Projects / Canada · Announced

Belledune Prodigy transportable nuclear proposal

Pabineau and Eel River Bar First Nations and Prodigy Clean Energy propose an Indigenous-owned transportable nuclear power plant of up to 50 MWe at Belledune, New Brunswick.

Current status

Stage
Announced
How current
General record check . Bounded evidence review . 2 of 2 listed sources have a publication or document date recorded here; the newest is 5 Oct 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
Announced 5 Oct 2026 · Announcement: BWXT announces BANR selection for Belledune transportable plant. BWXT announced the selection of BANR, with two reactors planned for the up to 50 MWe transportable plant. Source: BWXT: BWXT's BANR microreactor chosen for Canadian transportable nuclear power plant project (5 October 2026) (published 5 Oct 2026). Updates entry
More on this development

New Brunswick signed a letter of intent to buy power. This announcement is not a license or a construction start.

Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • No map pin is shown for this record.
Same design
3 tracked: 3 announced. 96 tracked at announced across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
High-temperature gas-cooled reactor. How it works, with a 3D view.
Schematic of HTR-PM, this type's example. On the left, a tall reactor vessel holds a bed of fuel spheres inside a graphite reflector, with fuel tubes above and below.
Schematic of HTR-PM, this type's example.

Description

BWXT’s 5 October 2026 announcement selects BANR and explicitly plans two reactors to be fabricated in Ontario; this is not a count of reactors built. Prodigy’s 1 September announcement says a qualified operating organization and future licensee will be procured, so Prodigy is recorded as proposer, not operator. The plant’s up to 50 MWe envelope is not an exact rating or an inferred 44 MWe total. In-service in the early 2030s is a target. No license application, construction start or precise parcel is established. The Government of New Brunswick provided a letter of intent to offtake electricity; a definitive power-sales contract is not established here.

Key facts

Design
BWXT BANR (Microreactor)
Technology
High-temperature gas-cooled reactor (HTGR) · helium
Operator(s)
Not recorded
Vendor for linked design
BWX Technologies
Design origin
United States: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
Location
Belledune · Canada · precision: town or locality only
Belledune is the named locality; a parcel had not been selected in the reviewed announcement.
Coordinates
Town named, no map pin
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
2
Inclusion basis
Labeled microreactor
Confidence
medium
Record reviewed
13 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Belledune Prodigy transportable nuclear proposal is recorded at Belledune, New Brunswick, Canada. Operator: No operator is recorded. Recorded vendor: BWX Technologies. Stage: Announced. Location precision: town or locality only; town named, no map pin.

Electrical output is not recorded on this project. Modules planned: 2. Thermal output is not recorded on this project. The linked design record states 75 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Reactor supplier
Customer or offtaker
Source-backed project statement

Prodigy's 1 September 2026 announcement and BWXT's 5 October 2026 release say the Government of New Brunswick signed a letter of intent to offtake the electricity from the proposed Belledune transportable plant and notified Natural Resources Canada of its support. A letter of intent is not a definitive power-sales contract. Prodigy Belledune Indigenous-led proposal; BWXT: BWXT's BANR microreactor chosen for Canadian transportable nuclear power plant project (5 October 2026)

Contractor

Source-backed project statement Prodigy announced on 1 September 2026 that BWXT Canada Ltd. and Kinectrics Inc. would advance licensing and supply-chain development. BWXT subsequently described planned workforce support. The cited releases do not establish an EPC award, a license or completed fabrication. Prodigy Belledune Indigenous-led proposal; BWXT: BWXT's BANR microreactor chosen for Canadian transportable nuclear power plant project (5 October 2026)

Fuel
  • Fuel form stated for BWXT BANRTRISO-coated fuel particles
  • Enrichment stated for BWXT BANR19.75%
No project-specific fuel supply arrangement is recorded as a structured fact.

The 5 October 2026 release says BANR is intended to use high-assay low-enriched uranium in TRISO fuel. That is the design description in the selection announcement, not a supplier, a quantity, or a delivery committed to Belledune. The plant is described as arriving ready for fueling, which is also not a fuel contract. BWXT: BWXT's BANR microreactor chosen for Canadian transportable nuclear power plant project (5 October 2026)

Programs and agreements naming the project
Not found in the sources we checked (2): Funding and government decisions; Comparable schedule revision
Funding and government decisions

The 1 September 2026 release sets an objective of a final investment decision within 18 months. It states no amount, application, or allocation. Notice to the federal Major Projects Office is institutional support, not a disclosed sum. No disbursement is stated. Prodigy Belledune Indigenous-led proposal

Comparable schedule revision

Comparable schedule revision not established. The 1 September and 5 October 2026 releases both target in-service operation by the early 2030s. Repeating one target is not a revision. The September release also says reactor technology should be demonstrably ready by 2032 for commercial generation. That is a down-selection criterion, not a second date for the same in-service milestone. A final investment decision within 18 months is a different objective. Prodigy Belledune Indigenous-led proposal

Not recorded in SMRMap's reviewed evidence (2): Operator or intended licensed owner; Site host or owner
Operator or intended licensed owner
Site host or owner

Timeline

Recorded developments

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)
  • Evidence review. On 1 September 2026 Pabineau First Nation, Eel River Bar First Nation and Prodigy announced a proposal in Belledune for an up to 50 MWe transportable plant, and said a qualified operating organization that will become the licensee will be procured. That release also says site selection and characterization are still ahead. On 5 October 2026 BWXT said those parties selected BANR for a plant to be located in Belledune and that two BANR units will be fabricated in Ontario. Two planned units are not a count of reactors built, and the up to 50 MWe envelope is not stored as an exact rating or as 44 MWe. New Brunswick signed a letter of intent to offtake the electricity. Prodigy stays the proposer, not the operator. Last checked 19 Oct 2026. Prodigy Belledune Indigenous-led proposal; BWXT: BWXT's BANR microreactor chosen for Canadian transportable nuclear power plant project (5 October 2026)
    What would change this

    A licence-to-prepare-site application, or a document that selects the Belledune parcel and the operating licensee. Next scheduled check: 19 Jan 2027.

  • Site location recorded as disclosed. Both releases name Belledune, New Brunswick, as the place. The 1 September release still lists site selection and characterization as future work, so this is not an exact plot. Last checked 19 Oct 2026. BWXT: BWXT's BANR microreactor chosen for Canadian transportable nuclear power plant project (5 October 2026); Prodigy Belledune Indigenous-led proposal
    What would change this

    A site-selection result that identifies the parcel inside Belledune. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. New Brunswick has told Natural Resources Canada it intends to advance the project to the federal Major Projects Office, according to the September 2026 announcement, and the partners target in-service operation by the early 2030s. A referral intention is not a federal designation or a license, and no regulatory filing date is given. Last checked 23 Oct 2026. Prodigy Belledune Indigenous-led proposal
    What would change this

    A Major Projects Office listing or a CNSC application for the Belledune plant. Next scheduled check: 21 Jan 2027.

  • Permissions and public process: Not disclosed in the reviewed evidence. The September 2026 announcement places the First Nation-owned plant within the traditional territory of the Pabineau and Eel River Bar First Nations and names BWXT Canada and Kinectrics to advance licensing. It records no CNSC license application, environmental or impact assessment, or public consultation. First Nations ownership is a project role, not a regulatory or consent decision. Last checked 23 Oct 2026. Prodigy Belledune Indigenous-led proposal
    What would change this

    A CNSC license application or an impact-assessment notice for the Belledune plant. Next scheduled check: 21 Jan 2027.

  • Site dependencies (land, grid, water). The September and October 2026 releases place the plant at Belledune, New Brunswick, within the traditional territory of the Pabineau and Eel River Bar First Nations. Neither names a specific parcel or port berth, a grid-connection arrangement or a water source. Last checked 23 Oct 2026. Prodigy Belledune Indigenous-led proposal; BWXT: BWXT's BANR microreactor chosen for Canadian transportable nuclear power plant project (5 October 2026)
    What would change this

    A site description, environmental-assessment registration or license application for the Belledune plant. Next scheduled check: 21 Jan 2027.

  • Spent fuel, waste and closure: Not disclosed in the reviewed evidence. The September 2026 Prodigy release describes the plant type as designed to be removed at the end of its life for centralized decommissioning. That is a design intention, not a project arrangement: neither release names who would hold spent fuel, where it would be managed or how decommissioning would be funded for Belledune. Last checked 23 Oct 2026. Prodigy Belledune Indigenous-led proposal; BWXT: BWXT's BANR microreactor chosen for Canadian transportable nuclear power plant project (5 October 2026)
    What would change this

    A license application or project agreement naming spent-fuel, waste and decommissioning responsibilities. Next scheduled check: 21 Jan 2027.

Evidence dates

(2 of 2 sources with a publication or document date)
Latest dated listed source publication: BWXT: BWXT's BANR microreactor chosen for Canadian transportable nuclear power plant project (5 October 2026): 5 Oct 2026.Latest dated recorded event: Belledune transportable plant: BWXT BANR microreactor selected: 5 Oct 2026.All 2 listed sources have a publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(2)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Belledune Prodigy transportable nuclear proposal — https://smrmap.com/projects/prodigy-belledune/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Belledune Prodigy transportable nuclear proposal”. Record reviewed 13 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/prodigy-belledune/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.