PWR-20
Last Energy identifies PWR-20 as its 20 MWe microreactor design; the recorded electrical basis remains unspecified. The UK regulators completed a Preliminary Design Review in June 2025 on three selected topics: organizational arrangements, environment and decommissioning, and safety-analysis maturity. Their report identifies further work, including disposal routes for certain reactor materials. This early review does not replace a full design assessment, nuclear site license or environmental permits. ONR describes a December 2027 site-license decision as Last Energy's aspiration, conditional on adequate submissions and schedule; it is not a granted permission.
- Reactor type
- Pressurized water reactor. How it works, with a 3D view.
- Projects
- Licensing: Last Energy first commercial PWR-20 site, Caldwell County. Furthest recorded stage of 6 using this design. Development status as stated: Detailed design.
- Evidence
- 3 sources; first primary source: Last Energy Haskell County proposal. Record reviewed 1 Oct 2026.
Key facts · Tracked projects · Agreements · Sources · Evidence · Regulatory actions · Its projects in the table · Compare with other designs
Key facts
- Class
- Microreactor
- Technology
- Pressurized water reactor (PWR)
The 2024 SMR Technology Catalogue describes a single-loop pressurized water reactor, so no integral layout is recorded. - Coolant
- Light water
- Spectrum
- Thermal
- Developer / vendor(s)
- Last Energy
- Module electrical
- 20 MWe (gross/net unspecified)
- Module thermal
- 80 MWth (nameplate; basis unspecified)
- Fuel form
- UO2 pellet / 17x17 grid
- Development status (as stated)
- Detailed design
- Reactor vessel
- 8.9 m tall, 1.8 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 65.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.All vessels to scale10 m bar; a person 1.8 m tallPWR-20
8.9 m tall, 1.8 m across - Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 1 Oct 2026 (record review date, not proof of current availability or a deployment)
Tracked deployment projects
- Last Energy Haskell County PWR-20 campus — Siting · United States
- Last Energy first commercial PWR-20 site, Caldwell County — Licensing · United States
- Last Energy Llynfi PWR-20 proposal — Siting · United Kingdom
- Last Energy London Gateway PWR-20 proposal — Announced · United Kingdom
- Last Energy ten-SMR plant for the Legnica Special Economic Zone (2022) — Announced · Poland
- Last Energy PWR-20 demonstrator at RATEN Mioveni (2022 plan) — Announced · Romania
Agreements naming this design (2)
Agreements, plans, studies and government programs whose sources name this design. They are not deployment projects.
- Last Energy PWR-20 licensing engagement with Romania's regulator CNCAN — Regulatory engagement · Active · announced 7 Oct 2024
Concerns Romania - Enea and Last Energy letter of intent to cooperate on SMRs in Poland — Cooperation agreement or MOU · Status not established · announced Jun 2022
Concerns Poland
Design sources
(3)
- Last Energy Haskell County proposal (company, accessed 1 Oct 2026)
- Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition) (IAEA/NEA, published Jun 2025, accessed 2 Oct 2026)
- ONR and Environment Agency: Last Energy PWR-20 Preliminary Design Review summary (regulator, accessed 14 Oct 2026)
Evidence and open questions
(2 notes)
- Evidence review. The 2024 SMR Technology Catalogue (third edition, June 2025) describes Last Energy's PWR-20 as a modular PWR with light water coolant and moderator, 80 MWth / 20 MWe (nominal), forced circulation (4 pumps), UO2 pellets in a 17x17 grid below 4.95% enrichment, for distributed baseload power and combined heat and power, at 'Detailed Design'; its licensing paragraph still projects commercial operation in 2025, which is a stale edition-dated claim. ONR and the Environment Agency completed a Preliminary Design Review of the PWR-20 concept in June 2025 on three selected topics; ONR records Last Energy's aspiration to a nuclear site license decision for the Llynfi site by December 2027 as conditional, and says the PDR is not a substitute for design assessment, site licensing or permitting. Last Energy's 28 February 2025 release announces 30 microreactors in Haskell County, Texas and says the PWR-20 produces 20 MWe. Deployment links supported: the Haskell County project (Last Energy release) and the Llynfi project (ONR); London Gateway and Mioveni are not named in any opened source. Stored vendor, light-water coolant, 20 MWe with unspecified basis and fuel form stay; the recorded 80 MWth thermal rating matches the catalog's 80 MWth, the stored thermal spectrum is not stated, and the catalog calls it a PWR rather than an integral PWR. Last checked 19 Oct 2026. Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition); ONR and Environment Agency: Last Energy PWR-20 Preliminary Design Review summary; Last Energy Haskell County proposal
What would change this
Last Energy's nuclear site license application for Llynfi to ONR (and ONR's decision), or an NRC early site permit application for Haskell County, either of which would carry a licensed per-unit thermal and electrical rating. Next scheduled check: 19 Jan 2027.
- Technology family. The 2024 SMR Technology Catalogue describes a single-loop pressurized water reactor, so no integral layout is recorded. Last checked 1 Nov 2026. Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition)
What would change this
A developer, regulator or IAEA document that states this design's primary-circuit layout. Next scheduled check: 1 Feb 2027.
Regulatory actions
Compare reviews and approvals across designs
Construction applications and decisions
- Last Energy Caldwell site phased construction permit application, Part 1 (with limited work authorization request) — Last Energy first commercial PWR-20 site, Caldwell County
Construction permission sought · Application received · NRC · submitted 20 Oct 2026 · docket 99902140 · ADAMS ML26294A162 · 91 FR 69895
Last Energy filed Part 1 of a two-part phased construction permit application on 20 October 2026 for a PWR-20 facility at the Caldwell Site in Caldwell County, Texas. Part 1 includes a limited work authorization request under 10 CFR 50.10(d) covering early foundation work, with financial information, a preliminary safety analysis report for the LWA scope, an environmental report and a site redress plan. The NRC published a notice of receipt on 5 November 2026 (91 FR 69895). That notice reports receipt and says later notices will address whether the application is acceptable for docketing; it does not report an acceptance decision or grant a limited work authorization or construction permit. Receipt authorizes no construction.
Sources: Federal Register 91 FR 69895 (5 Nov 2026): Last Energy phased construction permit application with limited work authorization request, Caldwell site (notice of receipt)