the end of 2030; these are targets. PRIS gives 870 MWth with 300 MWe gross and 300 MWe net, the CNSC page calls the BWRX-300 a 300 MWe reactor, and OPG's licensing submission described a 327 MWe output, so the gross figure is not consistent across sources. Stored values (one unit, 300 MWe net, 870 MWth, the April 2025 license and the 2030 grid target) match the sources; PRIS's construction-license date field shows 31 October 2022, which is the CNSC application date, not the license date. OPG remains majority owner and operator after the October 2025 equity commitments. Its license-applicant, site-owner and intended licensed-owner roles are recorded separately from the Commission's decisions. Last checked 19 Oct 2026. CNSC Darlington New Nuclear Project; CNSC Record of Proceedings, Including Reasons for Decision: OPG application for a licence to construct one BWRX-300 (CMD 24-H3); IAEA PRIS: Darlington BWRX-300 Unit 1; World Nuclear News: OPG secures government equity financing for SMR project; World Nuclear News: First Nations group takes stake in Ontario nuclear plant
    What would change this

    The CNSC hearing notice or decision on OPG's March 2026 licence-to-operate application, or CNSC removal of regulatory hold point 2. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. Two Commission decisions are pending: removal of the remaining construction hold points as OPG meets their commitments, and the operating-license decision after a public hearing that CNSC says will be announced later. No hearing date is recorded. Last checked 23 Oct 2026. CNSC Darlington New Nuclear Project
    What would change this

    A CNSC hold-point removal, hearing notice or operating-license decision for Darlington Unit 1. Next scheduled check: 21 Jan 2027.

  • Permissions and public process. The CNSC construction license for Unit 1, issued in April 2025 after a public hearing, carries three regulatory hold points; the first, for the reactor-building foundation, was removed on 30 March 2026. OPG's March 2026 application for a 20-year operating license will be decided by the Commission after a public hearing not yet scheduled. The application is not an operating license. Last checked 23 Oct 2026. CNSC Darlington New Nuclear Project
    What would change this

    A CNSC hearing notice or decision on the Unit 1 operating license, or removal of a further hold point. Next scheduled check: 21 Jan 2027.

  • Spent fuel, waste and closure. OPG's March 2026 operating-license application covers Unit 1 together with an associated low- and intermediate-level waste storage structure at the project site. The opened CNSC page does not describe spent-fuel storage or its long-term disposition for this unit. Last checked 23 Oct 2026. CNSC Darlington New Nuclear Project
    What would change this

    A CNSC or OPG document describing spent-fuel storage for Darlington Unit 1. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water). The 2025 CNSC construction-license decision places the unit on the existing Darlington Nuclear site on the north shore of Lake Ontario, a site already holding a license to prepare site. An October 2025 trade report says a tunnel-boring machine will build a 3.4 km tunnel for the condenser cooling-water system. These sources do not describe the transmission connection agreement or its terms. Last checked 23 Oct 2026. CNSC Record of Proceedings, Including Reasons for Decision: OPG application for a licence to construct one BWRX-300 (CMD 24-H3); World Nuclear News: OPG secures government equity financing for SMR project
    What would change this

    An OPG, IESO or Hydro One document describing the unit's grid connection, or a CNSC update on cooling-water works. Next scheduled check: 21 Jan 2027.

Evidence dates

(14 of 19 sources with a publication or document date)
Latest dated listed source publication: World Nuclear News: OPG set to revise timeline and cost of first SMR unit: 11 Nov 2026.Latest dated listed source document: Ontario Power Generation: 2025 annual Management's Discussion and Analysis (OEB-filed copy, 12 March 2026): 12 Mar 2026.Latest dated recorded event: OPG says Darlington BWRX-300 Unit 1 is no longer expected to meet its October 2030 commercial-operation target or C$7.7 billion estimate: 10 Nov 2026.5 of 19 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(19)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Darlington BWRX-300 Unit 1 — https://smrmap.com/projects/darlington-bwrx-300/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Darlington BWRX-300 Unit 1”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/darlington-bwrx-300/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.