Projects / Sweden · Licensing
Studsvik new nuclear at the Nyköping home site
Studsvik applied to the Swedish Government on 25 May 2026 for approval of up to 1,400 MW of new nuclear power (two to four light-water reactors) at its Nyköping home site.
Current status
- How current
- General record check . Bounded evidence review . 1 of 9 listed sources has a publication or document date recorded here: 14 Oct 2026. Swedish Government approval application for a nuclear facility at Studsvik, Nyköping: status (under review) confirmed against Government of Sweden: Government review of new nuclear (status of applications).
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Under review: Swedish Government approval application for a nuclear facility at Studsvik, Nyköping. An application under review is not a permit. All permissions and applications
- Latest development
- 3 Sep 2026 · Contract: Studsvik selects GE Vernova Hitachi and Samsung C&T for a four-unit BWRX-300 project. Studsvik selected GE Vernova Hitachi and Samsung C&T as strategic partners for an initial four-unit BWRX-300 project of up to 1.2 GW at Nyköping or Målma. Source: Studsvik: Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing 1.2 GW nuclear power project in Sweden (3 September 2026). Updates entry
More on this development
The first site is still to be decided. This is not an investment decision.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Module/unit count (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
- Same design
- 18 tracked: 1 construction, 4 licensing, 10 siting, 3 announced. 19 tracked at licensing across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Boiling water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The Government assigned the county administrative board to draft a facility plan by 31 December 2026. On 12 June 2026 the Government announced Studsvik AB's application for state support covering both alternative projects (Nyköping: two to four reactors, about 600-1,400 MW; Valdemarsvik: four to six reactors, about 1,200-1,600 MW); an application is not an award. The September 2026 BWRX-300 agreement covers this site and Valdemarsvik. The capacity ceiling is not stored as a plant total. Valdemarsvik (Kärnfull Next SMR park at Målma, Valdemarsvik) is the alternative site for the initial four-unit BWRX-300 project; only one of the two will host it. Studsvik's own 3 September 2026 release names GE Vernova Hitachi Nuclear Energy and Samsung C&T as strategic partners for the ReFirm program, with the first unit expected in the mid-2030s. Studsvik announced a public information meeting on the application with the county board and Nyköping municipality for 22 October 2026.
Key facts
- Design
- BWRX-300 (SMR)
- Technology
- Boiling water reactor (BWR) · light water
- Reactor vessel of this design
- 27 m tall, 4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 25.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Studsvik
- Vendor for linked design
- GE Vernova Hitachi Nuclear Energy
- Design origin
- United States: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
- Location
- Studsvik site, Nyköping · Sweden · precision: town or locality only
OpenStreetMap Nominatim locality 'Studsvik, Nyköpings kommun', the named home site; locality point, not a reactor plot. - Coordinates
- 58.7602, 17.3837 · town-level point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded. Only a range is published: two to four reactors at Nyköping.
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
Studsvik new nuclear at the Nyköping home site is recorded at Studsvik site, Nyköping, Södermanland, Sweden. Operator: Studsvik. Recorded vendor: GE Vernova Hitachi Nuclear Energy. Stage: Licensing. Location precision: town or locality only; town-level point (approximate).
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: 'Studsvik, Nyköpings kommun' (locality)
Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project. The linked design record states 870 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorStudsvik
- Reactor supplier
- Vendor for the linked designGE Vernova Hitachi Nuclear Energy
- Contractor
- Planned construction contractorSamsung C&T · sourceNamed with GE Vernova Hitachi as the execution team with single-point responsibility for construction in a 3 Sep 2026 exclusive agreement for a first four-unit project at Nyköping or Valdemarsvik; site not chosen; no FID or permit.
- Planned construction contractorGE Vernova Hitachi Nuclear Energy · sourceNamed with Samsung C&T as the execution team with single-point responsibility for construction in a 3 Sep 2026 exclusive agreement for a first four-unit project at Nyköping or Valdemarsvik; site not chosen; no FID or permit.
Source-backed project statement
GE Vernova's 3 September 2026 release says GE Vernova Hitachi leads reactor engineering, licensing support and cost estimation, and together with Samsung C&T acts as the execution team with single-point responsibility for construction and execution of an initial four-unit BWRX-300 project planned for either Nyköping or Valdemarsvik. This is an exclusive, time-limited development agreement. The site is not chosen and there is no investment decision or permission. Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project
- Funding and government decisions
Source-backed project statement GE Vernova's 3 September 2026 release says DS Investment Partners will lead the investment during the exclusivity period for the initial four-unit project, with GE Vernova's Financial Services business advising. The Swedish government said on 12 June 2026 that Studsvik AB had applied for state support covering two to four reactors at Nyköping. No amount is committed and the application is undecided. Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project; Government of Sweden: Studsvik applies for state support (Nyköping and Valdemarsvik)
- Programs and agreements naming the project
- Feasibility or siting study; activeKärnfull Next Re:Firm South program: candidate SMR sites in Karlshamn, Motala and Västervik
Not found in the sources we checked (3): Customer or offtaker; Fuel; Comparable schedule revision
- Customer or offtaker
Studsvik's 25 May 2026 application release and GE Vernova's 3 September 2026 release on the initial four-unit BWRX-300 project, planned for Nyköping or Valdemarsvik, name no buyer of the power or offtake agreement. The government's June 2026 note on the state-support application names none either. Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
GE Vernova's 3 September 2026 release describes Global Nuclear Fuel only in its company background and does not say it will supply the Nyköping or Valdemarsvik units. No fuel supplier or delivery for the project is named in the sources read. Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project
- Comparable schedule revision
Comparable schedule revision not established. Studsvik's 25 May 2026 application release aims for commercial operation of the first reactors in the 2030s, and GE Vernova's 3 September 2026 release expects the first unit of the four-unit project, at Nyköping or Valdemarsvik, in the mid-2030s. The later statement narrows the earlier one rather than moving it, and the record's events hold no revision pair. Studsvik applies to build up to 1,400 MW of new nuclear power at its home site in Nyköping; Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project
Not recorded in SMRMap's reviewed evidence (1): Site host or owner
- Site host or owner
Timeline
Recorded developments
- · Contract
Studsvik selects GE Vernova Hitachi and Samsung C&T for a four-unit BWRX-300 project - · Application submitted
Application submitted: Swedish Government approval application for a nuclear facility at Studsvik, Nyköping
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Site applications and decisions
- Swedish Government approval application for a nuclear facility at Studsvik, Nyköping
Site permission sought · Under review · Government of Sweden · submitted 25 May 2026
Studsvik AB applied on 25 May 2026 for the Government's approval of a nuclear facility for two to four light-water reactors of about 600-1,400 MW in total at Studsvik in Nyköping municipality; on 9 June 2026 the Government assigned the Södermanland county administrative board to draft a facility plan by 31 December 2026. It is an application under the Act on the Government's approval of nuclear facilities (SFS 2026:585), which the Government's status page of 2 October 2026 lists as under preparation. Approval needs municipal consent and a facility plan in force; it would replace the Environmental Code permissibility review but not licensing under the Environmental Code and the Nuclear Activities Act. No approval, license or construction is established.
Sources: Government of Sweden: Government review of new nuclear (status of applications); Government of Sweden: facility-plan assignment for the Studsvik applicationStatus confirmed on against Government of Sweden: Government review of new nuclear (status of applications). This confirms the recorded status only; the general record check date remains separate.
Assessments of the design (not of this site)
(2)
- BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs - CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes)
- Evidence review. The source review records a range of two to four reactors at Nyköping and stores no single module count or plant total. The Government notice published 9 June 2026 says Studsvik AB applied on 25 May 2026 to approve a nuclear facility in Nyköping, described as two to four light-water reactors of about 600 to 1,400 MW electrical in total. The status list shows Studsvik, Nyköping, received 2026-05-25, under preparation. The county board must report the facility plan by 31 December 2026. Approval under this process does not replace Environmental Code or Nuclear Activities Act licensing. A 3 September 2026 GE Vernova release says an initial four-unit BWRX-300 project of 1.2 GW is planned for either the existing Nyköping site or the Målma site in Valdemarsvik. That 1.2 GW figure is not stored as this site's plant total. A separate notice published 12 June 2026 is a state-support application covering both Nyköping and Valdemarsvik, not an award. World Nuclear News says commercial operation of the first reactors in the 2030s is an aim, subject to permits. Last checked 20 Oct 2026. Government of Sweden: facility-plan assignment for the Studsvik application; Government of Sweden: Government review of new nuclear (status of applications); Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project; Government of Sweden: Studsvik applies for state support (Nyköping and Valdemarsvik); WNN: Third application lodged for Swedish SMR plant; Studsvik: Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing 1.2 GW nuclear power project in Sweden (3 September 2026); Studsvik: Invitation to information meeting on planned nuclear power development at Studsvik
What would change this
The Södermanland county board's Nyköping facility-plan proposal, due by 31 December 2026, or a decision that this site rather than Målma will host the four-unit BWRX-300 project. Next scheduled check: 7 Jan 2027.
- Plant capacity (scope qualified): Not disclosed in the reviewed evidence. No single plant total is fixed. The Government's facility-plan assignment describes two to four light-water reactors of about 600–1,400 MW in total, and Studsvik's release gives 600 to 1,400 MWe. The initial four-unit BWRX-300 project of up to 1.2 GW is planned for Nyköping or Valdemarsvik. Last checked 18 Oct 2026. Government of Sweden: facility-plan assignment for the Studsvik application; Studsvik applies to build up to 1,400 MW of new nuclear power at its home site in Nyköping
What would change this
Studsvik's site decision or the Södermanland draft facility plan stating a capacity. Next scheduled check: 18 Jan 2027.
- Module/unit count: Not disclosed in the reviewed evidence. Only a range is published: two to four reactors at Nyköping. The four-unit BWRX-300 project may go to Nyköping or Målma. Last checked 18 Oct 2026. Government of Sweden: facility-plan assignment for the Studsvik application
What would change this
Studsvik's site decision or the draft facility plan. Next scheduled check: 18 Jan 2027.
- Next decision and prerequisites. The next steps are the Södermanland county board's draft facility plan, the municipality's approval of the plan and the application, and then the Government's decision. Approval would lead to separate Environmental Code and Nuclear Activities Act permit reviews. Last checked 23 Oct 2026. Government of Sweden: Government review of new nuclear (status of applications)
What would change this
The draft facility plan, a municipal vote or a Government decision for Studsvik in Nyköping. Next scheduled check: 21 Jan 2027.
- Permissions and public process. The Government Offices list the application for Studsvik in Nyköping as under preparation, with the Södermanland county administrative board drafting a facility plan on the Government's behalf. The municipality must approve both the plan and the application before the Government can decide, and Government approval does not replace permits under the Environmental Code and the Nuclear Activities Act. No municipal or Government decision is recorded. Last checked 23 Oct 2026. Government of Sweden: Government review of new nuclear (status of applications)
What would change this
A municipal decision on the facility plan or a Government decision on the Studsvik in Nyköping application. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). Studsvik's 25 May 2026 application release says the new capacity would be built at and around its existing nuclear site in Nyköping Municipality, and the September 2026 GE Vernova release says Studsvik operates an existing licensed nuclear facility there. The county board's facility plan, due by 31 December 2026, will set land and water use. These sources do not describe a grid connection, cooling-water arrangement or the exact land boundary for the new reactors. Last checked 23 Oct 2026. Studsvik applies to build up to 1,400 MW of new nuclear power at its home site in Nyköping; Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project
What would change this
Publication of the Södermanland county board's draft facility plan for Studsvik or a grid-connection agreement for the Nyköping project. Next scheduled check: 7 Jan 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. Studsvik's 25 May 2026 application release and the World Nuclear News report of 26 May describe the reactors, capacity and timetable but not how spent fuel and nuclear waste from the new units would be stored or disposed of. The Government's review page says approval depends partly on conditions for taking care of the nuclear waste produced, and as of early October 2026 the radiation safety authority had published an opinion only on the separate Målma application. Last checked 23 Oct 2026. Studsvik applies to build up to 1,400 MW of new nuclear power at its home site in Nyköping; Government of Sweden: Government review of new nuclear (status of applications); SSM, work on new nuclear power
What would change this
A published SSM opinion on Studsvik's Nyköping application or the Government's decision on it. Next scheduled check: 23 Jan 2027.
Evidence dates
(1 of 9 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(9)
- Studsvik applies to build up to 1,400 MW of new nuclear power at its home site in Nyköping (company, accessed 18 Oct 2026)
- WNN: Third application lodged for Swedish SMR plant (news report, accessed 2 Oct 2026)
- Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing nuclear project (company, accessed 2 Oct 2026)
- Studsvik: Studsvik, GE Vernova Hitachi and Samsung C&T commit to advancing 1.2 GW nuclear power project in Sweden (3 September 2026) (company, accessed 18 Oct 2026)
- Government of Sweden: Government review of new nuclear (status of applications) (government, accessed 3 Nov 2026)
- Government of Sweden: facility-plan assignment for the Studsvik application (government, accessed 18 Oct 2026)
- Government of Sweden: Studsvik applies for state support (Nyköping and Valdemarsvik) (government, accessed 18 Oct 2026)
- Studsvik: Invitation to information meeting on planned nuclear power development at Studsvik (company, published 14 Oct 2026, accessed 18 Oct 2026)
- SSM, work on new nuclear power (regulator, accessed 5 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Studsvik new nuclear at the Nyköping home site — https://smrmap.com/projects/studsvik-nykoping/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Studsvik new nuclear at the Nyköping home site”. Record reviewed 18 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/studsvik-nykoping/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.