Projects / United States · Announced
Microreactor at Naval Weapons Station Crane
The Navy announced a commercially owned and operated microreactor at Naval Weapons Station Crane through the Army's Janus Program in September 2026.
Current status
- How current
- General record check . Bounded evidence review . 1 of 4 listed sources has a publication or document date recorded here: 20 Oct 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Company announcement 20 Oct 2026 · Announcement: Radiant announces Kaleidos selection for Naval Weapons Station Crane. The company identifies the vendor and design for the previously announced Indiana microreactor proposal. Source: Radiant announces Navy selection of Kaleidos for Naval Weapons Station Crane (published 20 Oct 2026). Updates entry
More on this development
Company-reported selection; testing, environmental review, site preparation and regulatory coordination remain ahead. No Crane-specific capacity or operating date is inferred.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 4 tracked: 1 commissioning, 1 siting, 2 announced. 96 tracked at announced across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- High-temperature gas-cooled reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
On 20 October, Radiant announced its selection to deploy Kaleidos at Crane. This company-reported selection identifies the vendor and design; it does not establish an intended licensed operator, construction or operating permission, a site-specific rating or a reactor count. The Navy is the host. Radiant says design refinement, prototype testing, environmental review, site preparation and regulatory coordination precede deployment. The earlier September 2028 installation target remains a reported target, not an achieved milestone or a date newly confirmed by the October announcement.
Key facts
- Design
- Kaleidos (Microreactor)
- Technology
- High-temperature gas-cooled reactor (HTGR) · helium
- Operator(s)
- Not recorded
- Vendor for linked design
- Radiant Industries
- Location
- Naval Weapons Station Crane · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Installation point from the Wikipedia article for the Crane naval installation; the sources name the installation but no pad or parcel on it, so this marks the base area, not a reactor site (Eielson and Buckley precedent). - Coordinates
- 38.8701, -86.8344 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 25 Oct 2026
Site and capacity notes
Microreactor at Naval Weapons Station Crane is recorded at Naval Weapons Station Crane, Indiana, United States. Operator: No operator is recorded. Recorded vendor: Radiant Industries. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: Wikipedia: Naval Surface Warfare Center Crane Division (article coordinates), Article coordinate 38.8701, -86.8344 on 'Naval Surface Warfare Center Crane Division', read 30 October 2026
Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project. The linked design record states 3.5 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Reactor supplier
- Vendor for the linked designRadiant Industries
- Customer or offtaker
Source-backed project statement The American Nuclear Society's 11 September 2026 report quotes the Defense Department saying the Crane microreactor will provide reliable, around-the-clock power independent of the commercial grid to sustain critical operations, and World Nuclear News on 14 September 2026 reports the same. The stated user is the Naval Weapons Station Crane installation, which is also the host. No power purchase agreement or other buyer is named, and a separate Indiana and Eli Lilly letter of intent is not tied to Crane. ANS: Navy's first terrestrial reactor coming to Indiana's NWS Crane; WNN: Indiana to get its first power-producing nuclear reactor
- Fuel
- Fuel form stated for KaleidosTRISO
- Enrichment stated for Kaleidos19.75%
The September 2026 reports reviewed here did not identify a Crane-specific fuel supplier or delivery. The later selection of Kaleidos is recorded separately and does not establish a project-specific fuel delivery. WNN: Indiana to get its first power-producing nuclear reactor; ANS: Navy's first terrestrial reactor coming to Indiana's NWS Crane
Not found in the sources we checked (3): Contractor; Funding and government decisions; Comparable schedule revision
- Contractor
The September 2026 source scope did not name a Crane developer or engineering/construction contractor. Radiant's later selection is now recorded as the vendor; vendor selection does not identify a separate awarded engineering or construction contract. ANS: Navy's first terrestrial reactor coming to Indiana's NWS Crane; WNN: Indiana to get its first power-producing nuclear reactor
- Funding and government decisions
The September 2026 reports reviewed here state no Crane-specific funding amount or award. Radiant's later selection is recorded separately; a program-wide amount must not be allocated to this installation. WNN: Indiana to get its first power-producing nuclear reactor; ANS: Navy's first terrestrial reactor coming to Indiana's NWS Crane
- Comparable schedule revision
Comparable schedule revision not established. The American Nuclear Society's 11 September 2026 report and World Nuclear News' 14 September 2026 report both say the Crane reactor will be installed by September 2028. The same target in two reports of one announcement is not a revision. ANS: Navy's first terrestrial reactor coming to Indiana's NWS Crane; WNN: Indiana to get its first power-producing nuclear reactor
Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Operator or intended licensed owner; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Operator or intended licensed owner
- Programs and agreements naming the project
Timeline
Recorded developments
- Company announcement · Announcement
Radiant announces Kaleidos selection for Naval Weapons Station Crane
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(9 notes)
- Evidence review. Radiant's 20 October original announcement names its Kaleidos design for Crane, superseding September reports that left the vendor unnamed. The Navy original was located but access was blocked; selection is attributed to Radiant. The company lists design refinement, testing, environmental review, site preparation and regulatory coordination before deployment. No operator appointment, site-specific capacity, count or permission is inferred. The September 2028 installation target remains historical target context. Last checked 25 Oct 2026. Radiant announces Navy selection of Kaleidos for Naval Weapons Station Crane; WNN: Indiana to get its first power-producing nuclear reactor; ANS: Navy's first terrestrial reactor coming to Indiana's NWS Crane
What would change this
An original Navy/Army Crane-specific award, developer announcement or regulatory instrument identifying the reactor, operator and authorized next step. Next scheduled check: 19 Jan 2027.
- Design identified. Radiant's 20 October 2026 announcement identifies Kaleidos as the selected design for Crane. This is company-reported selection, not a design approval or deployment permission. Last checked 25 Oct 2026. Radiant announces Navy selection of Kaleidos for Naval Weapons Station Crane; ANS: Navy's first terrestrial reactor coming to Indiana's NWS Crane
What would change this
An original Navy/Army Crane-specific award, developer announcement or regulatory instrument identifying the reactor, operator and authorized next step. Next scheduled check: 19 Jan 2027.
- Developer or proposer. Radiant's original announcement identifies the company as selected to deploy Kaleidos at Crane. The Navy remains the host. The announcement does not establish the intended licensed operating entity. Last checked 25 Oct 2026. Radiant announces Navy selection of Kaleidos for Naval Weapons Station Crane; WNN: Indiana to get its first power-producing nuclear reactor; ANS: Navy's first terrestrial reactor coming to Indiana's NWS Crane
What would change this
An original Navy/Army Crane-specific award, developer announcement or regulatory instrument identifying the reactor, operator and authorized next step. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed: Not disclosed in the reviewed evidence. The installation is named, but a reactor parcel or boundary is not disclosed in the opened reports. Last checked 19 Oct 2026. WNN: Indiana to get its first power-producing nuclear reactor
What would change this
An original Navy/Army Crane-specific award, developer announcement or regulatory instrument identifying the reactor, operator and authorized next step. Next scheduled check: 19 Jan 2027.
- Primary source. Radiant's original company announcement dated 20 October 2026 was captured and read. The separate Navy announcement URL returned an access refusal (HTTP 403), so it is not treated as independently read or as a regulatory instrument. Last checked 25 Oct 2026. Radiant announces Navy selection of Kaleidos for Naval Weapons Station Crane; WNN: Indiana to get its first power-producing nuclear reactor; ANS: Navy's first terrestrial reactor coming to Indiana's NWS Crane
What would change this
An original Navy/Army Crane-specific award, developer announcement or regulatory instrument identifying the reactor, operator and authorized next step. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. Following its company-reported selection, Radiant lists design refinement, prototype testing, environmental review, site preparation and regulatory coordination before deployment. No completed permission or site work is established. The earlier September 2028 installation date remains a target, not a date newly confirmed by this announcement. Last checked 25 Oct 2026. Radiant announces Navy selection of Kaleidos for Naval Weapons Station Crane; WNN: Indiana to get its first power-producing nuclear reactor
What would change this
A Crane-specific environmental or licensing document, site-preparation evidence or dated deployment update. Next scheduled check: 21 Jan 2027.
- Permissions and public process. The September reporting reviewed here describes Crane within Janus, an Army-regulated-reactor goal by September 2028, and applicable NEPA review; it did not establish a Crane license or completed environmental review. The later company-reported vendor selection and remaining project steps are recorded separately under design_identified, developer_identified and next_decision. Last checked 23 Oct 2026. WNN: Indiana to get its first power-producing nuclear reactor; POWER: U.S. Army mobilizes $2.2B Janus program
What would change this
An Army licensing decision, NEPA document or vendor award for the Crane reactor. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). The reactor is proposed at Naval Weapons Station Crane in Indiana to support critical operations independently of the commercial grid. The September reports reviewed here identify no reactor plot, connection arrangement or site-specific water source. The later vendor selection is recorded separately and does not establish those site details. Last checked 23 Oct 2026. ANS: Navy's first terrestrial reactor coming to Indiana's NWS Crane; WNN: Indiana to get its first power-producing nuclear reactor
What would change this
A NEPA document or award naming the Crane reactor site and its connections. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. For the Janus program through which the Crane reactor is procured, Army officials said in August 2026 that all nuclear waste must leave an installation within two years of shutdown and that the Army plans one arrangement for the Department of Energy to take the spent fuel for payment. That arrangement was still to be negotiated, and no Crane-specific plan is published. Last checked 23 Oct 2026. POWER: U.S. Army mobilizes $2.2B Janus program; WNN: Indiana to get its first power-producing nuclear reactor
What would change this
An Army–DOE spent-fuel agreement or a NEPA document for the Crane reactor. Next scheduled check: 21 Jan 2027.
Evidence dates
(1 of 4 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(4)
- WNN: Indiana to get its first power-producing nuclear reactor (news report, accessed 10 Oct 2026)
- ANS: Navy's first terrestrial reactor coming to Indiana's NWS Crane (news report, accessed 2 Oct 2026)
- POWER: U.S. Army mobilizes $2.2B Janus program (news report, accessed 2 Oct 2026)
- Radiant announces Navy selection of Kaleidos for Naval Weapons Station Crane (company, published 20 Oct 2026, accessed 25 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Microreactor at Naval Weapons Station Crane — https://smrmap.com/projects/navy-crane-microreactor/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Microreactor at Naval Weapons Station Crane”. Record reviewed 25 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/navy-crane-microreactor/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.