Projects / United States · Canceled
B&W mPower plan at TVA's Clinch River site (2013-2017)
The B&W mPower plan at TVA's Clinch River site is a historical proposal, now recorded as canceled.
Current status
- How current
- General record check . Bounded evidence review . None of the 3 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Developer or proposer (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Integral pressurized water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Under a February 2013 contract, TVA, Babcock & Wilcox and Generation mPower were preparing an NRC license application for up to four B&W mPower SMRs at TVA's Clinch River site, with DOE cost sharing under an April 2013 cooperative agreement. TVA is the site owner and one of the three parties preparing that application. The 2013 report does not name TVA as the reactor operator, so that operator link is not kept. The consortium shelved the mPower project in March 2017. A 2017 account also describes a planned two-reactor plant and says Bechtel notified BWXT on 3 March 2017 that it was terminating the program. Neither the 2013 upper bound nor the later two-reactor description is stored as a selected count. TVA's BWRX-300 project at the same site is a separate record; this historical plan shares the site's pin.
Key facts
- Design
- mPower (SMR)
- Technology
- Integral pressurized water reactor (iPWR) · light water
- Operator(s)
- Not recorded
- Vendor for linked design
- —
- Location
- Clinch River Nuclear Site · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for Clinch River SMR unit 1 (BWRX-300) at TVA's Clinch River site (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); site-area point, not a surveyed plot. - Coordinates
- 35.88944, -84.3793 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded. The 2013 text says up to four modules.
- Inclusion basis
- Earlier-plan record (historical SMR program)
- Confidence
- medium
- Record reviewed
- 19 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
B&W mPower plan at TVA's Clinch River site (2013-2017) is recorded at Clinch River Nuclear Site, Tennessee, United States. Operator: No operator is recorded. Recorded vendor: No vendor is recorded. Stage: Canceled. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: TVA Clinch River BWRX-300.
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'clinch-river-smr-nuclear-power-plant-1' (35.88944, -84.3793)
Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project. The linked design record states 575 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Customer or offtaker
Source-backed project statement TVA's fiscal 2013 annual report says SMRs at Clinch River would provide an important option for clean base-load energy for TVA's customers, with TVA preparing the license application and owning the site. That is a possible supply to TVA's own system, not a purchase agreement, and TVA said it would not decide on construction for several years. The project was shelved in March 2017. TVA annual report on Form 10-K, fiscal year 2013 (mPower at Clinch River)
- Contractor
Source-backed project statement TVA's fiscal 2013 annual report says that under a contract TVA executed with Babcock & Wilcox in February 2013, TVA, B&W and Generation mPower, a B&W affiliate minority-owned by Bechtel, were preparing an NRC license application for up to four mPower SMRs at Clinch River. That was preparatory licensing work, not a construction contract. ANS reported that Bechtel took the program lead in 2016 and terminated it on 3 March 2017. TVA annual report on Form 10-K, fiscal year 2013 (mPower at Clinch River); ANS Nuclear Newswire: mPower consortium halts project (16 March 2017)
- Funding and government decisions
Source-backed project statement TVA's fiscal 2013 annual report says that under an April 2013 DOE cooperative agreement with B&W, TVA was reimbursed through B&W for roughly half of its qualified site-study and license-development costs, retroactive to October 2012. ANS reported in March 2017 that DOE reduced its funding after B&W scaled back in 2014 and halted payments at the end of 2014, and that the program ended in 2017 for lack of funding. TVA annual report on Form 10-K, fiscal year 2013 (mPower at Clinch River); ANS Nuclear Newswire: mPower consortium halts project (16 March 2017)
- Site host or owner
- Current site ownerTennessee Valley Authority · source
Not found in the sources we checked (2): Fuel; Comparable schedule revision
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
TVA's fiscal 2013 annual report and ANS's March 2017 account describe licensing preparation, DOE cost sharing and the project's shelving, but name no fuel supplier, fabrication or delivery for mPower units at Clinch River. The plan ended before any license application. ANS Nuclear Newswire: mPower consortium halts project (16 March 2017)
- Comparable schedule revision
Comparable schedule revision not established. TVA's fiscal 2013 annual report says TVA would not decide to submit the license application until mid-2015 and would make construction decisions several years later. ANS's 2017 account gives no later date for the same step before the March 2017 shelving. No earlier and later date for the same milestone is shown in these sources. TVA annual report on Form 10-K, fiscal year 2013 (mPower at Clinch River)
Not recorded in SMRMap's reviewed evidence (4): Project proposer or applicant; Operator or intended licensed owner; Reactor supplier; Programs and agreements naming the project
- Project proposer or applicant
- Reviewed 19 Oct 2026: not disclosed in the reviewed evidence.
- Operator or intended licensed owner
- Reactor supplier
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes, 1 not yet reviewed)
- Evidence review. The TVA report supports 2013 preparation of an application for up to four modules and TVA's ownership of the site, that it does not name an operator, and that the 2017 account supports the 3 March 2017 termination notice and a two-reactor description that does not replace the earlier upper bound. Last checked 20 Oct 2026. TVA annual report on Form 10-K, fiscal year 2013 (mPower at Clinch River); ANS Nuclear Newswire: mPower consortium halts project (16 March 2017)
What would change this
A BWXT, Bechtel, or TVA document that states the termination in the company's own words. Next scheduled check: 20 Jan 2027.
- Developer or proposer: Not disclosed in the reviewed evidence. The 2013 report names TVA, Babcock & Wilcox and Generation mPower as the parties preparing the application. It does not single out a plant vendor or a reactor operator. Only TVA is linked, as the site owner. Last checked 19 Oct 2026. TVA annual report on Form 10-K, fiscal year 2013 (mPower at Clinch River)
What would change this
A source that identifies the reactor vendor or the intended operator for this Clinch River plan. Next scheduled check: 19 Jan 2027.
- Plant capacity (scope qualified): Not disclosed in the reviewed evidence. The Clinch River application text states no plant output. The linked design profile's module rating is not copied onto this project. Last checked 19 Oct 2026. TVA annual report on Form 10-K, fiscal year 2013 (mPower at Clinch River)
What would change this
An application that states the Clinch River plant output. Next scheduled check: 19 Jan 2027.
- Module/unit count: Not disclosed in the reviewed evidence. The 2013 text says up to four modules. A 2017 account describes a two-reactor plant. Neither statement selects a count, so the count stays empty. Last checked 19 Oct 2026. ANS Nuclear Newswire: mPower consortium halts project (16 March 2017)
What would change this
A filing that selects the number of mPower modules at Clinch River. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites: Not applicable. The American Nuclear Society reported in March 2017 that the mPower consortium had ended the project planned for TVA's Clinch River site, so this proposal has no pending decision. TVA's later Clinch River work for other designs is a separate record. Last checked 23 Oct 2026. ANS Nuclear Newswire: mPower consortium halts project (16 March 2017)
What would change this
A statement reviving mPower at Clinch River. Next scheduled check: 21 Jan 2027.
- Permissions and public process. TVA's fiscal 2013 annual report says TVA, B&W and Generation mPower were preparing an NRC license application for up to four mPower SMRs at Clinch River, with no decision to submit it before mid-2015. The American Nuclear Society reported in March 2017 that the consortium had ended the effort. No mPower application or license for this site is recorded. Last checked 23 Oct 2026. TVA annual report on Form 10-K, fiscal year 2013 (mPower at Clinch River); ANS Nuclear Newswire: mPower consortium halts project (16 March 2017)
What would change this
An NRC record of any mPower application for Clinch River. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). The proposal used TVA's Clinch River site in Roane County, Tennessee; by fiscal 2013 TVA had completed about half of the subsurface studies needed for the environmental review and license application. No grid or cooling arrangement for mPower units is described. Last checked 23 Oct 2026. TVA annual report on Form 10-K, fiscal year 2013 (mPower at Clinch River)
What would change this
A TVA or NRC document describing mPower site infrastructure at Clinch River. Next scheduled check: 21 Jan 2027.
Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.
Evidence dates
(0 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- TVA annual report on Form 10-K, fiscal year 2013 (mPower at Clinch River) (company, accessed 3 Oct 2026)
- ANS Nuclear Newswire: mPower consortium halts project (16 March 2017) (news report, accessed 3 Oct 2026)
- ANS Nuclear Newswire: mPower consortium halts project (16 March 2017) (news report, accessed 19 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: B&W mPower plan at TVA's Clinch River site (2013-2017) — https://smrmap.com/projects/mpower-clinch-river/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “B&W mPower plan at TVA's Clinch River site (2013-2017)”. Record reviewed 19 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/mpower-clinch-river/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.