Projects / United States · Siting
Last Energy Haskell County PWR-20 campus
Thirty proposed PWR-20 units at one controlled Haskell County, Texas campus.
Current status
- How current
- General record check . Bounded evidence review . 2 of 5 listed sources have a publication or document date recorded here; the newest is Jul 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Announced 28 Feb 2025 · Announcement: Last Energy Haskell County PWR-20 campus proposal documented. Last Energy announced thirty proposed PWR-20 units at one controlled Haskell County campus. Source: Last Energy Haskell County proposal; NRC pre-application activities: Last Energy Haskell County. Updates entry
More on this development
The announcement did not specify the electrical gross/net basis; the later NRC pre-application page calls 20 MWe per unit gross. This is one proposed site, not thirty deployment sites, and no early site permit is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- No operator is recorded.
- No map pin is shown for this record.
- Expected for this stage but not recorded as a structured fact: Site location recorded as disclosed. A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
- Same design
- 6 tracked: 1 licensing, 2 siting, 3 announced. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Pressurized water reactor. How it works, with a 3D view.
View on the map · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Twenty MWe gross is per unit, per the NRC pre-application page. The NRC records pre-application engagement for this named site; Last Energy's earlier announcement said it was preparing an early site permit. No early site permit or construction permit is recorded. This is one project, not thirty deployment sites. The July 2026 regulatory engagement plan instead names Caldwell County as the priority site (a separate record); its near-term filing schedule is not established as Haskell's schedule. That plan gives the PWR-20 as 20 MWe net and 80 MWt, while the NRC page says 20 MWe gross; the stored figure keeps the NRC page's gross basis.
Key facts
- Design
- PWR-20 (Microreactor)
- Technology
- Pressurized water reactor (PWR) · light water. The 2024 SMR Technology Catalogue describes a single-loop pressurized water reactor, so no integral layout is recorded.
- Reactor vessel of this design
- 8.9 m tall, 1.8 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 65.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Not recorded
- Vendor for linked design
- Last Energy
- Location
- Haskell County · United States · precision: region only
Last Energy names a controlled ~200-acre site in Haskell County without a parcel point. The NuclearChain export gives only a county-area point for this proposal, so no pin is shown. - Coordinates
- Region only, no map pin
- Electrical capacity
- 20 MWe (gross) · scope: module
- Thermal capacity
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 9 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
Last Energy Haskell County PWR-20 campus is recorded at Haskell County, Texas, United States. Operator: No operator is recorded. Recorded vendor: Last Energy. Stage: Siting. Location precision: region only; region only, no map pin.
Recorded electrical output is 20 MWe (gross), scope module. Modules planned: 30. Thermal output is not recorded on this project. The linked design record states 80 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerLast Energy · source
- Reactor supplier
- Vendor for the linked designLast Energy
- Fuel
- Fuel form stated for PWR-20UO2 pellet / 17x17 grid
Last Energy's 28 February 2025 release says the company has secured its first full core load of fuel, scheduled to arrive in September 2026. The sentence does not say the fuel is for the Haskell County units, so it is not recorded as this project's fuel. No supplier is named. Last Energy Haskell County proposal
Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
- Customer or offtaker
Last Energy's 28 February 2025 release says the Haskell County microreactors would serve American data center customers across Texas and supply offtakers by private wire and grid transmission. It names no buyer, agreement or contracted quantity for Haskell. Its existing agreements for over 80 microreactors are in Europe. Last Energy Haskell County proposal
- Contractor
Last Energy's 28 February 2025 release says the company itself will build the microreactors on its controlled Haskell County site, and the NRC's pre-application page names Last Energy only. Neither names an engineering, manufacturing or construction contractor for the Haskell units. Last Energy Haskell County proposal; NRC pre-application activities: Last Energy Haskell County
- Funding and government decisions
Last Energy's 28 February 2025 release and the NRC's pre-application page state no funder, amount, loan or financing for the Haskell County campus. Last Energy Haskell County proposal
- Comparable schedule revision
Comparable schedule revision not established. Last Energy's 28 February 2025 release says it was preparing to file for an early site permit, and the NRC's page shows pre-application activity from May 2025 to the present. Neither gives an earlier and later date for the same construction or operation milestone. Last Energy's February 2025 engagement plan to the NRC targeted a Part 52 early site permit by June 2025 for at least one Texas site under its control, without naming it; its 28 February 2025 release describes Haskell County site control and early-site-permit preparation, so the plan probably concerns Haskell (an inference). The NRC page, updated 15 September 2026, lists no early site permit application. The June 2025 target passed without a recorded filing, and no later date for that permit has been stated. Last Energy Haskell County proposal; NRC pre-application activities: Last Energy Haskell County; Last Energy Regulatory Engagement Plan, February 2025 (ML25038A060)
Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Reviewed 20 Oct 2026: not disclosed in the reviewed evidence.
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- Announced · Announcement
Last Energy Haskell County PWR-20 campus proposal documented
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. The source review uses the 28 February 2025 announcement of 30 microreactors on a 200-acre Haskell County site and of preparation to file an early site permit, and its cited announcement sentences do not state 20 MWe. The NRC pre-application page says the Haskell, Texas site would house Last Energy's PWR-20 generating 20 MWe gross, and that the activity is pre-application for a future application, dated on that page as May 2025 to present. No early site permit or construction permit is on these pages. The company says it has site control. Thirty units are one campus, not thirty sites. The stored 30 modules and 20 MWe module figure stay. The participating organizations retain only their source-supported roles; a reactor operator is not assigned from the study, proposer, parent, existing-fleet or proposed-owner relationship. Last checked 20 Oct 2026. Last Energy Haskell County proposal; NRC pre-application activities: Last Energy Haskell County
What would change this
An NRC docket for a Haskell County early site permit or construction permit, or a notice that changes the 30-unit plan. Next scheduled check: 20 Jan 2027.
- Operator or intended licensed owner: Not disclosed in the reviewed evidence. The reviewed sources establish other participant roles, but do not appoint the recorded party as this reactor’s operator. The operator remains unassigned; this does not assert that no operator exists. Last checked 20 Oct 2026. Last Energy Haskell County proposal; NRC pre-application activities: Last Energy Haskell County
What would change this
A project-specific filing, operating agreement or developer statement explicitly names the proposed reactor operator. Next scheduled check: 20 Jan 2027.
- Next decision and prerequisites. Last Energy's July 2026 regulatory engagement plan lists its near-term NRC steps as a limited work authorization application in September 2026, a docket number in October, and a Part 57 exemption request and full application in early and mid-2027, but it calls Caldwell County its priority site and does not tie these steps to Haskell. No dated next step for the Haskell site appears in the sources read, and the 2025 early site permit plan has no recorded filing. Last checked 23 Oct 2026. Last Energy Regulatory Engagement Plan, Revision 1.0 (US000-NLC-REP-0001)
What would change this
An NRC filing naming the Haskell site, or a Last Energy statement on Haskell's schedule. Next scheduled check: 23 Apr 2027.
- Permissions and public process. The NRC's Last Energy page, updated 15 September 2026, says the NRC has been in pre-application activities since May 2025 on a future application at Last Energy's Haskell, Texas site; Last Energy's February 2025 announcement said it was preparing to file for an early site permit after local stakeholder briefings. However, Last Energy's July 2026 regulatory engagement plan calls its Caldwell County site the priority for NRC engagement and lists Haskell among projects under development. No Haskell application, permit or public hearing is recorded. Last checked 23 Oct 2026. NRC pre-application activities: Last Energy Haskell County; Last Energy Haskell County proposal; Last Energy Regulatory Engagement Plan, Revision 1.0 (US000-NLC-REP-0001)
What would change this
An NRC application or docket for the Haskell site, or an NRC page update dropping or confirming Haskell. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). Last Energy's February 2025 announcement says it has obtained site control of a 200-acre Haskell County site, will supply offtakers through a mix of private wire and grid transmission, and has filed for a grid connection with ERCOT. These are the company's statements; the sources read show no ERCOT study result or interconnection agreement, no private-wire customer contract, and no cooling-water arrangement. Last checked 23 Oct 2026. Last Energy Haskell County proposal
What would change this
An ERCOT interconnection agreement or study result, or a named offtaker contract for the Haskell site. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure: Not disclosed in the reviewed evidence. Last Energy's February 2025 Haskell announcement does not address spent fuel. Its July 2026 regulatory engagement plan says each PWR-20 nuclear island runs on one core for about six years, stays sealed until decommissioning, and that spent fuel can remain sealed in place indefinitely. That is a design description for the reactor type, not a Haskell-specific storage, removal or disposal arrangement. Last checked 23 Oct 2026. Last Energy Regulatory Engagement Plan, Revision 1.0 (US000-NLC-REP-0001)
What would change this
A license application or environmental report for Haskell describing spent-fuel storage and responsibility. Next scheduled check: 23 Apr 2027.
Evidence dates
(2 of 5 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(5)
- Last Energy Haskell County proposal (company, accessed 1 Oct 2026)
- Global Energy Monitor Global Nuclear Power Tracker (directory or tracker, accessed 2 Oct 2026)
- NRC pre-application activities: Last Energy Haskell County (regulator, accessed 9 Oct 2026)
- Last Energy Regulatory Engagement Plan, Revision 1.0 (US000-NLC-REP-0001) (company, published Jul 2026, accessed 23 Oct 2026)
- Last Energy Regulatory Engagement Plan, February 2025 (ML25038A060) (company, dated Feb 2025, accessed 28 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Last Energy Haskell County PWR-20 campus — https://smrmap.com/projects/last-energy-haskell/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Last Energy Haskell County PWR-20 campus”. Record reviewed 9 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/last-energy-haskell/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.