Projects / Sweden · Licensing

Kärnfull Next SMR park at Målma, Valdemarsvik

Refirm Målma AB filed the first application under Sweden's new government-approval law on 23 March 2026, for 1,200-1,600 MWe at Valdemarsvik.

Current status

Stage
Licensing
How current
General record check . Bounded evidence review . 1 of 9 listed sources has a publication or document date recorded here: 3 Jun 2026. Swedish Government approval application for a nuclear facility at Målma, Valdemarsvik: status (under review) confirmed against Government of Sweden: Government review of new nuclear (status of applications).
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Under review: Swedish Government approval application for a nuclear facility at Målma, Valdemarsvik. An application under review is not a permit. All permissions and applications
Latest development
3 Sep 2026 · Recorded development: Studsvik selects GE Vernova Hitachi and Samsung C&T for four-unit BWRX-300 project. Studsvik selected GE Vernova Hitachi and Samsung C&T for an initial four-unit BWRX-300 project. Source: Studsvik: Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing 1.2 GW nuclear power project in Sweden (3 September 2026). Updates entry
Next dated milestone
Planned step: 31 Dec 2026 (target). Målma facility plan proposal due to the Government. This is not an achieved milestone. Source: Government of Sweden: facility-plan assignment for the Valdemarsvik application.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No map pin is shown for this record.
  • Expected for this stage but not recorded as a structured fact: Module/unit count (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
Same design
18 tracked: 1 construction, 4 licensing, 10 siting, 3 announced. 19 tracked at licensing across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Boiling water reactor. How it works, with a 3D view.
Schematic of BWRX-300. A tall reactor vessel with, from bottom to top, control rods and drives, the core, a tall chimney, steam separators and a steam dryer.
Schematic of BWRX-300.

Description

Kärnfull Next presents it as its Målma project, and the Government assigned the county administrative board to draft a facility plan on 7 May 2026. SSM's new-build page, fetched 5 October 2026, says no Nuclear Activities Act license application has been filed. SSM's 3 June 2026 opinion on the ReFirm Målma AB government-approval application says the application is high-level and that some statements are deficient or incorrect, and that the government has to decide whether that level is reasonable. The opinion is not a permit and not a refusal. On 12 June 2026 the Government announced that Studsvik AB had applied for state support covering both alternatives, including four to six reactors of about 1,200-1,600 MW in Valdemarsvik municipality; an application is not an award. A September 2026 agreement with GE Vernova Hitachi and Samsung C&T covers the Valdemarsvik and Nyköping sites with an initial four-unit BWRX-300 project, which will go to one of the two sites. The capacity range is not stored as a plant total. Nyköping (Studsvik new nuclear at the Nyköping home site) is the alternative site. Studsvik's own 3 September 2026 release confirms the partner selection; the first site is still to be decided.

Key facts

Design
BWRX-300 (SMR)
Technology
Boiling water reactor (BWR) · light water
Reactor vessel of this design
27 m tall, 4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 25.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Operator(s)
Kärnfull Next
Vendor for linked design
GE Vernova Hitachi Nuclear Energy
Design origin
United States: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
Location
Målma, Valdemarsvik · Sweden · precision: town or locality only
The sources name this place but publish no coordinate for it, so no pin is shown.
Coordinates
Town named, no map pin
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded. Only a range is published for Målma: four to six reactors (Government, 12 June 2026; Kärnfull Next, 18 February 2025).
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Kärnfull Next SMR park at Målma, Valdemarsvik is recorded at Målma, Valdemarsvik, Östergötland, Sweden. Operator: Kärnfull Next. Recorded vendor: GE Vernova Hitachi Nuclear Energy. Stage: Licensing. Location precision: town or locality only; town named, no map pin.

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project. The linked design record states 870 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Operator or intended licensed owner
Reactor supplier
Contractor
  • Planned construction contractorSamsung C&T · sourceNamed with GE Vernova Hitachi as the execution team with single-point responsibility for construction in a 3 Sep 2026 exclusive agreement for a first four-unit project at Nyköping or Valdemarsvik; site not chosen; no FID or permit.
  • Planned construction contractorGE Vernova Hitachi Nuclear Energy · sourceNamed with Samsung C&T as the execution team with single-point responsibility for construction in a 3 Sep 2026 exclusive agreement for a first four-unit project at Nyköping or Valdemarsvik; site not chosen; no FID or permit.
Source-backed project statement

GE Vernova's 3 September 2026 release says GE Vernova Hitachi leads reactor engineering, licensing support and cost estimation, and together with Samsung C&T acts as the execution team with single-point responsibility for construction and execution of an initial four-unit BWRX-300 project planned for either Nyköping or Valdemarsvik. This is an exclusive, time-limited development agreement. The site is not chosen and there is no investment decision or construction permission. Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project

Funding and government decisions

Source-backed project statement GE Vernova's 3 September 2026 release says DS Investment Partners, a South Korean investment firm, will lead the investment during the exclusivity period, with GE Vernova's Financial Services business advising on financial structuring. The Swedish government said on 12 June 2026 that it had received Studsvik's application for state support covering four to six reactors at Valdemarsvik. No amount is committed and the state-support application is undecided. Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project; Government of Sweden: Studsvik applies for state support (Nyköping and Valdemarsvik)

Site host or owner
Programs and agreements naming the project
Not found in the sources we checked (3): Customer or offtaker; Fuel; Comparable schedule revision
Customer or offtaker

GE Vernova's 3 September 2026 release on the Studsvik, GE Vernova Hitachi and Samsung C&T agreement describes an initial four-unit BWRX-300 project of 1.2 GW at Nyköping or Valdemarsvik, with the first unit in operation in the mid-2030s. It names no buyer of the power, and the Swedish government's June 2026 note on Studsvik's state-support application names none either. Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project

Fuel
No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.

GE Vernova's 3 September 2026 release describes GE Vernova's fuel business, Global Nuclear Fuel, in its company background, but does not say it will supply fuel to the Målma or Nyköping units. No fuel supplier or delivery for the project is named. Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project

Comparable schedule revision

Comparable schedule revision not established. GE Vernova's 3 September 2026 release expects the first unit of the initial four-unit project to enter operation in the mid-2030s, at a site not yet chosen. That target is stated once in the sources read, and the record's events hold no revision pair. Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project

Timeline

Recorded developments

Earlier developments (2)

Targets

Planned, target and estimated dates are not achievements or commitments.

Permissions and applications

Site applications and decisions

Assessments of the design (not of this site)

(2)
  • BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
    The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
    Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs
  • CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
    CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(9 notes)
  • Evidence review. The Government's release of 8 May 2026 says Refirm Målma AB applied on 23 March 2026 for approval of a nuclear facility in Valdemarsvik municipality and that the Östergötland county administrative board is assigned to draft a facility plan for it at Målma, due by 31 December 2026; Kärnfull Next's news page presents the filing as its application under the new Act on Government Approval of Nuclear Facilities, for an SMR park of four to six small modular reactors at Målma on land secured from landowner Latona Group in February 2025. The Government's status page (2 October 2026) lists the application as under preparation; the municipality must approve both the facility plan and the application before the Government can decide, and approval would not replace licensing under the Environmental Code and the Nuclear Activities Act. SSM's page (opened 19 October 2026) says no license application has been filed yet, and its opinion of 3 June 2026 calls the ReFirm Målma application high-level, describing possible paths for a development project. This is an application for an early government approval, not a permission, and no opened source reports site preparation or nuclear construction at Målma. On 12 June 2026 the Government said Studsvik AB had applied for state support for four to six modular reactors of the same type, about 1,200 to 1,600 MW electrical in total, in Valdemarsvik, as an alternative to Nyköping, with Studsvik to decide later which project to pursue; an application is not an award. GE Vernova's release of 3 September 2026 says an initial four-unit BWRX-300 project of about 1,200 MWe is planned for one of the two sites, to be decided during development, with the first unit expected in the mid-2030s. The licensing stage and the empty module count and output stay stored. The stored BWRX-300 design and GE Vernova Hitachi vendor rest on a partner selection that may go to Nyköping instead. No opened source names an intended reactor operator, so the stored operator Kärnfull Next, a project developer now owned by Studsvik, is not supported as an operator. The stored 7 May 2026 assignment date is not printed in the opened release, which is dated 8 May 2026. Last checked 19 Oct 2026. Government of Sweden: facility-plan assignment for the Valdemarsvik application; Government of Sweden: Government review of new nuclear (status of applications); SSM, work on new nuclear power; Government of Sweden: Studsvik applies for state support (Nyköping and Valdemarsvik); Kärnfull Next news list; Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project; Studsvik: Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing 1.2 GW nuclear power project in Sweden (3 September 2026); WNN: Third application lodged for Swedish SMR plant
    What would change this

    The Östergötland county board's draft facility plan for Målma (due 31 December 2026), Valdemarsvik municipality's position on the plan and application, or Studsvik's choice between Målma and Nyköping for the first BWRX-300 project. Next scheduled check: 7 Jan 2027.

  • Site location recorded as disclosed. The Government's facility-plan assignment of May 2026 names the site as Målma in Valdemarsvik municipality, Östergötland, and Kärnfull Next's release of 18 February 2025 describes the planned SMR park at Målma on land held under permanent land rights from landowner Latona Group. No property designation or plan boundary is published. Last checked 19 Oct 2026. Government of Sweden: facility-plan assignment for the Valdemarsvik application; Kärnfull Next news list
    What would change this

    Östergötland county board publishes the Målma facility-plan consultation. Next scheduled check: 19 Jan 2027.

  • Plant capacity (scope qualified): Not disclosed in the reviewed evidence. No single plant total is fixed. The Government's release of 12 June 2026 describes the Valdemarsvik alternative as four to six modular reactors of about 1,200 to 1,600 MW electrical in total, and Studsvik is to choose later between Valdemarsvik and Nyköping. The initial four-unit BWRX-300 project of about 1,200 MWe is planned for one of the two sites (GE Vernova, 3 September 2026). A range and an unassigned project figure are not stored as a plant total. Last checked 19 Oct 2026. Government of Sweden: Studsvik applies for state support (Nyköping and Valdemarsvik); Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project
    What would change this

    Studsvik's site decision or the Östergötland draft facility plan stating a capacity. Next scheduled check: 19 Jan 2027.

  • Module/unit count: Not disclosed in the reviewed evidence. Only a range is published for Målma: four to six reactors (Government, 12 June 2026; Kärnfull Next, 18 February 2025). The initial four-unit BWRX-300 project may go to Målma or Nyköping. Last checked 19 Oct 2026. Government of Sweden: Studsvik applies for state support (Nyköping and Valdemarsvik); Studsvik: Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing 1.2 GW nuclear power project in Sweden (3 September 2026); Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project
    What would change this

    Studsvik's site decision or the draft facility plan. Next scheduled check: 19 Jan 2027.

  • Map coordinates: Not disclosed in the reviewed evidence. No opened source publishes a facility point, property designation or plan boundary at Målma. The Östergötland county board's draft facility plan is due by 31 December 2026. Last checked 19 Oct 2026. Government of Sweden: facility-plan assignment for the Valdemarsvik application
    What would change this

    Publication of the Målma plan map or plan description. Next scheduled check: 7 Jan 2027.

  • Next decision and prerequisites. The next steps are the Östergötland county board's draft facility plan, the municipality's approval of the plan and the application, and then the Government's decision. Approval would lead to separate Environmental Code and Nuclear Activities Act permit reviews. Last checked 23 Oct 2026. Government of Sweden: Government review of new nuclear (status of applications)
    What would change this

    The draft facility plan, a municipal vote or a Government decision for Målma in Valdemarsvik. Next scheduled check: 21 Jan 2027.

  • Permissions and public process. The Government Offices list the application for Målma in Valdemarsvik as under preparation, with the Östergötland county administrative board drafting a facility plan on the Government's behalf. The municipality must approve both the plan and the application before the Government can decide, and Government approval does not replace permits under the Environmental Code and the Nuclear Activities Act. No municipal or Government decision is recorded. Last checked 23 Oct 2026. Government of Sweden: Government review of new nuclear (status of applications)
    What would change this

    A municipal decision on the facility plan or a Government decision on the Målma in Valdemarsvik application. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water). Kärnfull Next's newsroom entry, captured on 15 November 2026, says the Målma project in Valdemarsvik is based on a cooperation agreement with land-owner Latona Group securing permanent land rights. This is the developer's statement, not independent verification of a land registry entry. The Government's facility plan remains under preparation; the reported land-rights agreement does not establish construction permission or confirm grid or cooling-water arrangements. Last checked 16 Nov 2026. Government of Sweden: Government review of new nuclear (status of applications); Kärnfull Next news list
    What would change this

    The published draft facility plan or a grid or water arrangement for Målma in Valdemarsvik. Next scheduled check: 21 Jan 2027.

  • Spent fuel, waste and closure. The Swedish Radiation Safety Authority's opinion of 3 June 2026 on ReFirm Målma AB's government-approval application finds that the application does not show that conditions exist to take care of nuclear material and nuclear waste. It says the application relies on existing frameworks and SKB's disposal model, which currently do not cover new operators, and lacks a waste plan and named competence. Under Swedish law the license holder carries long-term responsibility for waste; the Government has not yet decided the application. Last checked 23 Oct 2026. SSM opinion on ReFirm Målma AB's application for government approval of a nuclear facility at Målma (SSM2026-2943-6)
    What would change this

    The Government's decision on the Målma application, or a supplemented application setting out a waste strategy and disposal route. Next scheduled check: 23 Jan 2027.

Evidence dates

(1 of 9 sources with a publication or document date)
Latest dated listed source publication: SSM opinion on ReFirm Målma AB's application for government approval of a nuclear facility at Målma (SSM2026-2943-6): 3 Jun 2026.Latest dated recorded event: Studsvik selects GE Vernova Hitachi and Samsung C&T for an initial four-unit BWRX-300 project: 3 Sep 2026.8 of 9 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(9)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Kärnfull Next SMR park at Målma, Valdemarsvik — https://smrmap.com/projects/knxt-valdemarsvik/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Kärnfull Next SMR park at Målma, Valdemarsvik”. Record reviewed 18 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/knxt-valdemarsvik/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.