Projects / Russia · Announced

Norilsk land small nuclear plant (RITM-400)

Planned land-based small nuclear plant for the isolated Norilsk power system.

Current status

Stage
Announced
How current
General record check . Bounded evidence review . None of the 3 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

No dated development is recorded. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
No actual dated development is recorded.
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • No map pin is shown for this record.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Pressurized water reactor. How it works, with a 3D view.
Schematic of Rolls-Royce SMR, this type's example. On the left, a reactor vessel holds a core of fuel assemblies, with control rod drives above its head.
Schematic of Rolls-Royce SMR, this type's example.

Description

Russia's December 2024 General Scheme to 2042 lists RITM-400 blocks at Norilsk as cumulative installed capacity: one block of 80 MW in 2032, two (160 MW) in 2034, three (240 MW) in 2036 and four (320 MW) from 2037; gross or net is not stated. Implementation depends on consumer agreements fixing volumes and prices, or another supply arrangement. Rosatom described a RITM-400 plant as a possible priority option in a 2023 agreement of intent with Nornickel; the reactor is described as an 80-90 MW pressurised water reactor developed by OKBM Afrikantov. The reviewed documents do not establish a site within Norilsk, host acceptance or procurement.

Key facts

Design
RITM-400 (SMR)
Technology
Pressurized water reactor (PWR) · light water. Nornickel's 2023 release calls RITM-400 a pressurised water reactor and no opened source states its layout, so no integral claim is recorded.
Operator(s)
Not recorded
Vendor for linked design
—
Location
Norilsk (small nuclear plant location to be selected) · Russia · precision: town or locality only
The plan names the city of Norilsk only; no parcel has been published and the NuclearChain point is not shown to be a site, so there is no map pin.
Coordinates
Town named, no map pin
Electrical capacity
320 MWe (gross/net unspecified) · scope: plant
Thermal capacity
Not recorded
Modules planned
4
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
6 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Norilsk land small nuclear plant (RITM-400) is recorded at Norilsk (small nuclear plant location to be selected), Krasnoyarsk Krai, Russia. Operator: No operator is recorded. Recorded vendor: No vendor is recorded. Stage: Announced. Location precision: town or locality only; town named, no map pin.

Recorded electrical output is 320 MWe (gross/net unspecified), scope plant. Modules planned: 4. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Funding and government decisions

Russia's General Scheme for power facilities to 2042, approved in December 2024, lists the Norilsk plant's capacity but says its implementation will be confirmed only after agreements with consumers fixing the volume and price of electricity, or another supply arrangement. Neither it nor Nornickel's 13 November 2023 release states a funder, investment amount or financing model, which the 2023 agreement left to be agreed. Government of Russia order No. 4153-r: General Scheme for the placement of electric power facilities to 2042; Nornickel: Nornickel and Rosatom to look into nuclear power potential in Norilsk

Not found in the sources we checked (4): Customer or offtaker; Contractor; Fuel; Comparable schedule revision
Customer or offtaker

Russia's December 2024 General Scheme says the Norilsk small nuclear plant will be confirmed only after agreements with consumers fixing volumes and prices, or another supply arrangement. Nornickel's 13 November 2023 release describes an agreement of intent with Rosatom to consider small plants to supply the Norilsk Industrial District, with Nornickel saying it will need more power beyond 2030. Neither source names a buyer or offtake agreement. Government of Russia order No. 4153-r: General Scheme for the placement of electric power facilities to 2042; Nornickel: Nornickel and Rosatom to look into nuclear power potential in Norilsk

Contractor

Nornickel's 13 November 2023 release says Nornickel and Rosatom signed an agreement of intent to evaluate options, identify a priority site, the plant's configuration and infrastructure, and an implementation model for a land-based small nuclear plant in the Norilsk Industrial District. That is a joint evaluation between the proposer and the prospective industrial user, not an engineering or construction appointment, and Russia's December 2024 General Scheme names no contractor. Nornickel: Nornickel and Rosatom to look into nuclear power potential in Norilsk

Fuel
No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.

Nornickel's 13 November 2023 release names the RITM-400 reactor as a possible priority option, and Russia's December 2024 General Scheme lists RITM-400 units, but neither names a fuel supplier, fabrication or delivery for the Norilsk plant. Nornickel: Nornickel and Rosatom to look into nuclear power potential in Norilsk

Comparable schedule revision

Comparable schedule revision not established. Russia's General Scheme to 2042, approved in December 2024, gives one planned build-up for Norilsk, from one 80 MW RITM-400 unit in 2032 to four units from 2037, and Nornickel's 13 November 2023 release only says more power is needed beyond 2030. No earlier and later date for the same Norilsk milestone is stated. Nornickel: Nornickel and Rosatom to look into nuclear power potential in Norilsk

Not recorded in SMRMap's reviewed evidence (4): Operator or intended licensed owner; Reactor supplier; Site host or owner; Programs and agreements naming the project
Operator or intended licensed owner
Reactor supplier
Site host or owner
Programs and agreements naming the project

Timeline

This timeline has no entries yet. Other dated information may appear in the description and checking notes.

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes, 1 not yet reviewed)
  • Evidence review. Russia's approved December 2024 general scheme lists planned cumulative Norilsk capacity of one RITM-400 unit/80 MW in 2032, two/160 MW in 2034, three/240 MW in 2036 and four/320 MW from 2037. Implementation depends on consumer agreements fixing volumes and prices or another supply arrangement. Nornickel's 13 November 2023 announcement confirms a signed agreement of intent with Rosatom to evaluate options, a priority site and an implementation model. RITM-400 is a priority possibility in that announcement; its 80–90 MW design description is not a selected project-module rating. The scheme is not a plant construction permission and no operator, final parcel or EPC contract is named. Last checked 19 Oct 2026. Government of Russia order No. 4153-r: General Scheme for the placement of electric power facilities to 2042; Nornickel: Nornickel and Rosatom to look into nuclear power potential in Norilsk
    What would change this

    A Norilsk project agreement establishing the site, implementing company and consumer commitments, followed by the project-specific permission or procurement decision. Next scheduled check: 19 Jan 2027.

  • Developer or proposer. Rosatom and Nornickel are the signed intent counterparties; the project implementation model is still to be agreed. The signed intent supports a proposer role, not a reactor operator or final vendor selection. Last checked 19 Oct 2026. Nornickel: Nornickel and Rosatom to look into nuclear power potential in Norilsk
    What would change this

    A Norilsk project agreement establishing the site, implementing company and consumer commitments, followed by the project-specific permission or procurement decision. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed: Not disclosed in the reviewed evidence. The documents identify the Norilsk area, while selection of the priority plant site remains a future task. Last checked 19 Oct 2026. Nornickel: Nornickel and Rosatom to look into nuclear power potential in Norilsk
    What would change this

    A Norilsk project agreement establishing the site, implementing company and consumer commitments, followed by the project-specific permission or procurement decision. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. The December 2024 General Scheme says the Norilsk small nuclear plant will be confirmed only after agreements with consumers fixing electricity volumes and prices, or another supply arrangement, are concluded; it then lists a first 80 MW RITM-400 block from 2032. The consumer agreement is the prerequisite; the 2032 date is a planning target, and these sources show no such agreement yet. Last checked 23 Oct 2026. Government of Russia order No. 4153-r: General Scheme for the placement of electric power facilities to 2042
    What would change this

    A power-purchase agreement between Rosatom and Norilsk consumers such as Nornickel, or an updated General Scheme. Next scheduled check: 23 Apr 2027.

  • Permissions and public process: Not disclosed in the reviewed evidence. Russia's General Scheme for power facilities to 2042 (government order of 30 December 2024) lists a Norilsk small nuclear plant with RITM-400 units, and the November 2023 Nornickel-Rosatom agreement of intent covers studying options. A national planning listing is not a permission, and neither document mentions a Rostekhnadzor license application, environmental review or public hearing for a Norilsk plant. Last checked 23 Oct 2026. Government of Russia order No. 4153-r: General Scheme for the placement of electric power facilities to 2042; Nornickel: Nornickel and Rosatom to look into nuclear power potential in Norilsk
    What would change this

    A Rostekhnadzor siting license application or public hearings on an environmental assessment for a Norilsk small nuclear plant. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). Nornickel's 13 November 2023 release says that under the agreement of intent the two companies will evaluate options and identify a priority site for an onshore plant, its configuration and the infrastructure needed to build and run it, for the Norilsk Industrial District, which is isolated from Russia's unified grid. The General Scheme places the plant only at the city of Norilsk. No site, land or grid arrangement had been identified in these sources. Last checked 23 Oct 2026. Nornickel: Nornickel and Rosatom to look into nuclear power potential in Norilsk
    What would change this

    Announcement of a priority site for the Norilsk small nuclear plant. Next scheduled check: 23 Apr 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(0 of 3 sources with a publication or document date)
Latest dated listed source publication: no date recorded.Latest dated recorded event: no date recorded.3 of 3 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(3)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Norilsk land small nuclear plant (RITM-400) — https://smrmap.com/projects/norilsk-asmm-ritm400/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Norilsk land small nuclear plant (RITM-400)”. Record reviewed 6 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/norilsk-asmm-ritm400/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.