Projects / Canada · Siting
Darlington BWRX-300 Units 2-4
The Darlington New Nuclear Project covers up to four BWRX-300 reactors under a license to prepare site; only Unit 1 has a license to construct.
Current status
- How current
- General record check . Bounded evidence review . 1 of 4 listed sources has a publication or document date recorded here: 12 Mar 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 18 tracked: 1 construction, 4 licensing, 10 siting, 3 announced. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Boiling water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
OPG plans three further units, for which a construction application may follow. Unit 1 is a separate record. Output is not stored.
Key facts
- Design
- BWRX-300 (SMR)
- Technology
- Boiling water reactor (BWR) · light water
- Reactor vessel of this design
- 27 m tall, 4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 25.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Ontario Power Generation
- Vendor for linked design
- GE Vernova Hitachi Nuclear Energy
- Design origin
- United States: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
- Location
- Darlington New Nuclear Project site · Canada · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the Darlington New Nuclear Project unit 1 (BWRX-300) (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); plant-area point on the existing Darlington campus, not a surveyed plot. Replaces an earlier hand-placed point about 1 km away that recorded no coordinate source. - Coordinates
- 43.8733, -78.7057 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Darlington BWRX-300 Units 2-4 is recorded at Darlington New Nuclear Project site, Ontario, Canada. Operator: Ontario Power Generation. Recorded vendor: GE Vernova Hitachi Nuclear Energy. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Darlington BWRX-300 Unit 1.
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'darlington-new-nuclear-power-plant-1' (43.8733, -78.7057)
Electrical output is not recorded on this project. Modules planned: 3. Thermal output is not recorded on this project. The linked design record states 870 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorOntario Power Generation
- Reactor supplier
- Vendor for the linked designGE Vernova Hitachi Nuclear Energy
- Funding and government decisions
Source-backed project statement World Nuclear News of 2 April 2026 says Ontario approved a CAD 20.9 billion budget and construction start for the first of the four planned BWRX-300s. OPG's 2025 annual MD&A (12 March 2026) gives the Board-approved budget for Unit 1 as C$7.7 billion, including C$1.6 billion of systems and services common to all four units, and about C$20.9 billion as the current estimate for the whole four-unit project, so the WNN sentence attaches the four-unit estimate to the first unit's approval. The CNSC page states no amount. The four-unit GDP and jobs figures are economic estimates. OPG's same 2025 report says C$55 million from the federal Future Electricity Fund was announced in March 2025 to support development of the three additional SMRs. It also reports up to C$3 billion in equity financing for the whole four-SMR DNNP, up to C$1 billion from the Building Ontario Fund and up to C$2 billion from the Canada Growth Fund, subject to conditions. Capital is to be made available in two tranches: Unit 1 funding and additional capital for the other three SMRs once milestones are met. These are reported funding and conditional financing commitments, not proof of disbursement or construction approval for Units 2 to 4; the C$3 billion is not an allocation solely to those three units. WNN: OPG applies for operating licence for BWRX-300 SMR; Ontario Power Generation: 2025 annual Management's Discussion and Analysis (OEB-filed copy, 12 March 2026)
Not found in the sources we checked (4): Customer or offtaker; Contractor; Fuel; Comparable schedule revision
- Customer or offtaker
The CNSC's Darlington New Nuclear Project page, modified 25 August 2026, and World Nuclear News of 2 April 2026 name Ontario Power Generation as site owner and licensee but name no purchaser of power from Units 2 to 4. The Ontario ministry's jobs and GDP figures are economic estimates, not an offtake. CNSC: Darlington New Nuclear Project; WNN: OPG applies for operating licence for BWRX-300 SMR
- Contractor
The CNSC's Darlington New Nuclear Project page, modified 25 August 2026, says OPG selected the BWRX-300 in December 2021 and that a construction application for up to three additional units is only a possibility. The CNSC's 4 April 2025 decision on the one-unit construction license names GE Vernova Hitachi, AtkinsRéalis and Aecon as OPG's contract partners for that application. No source read assigns engineering or construction contracts to Units 2 to 4. CNSC: Darlington New Nuclear Project; CNSC Record of Proceedings, Including Reasons for Decision: OPG application for a licence to construct one BWRX-300 (CMD 24-H3)
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
World Nuclear News of 2 April 2026 says the BWRX-300 uses GE Vernova Hitachi's existing licensed GNF2 fuel design, which is a design statement. Neither it nor the CNSC Darlington page names a fuel supplier, contract, quantity or delivery for Units 2 to 4. WNN: OPG applies for operating licence for BWRX-300 SMR
- Comparable schedule revision
Comparable schedule revision not established. The CNSC page, modified 25 August 2026, and World Nuclear News of 2 April 2026 give dates for the first unit only, including grid connection planned by the end of 2030, and describe a construction application for up to three more units only as a possibility. The site-preparation license's 2031 expiry is not a milestone. No dated target for Units 2 to 4 was read, so no revision is shown. CNSC: Darlington New Nuclear Project; WNN: OPG applies for operating licence for BWRX-300 SMR
Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Site host or owner; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Assessments of the design (not of this site)
(2)
- BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs - CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(5 notes)
- Evidence review. The CNSC describes the Darlington New Nuclear Project at the existing Darlington site in Bowmanville, Clarington, Ontario, as covering up to four reactors, with OPG as site owner and licensee and GE Vernova Hitachi's BWRX-300 selected. This record concerns the three proposed later units. The April 2025 construction license, March 2026 release of the foundation hold point and March 2026 operating-license application each concern one reactor, Unit 1, which has a separate record. They do not establish construction or operating permission for Units 2–4. The site-preparation license covers the broader site and is valid until 2031. CNSC describes a possible future construction application for up to three additional units, not one already filed. The stored three-unit proposal and siting stage remain; no output or new permission is assigned from Unit 1 to these later units. Last checked 19 Oct 2026. CNSC: Darlington New Nuclear Project
What would change this
An OPG construction-license application expressly covering Darlington Units 2, 3 or 4, and a CNSC decision on that application. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The next regulatory step for these three units is an OPG application to CNSC for a license to construct, which would be decided by the Commission. CNSC describes it only as a possible future application, with no date. Last checked 23 Oct 2026. CNSC: Darlington New Nuclear Project
What would change this
An OPG application or CNSC hearing notice for construction of Darlington Units 2 to 4. Next scheduled check: 21 Jan 2027.
- Permissions and public process. CNSC lists OPG's site-preparation license for the Darlington New Nuclear Project, valid until 2031, and a construction license for one BWRX-300 only. Units 2 to 4 need a future construction application, which the page describes as a possibility, not a filing. The project's environmental assessment was found in April 2024 to apply to the selected reactor technology. The site lies within Williams Treaties lands; the page records no separate consent decision for these units. Last checked 23 Oct 2026. CNSC: Darlington New Nuclear Project
What would change this
A CNSC notice of an OPG licence-to-construct application or hearing for Darlington Units 2 to 4. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). CNSC says the project site is OPG-owned land at the existing Darlington nuclear site in the Municipality of Clarington, under a site-preparation license covering up to four reactors. The opened page gives no grid-connection or cooling-water arrangement specific to Units 2 to 4. Last checked 23 Oct 2026. CNSC: Darlington New Nuclear Project
What would change this
A CNSC or OPG document on grid connection or cooling for Darlington Units 2 to 4. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. At the 2024 construction-license hearing for the first unit, OPG described project-wide plans for the Darlington New Nuclear Project: used fuel in the reactors' fuel pools, then dry storage on site, and a 2026 license-amendment application for interim storage of low- and intermediate-level waste on the Darlington site. The national waste organization NWMO is responsible for long-term used-fuel management. No license yet covers Units 2 to 4 or their waste. Last checked 23 Oct 2026. CNSC Record of Proceedings, Including Reasons for Decision: OPG application for a licence to construct one BWRX-300 (CMD 24-H3)
What would change this
A CNSC license application or decision covering Units 2 to 4, or OPG's waste-storage license amendment. Next scheduled check: 21 Jan 2027.
Evidence dates
(1 of 4 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(4)
- CNSC: Darlington New Nuclear Project (regulator, accessed 2 Oct 2026)
- WNN: OPG applies for operating licence for BWRX-300 SMR (news report, accessed 2 Oct 2026)
- CNSC Record of Proceedings, Including Reasons for Decision: OPG application for a licence to construct one BWRX-300 (CMD 24-H3) (regulator, accessed 10 Oct 2026)
- Ontario Power Generation: 2025 annual Management's Discussion and Analysis (OEB-filed copy, 12 March 2026) (company, dated 12 Mar 2026, accessed 13 Nov 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Darlington BWRX-300 Units 2-4 — https://smrmap.com/projects/darlington-bwrx-units-2-4/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Darlington BWRX-300 Units 2-4”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/darlington-bwrx-units-2-4/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.