Projects / China · Siting

Huakun One floating reactor platform demonstration at the Taipingling site

Huakun One is a floating platform demonstration with one 200 MWt reactor at the siting stage, planned for CGN's Taipingling site in Huidong county, China.

Current status

Stage
Siting
How current
Record checked · Evidence reviewed · Next recheck due
Development and review dates

Newest recorded development . 1 of 4 listed sources has a publication or document date recorded here: 2 Nov 2026. Status not rechecked since the record check; this project is not covered by the nightly status check. Next general check: . Next evidence or detail review: .

Permissions
Recorded: NNSA site-selection review opinion No. 2620, Huakun One science and technology demonstration project (2 Nov 2026). All permissions and applications
Latest development
2 Nov 2026 · Site permission recorded: NNSA issues site-selection opinion for Huakun One. NNSA's site-selection opinion No. 2620 of 2 November 2026 found no disqualifying site factor that engineering measures could not resolve, and agrees design work may proceed on the site parameters. Source: NNSA: site-selection review opinion No. 2620 for the Huakun One science and technology demonstration project (2 November 2026) (dated 2 Nov 2026). Updates entry
More on this development

It is not a construction license. Until it holds one, the company may not pour seismic Category I foundation concrete or build other safety-important structures.

Next dated milestone
No next milestone date is recorded.
Selected limitations
  • The mapped point is not an exact surveyed coordinate.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Pressurized water reactor. How it works, with a 3D view.
Schematic of Rolls-Royce SMR, this type's example. On the left, a reactor vessel holds a core of fuel assemblies, with control rod drives above its head.
Schematic of Rolls-Royce SMR, this type's example.

Description

The November 2025 siting-stage environmental assessment accepted by China's ecology ministry on 2 December 2025 describes one compact pressurised-water reactor of 200 MWt and about 50 MWe with two turbine-generators on a platform to be moored at a new operations base in the harbour basin of CGN's Taipingling site in Huidong county, Huizhou, owned by CGN Ocean Energy. The assessment says the start date will be set at an appropriate time. On 2 November 2026 NNSA issued site-selection review opinion 国核安证字第2620号 to CGN Ocean Energy. Its review found no disqualifying site factor affecting safety that engineering measures could not resolve, and it agrees design work may proceed on the siting report's site parameters. It is not a construction license: until the company holds one, it may not pour seismic Category I foundation concrete or build other safety-important structures. The National Energy Administration's July 2026 report cites the same floating reactor. Its relationship to CGN's earlier ACPR50S program is not stated in the assessment, and the separate Bohai ACPR50S proposal remains its own record.

Key facts

Design
Huakun One floating reactor platform (SMR)
Technology
Pressurized water reactor (PWR) · light water
Operator(s)
CGN Ocean Energy
Vendor for linked design
China General Nuclear Power Group
Location
Taipingling site operations base (harbour basin), Huidong · China · precision: site area (named plant, laboratory, base, port, campus or parcel)
Approximate NuclearChain export point for the Taipingling nuclear power plant (derived from GEM's tracker); the floating platform's berth is a new operations base in the site's harbour basin, so the point represents the Taipingling site, not the mooring.
Coordinates
22.694385, 114.984522 · site-area point (approximate)
Electrical capacity
50 MWe (gross/net unspecified) · scope: plant
Thermal capacity
200 MWth (nameplate; basis unspecified)
Modules planned
1
Record reviewed
6 Oct 2026Evidence review 4 Nov 2026. How current names both.
Site and capacity notes

Huakun One floating reactor platform demonstration at the Taipingling site is recorded at Taipingling site operations base (harbour basin), Huidong, Guangdong, China. Operator: CGN Ocean Energy. Recorded vendor: China General Nuclear Power Group. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).

Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'taipingling-nuclear-power-plant-1-1' (22.694385, 114.984522)

Recorded electrical output is 50 MWe (gross/net unspecified), scope plant. Modules planned: 1. Recorded thermal output is 200 MWth (nameplate; basis unspecified).

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Operator or intended licensed owner
Reactor supplier
Contractor

Source-backed project statement CGN Ocean Energy's November 2025 siting-stage environmental report for Huakun One says the owner commissioned the Pearl River Water Resources Protection Institute to study the marine environmental impact of the harbour works, the Nanjing Hydraulic Research Institute to model suspended sediment, and Suzhou Nuclear Power Research Institute to monitor baseline noise in June 2025. These are completed preparatory study contracts. The report names no construction contractor and leaves the start date open. MEE: siting-stage environmental impact report (November 2025), Huakun One science and technology demonstration project

Funding and government decisions

Source-backed project statement CGN Ocean Energy's November 2025 siting-stage environmental report for Huakun One says the funds needed for the project's investment will be raised and provided by the owner, CGN Ocean Energy. No amount is stated, and the report leaves the construction start to be set later. MEE: siting-stage environmental impact report (November 2025), Huakun One science and technology demonstration project

Not found in the sources we checked (3): Customer or offtaker; Fuel; Comparable schedule revision
Customer or offtaker

CGN Ocean Energy's November 2025 siting-stage environmental report for Huakun One, accepted by the Ministry of Ecology and Environment on 2 December 2025, says the moored reactor platform would generate electricity and send it to the local grid over 35 kV cables. It names no buyer or power purchase agreement. MEE: siting-stage environmental impact report (November 2025), Huakun One science and technology demonstration project

Fuel
No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.

CGN Ocean Energy's November 2025 siting-stage environmental report for Huakun One says new fuel could reach the site by rail or road in licensed containers and that spent fuel would be stored long-term at the Taipingling base. It names no fuel fabricator, quantity or delivery date. MEE: siting-stage environmental impact report (November 2025), Huakun One science and technology demonstration project

Comparable schedule revision

Comparable schedule revision not established. CGN Ocean Energy's November 2025 siting-stage environmental report says the specific construction start for Huakun One will be set at an appropriate time, considering all factors, and gives no construction or operation date. With no dated target there is nothing to revise. MEE: siting-stage environmental impact report (November 2025), Huakun One science and technology demonstration project

Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Site host or owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Site host or owner
Programs and agreements naming the project

Timeline

Recorded developments

Permissions and applications

Site applications and decisions

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(5 notes)
  • Evidence review. CGN Ocean Energy's siting-stage environmental impact report for the Huakun One (华鲲一号) science and technology demonstration project, dated November 2025, plans one floating reactor platform using compact pressurised-water reactor technology in a one-reactor, two-turbine-generator configuration of 200 MWt and about 50 MWe, plus a new Taipingling operations and maintenance base in Huangbu town, Huidong county, Huizhou, Guangdong, built on the Taipingling nuclear plant site; the platform is to be moored in the base's harbour basin and send power to the local grid. The report names CGN Ocean Energy as owner responsible for construction, production and operation and the CGN research institute as lead designer of the platform, and it describes itself as the technical document for the company's site-approval application to the Ministry of Ecology and Environment (National Nuclear Safety Administration). The ministry's notice records acceptance of the report on 2 December 2025, and the report leaves the construction start to be set at an appropriate time. The National Energy Administration's 2026 development report says research and development of a 200 MWt, about 50 MWe offshore floating reactor is progressing, without naming a site. The National Nuclear Safety Administration issued site-selection review opinion 国核安证字第2620号 on 2 November 2026 (notice 国核安发〔2026〕207号). It names CGN Ocean Energy as operating organization, finds no disqualifying site factor affecting safety that engineering measures could not resolve, and agrees design work may proceed on the siting report's site parameters. Before a construction license the company may not pour seismic Category I foundation concrete or build other safety-important structures. One condition refers to the siting-stage environmental report and its review opinion, but the ministry's decision on that report has not been opened. The next documentary decisions are that decision, if not already made, and a construction license. The stored single platform, 200 MWt and about 50 MWe, CGN Ocean Energy as operator, CGN as vendor and the siting stage stay; the opened sources support every stored field, and the stored 'Huakun' romanises 华鲲. Last checked 4 Nov 2026. MEE: siting-stage environmental impact report (November 2025), Huakun One science and technology demonstration project; MEE: acceptance notice for the Huakun One siting-stage environmental impact report (2 December 2025); National Energy Administration: China Nuclear Power Development Report 2026 (July 2026); NNSA: site-selection review opinion No. 2620 for the Huakun One science and technology demonstration project (2 November 2026)
    What would change this

    The Ministry of Ecology and Environment's approval of the Huakun One siting-stage environmental impact report, or a National Nuclear Safety Administration construction-license application or decision; a construction-stage report would follow. Next recheck due .

  • Next decision and prerequisites. The November 2025 siting-stage environmental report says the construction start will be set at a suitable time after weighing various factors, and the ministry had only accepted the report for review in December 2025. NNSA issued its siting opinion on 2 November 2026. One of its conditions refers to a review opinion on that environmental report, but the ministry's decision has not been opened. The next consequential steps are that decision, if not already made, and an NNSA construction license; no date for either is given in the documents reviewed. Last checked 4 Nov 2026. MEE: siting-stage environmental impact report (November 2025), Huakun One science and technology demonstration project; MEE: acceptance notice for the Huakun One siting-stage environmental impact report (2 December 2025); NNSA: site-selection review opinion No. 2620 for the Huakun One science and technology demonstration project (2 November 2026)
    What would change this

    MEE approval of the siting-stage environmental report, an NNSA construction-license application or decision, or a dated construction start. Next recheck due .

  • Permissions and public process. The Ministry of Ecology and Environment accepted the Huakun One siting-stage environmental report for review on 2 December 2025; acceptance is not an approval. The report says the owner ran public information notices and science-outreach events and that local people broadly support the project. NNSA issued its site-selection review opinion on 2 November 2026, and one of its conditions refers to the siting-stage report and that report's review opinion. The documents reviewed show no construction license, and the ministry's decision on the environmental report has not been opened. Last checked 4 Nov 2026. MEE: acceptance notice for the Huakun One siting-stage environmental impact report (2 December 2025); MEE: siting-stage environmental impact report (November 2025), Huakun One science and technology demonstration project; NNSA: site-selection review opinion No. 2620 for the Huakun One science and technology demonstration project (2 November 2026)
    What would change this

    MEE approval of the siting-stage environmental report or an NNSA construction-license application for Huakun One. Next recheck due .

  • Site dependencies (land, grid, water). The November 2025 siting-stage environmental report proposes a new maintenance base at CGN's Taipingling nuclear site in Huidong county, where the reactor platform would be moored alongside in the harbour basin to load fuel, test and generate. It says the base's fuel-storage building, waste facilities and environmental monitoring partly depend on the Taipingling plant, which needs related redesign. These are proposals in a siting report, not secured arrangements, and grid connection terms are not described in the passages reviewed. Last checked 23 Oct 2026. MEE: siting-stage environmental impact report (November 2025), Huakun One science and technology demonstration project
    What would change this

    An approved environmental report, sea-use permit or agreement with the Taipingling plant covering shared facilities. Next recheck due .

  • Spent fuel, waste and closure. The November 2025 siting-stage environmental report says spent fuel storage would be shared with the Taipingling nuclear plant in the short term, with a separate spent-fuel storage facility at the base considered for the long term. The owner commits to have the Taipingling plant receive, treat and store the platform's waste. These are planned arrangements in a siting report, not executed agreements, and no disposal route for spent fuel is set out in the passages reviewed. Last checked 23 Oct 2026. MEE: siting-stage environmental impact report (November 2025), Huakun One science and technology demonstration project
    What would change this

    A construction-stage environmental report or license condition fixing spent fuel storage and waste handling for Huakun One. Next recheck due .

Evidence dates

(1 of 4 sources with a publication or document date)
Latest dated listed source publication: no date recorded.Latest dated listed source document: NNSA: site-selection review opinion No. 2620 for the Huakun One science and technology demonstration project (2 November 2026): 2 Nov 2026.Latest dated recorded event: Huakun One: regulator siting review opinion issued: 2 Nov 2026.3 of 4 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(4)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Huakun One floating reactor platform demonstration at the Taipingling site — https://smrmap.com/projects/huakun-one-taipingling/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Huakun One floating reactor platform demonstration at the Taipingling site”. Record reviewed 6 Oct 2026. https://smrmap.com/projects/huakun-one-taipingling/ (accessed [date]).

“Record reviewed” is the record review date; the evidence review, individual sources and later additions keep their own dates. Add the date you read the page; save a PDF if you need a copy of it.

Record details
Inclusion basis
Vendor SMR claim, capacity checked
Confidence (as stored in the record)
medium

Data fingerprint 0153352d9753fff813ac32edec0a3ffbf1d8b7c7ee6420defec355f03d9ef915; build 2026-11-24. It identifies the underlying data collections, not an archived page or a download checksum. The build date is not a source review date.