Projects / United States · Construction
Project Pele (INL microreactor demonstration)
DoD Strategic Capabilities Office and BWXT transportable high-temperature gas microreactor demonstration at Idaho National Laboratory.
Current status
- How current
- General record check . Bounded evidence review . 2 of 8 listed sources have a publication or document date recorded here; the newest is 7 Dec 2022. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: Project Pele record of decision (prototype mobile microreactor environmental impact statement) (5 Apr 2022). All permissions and applications
- Latest development
- Company timeline Sep 2026 · Recorded development: BWXT says Pele core barrel cartridge installation is complete. BWXT's program page lists core barrel cartridge installation for the Pele reactor as complete in September 2026. Source: BWXT Project Pele page. Updates entry
More on this development
The reactor has not yet shipped to INL or been loaded with fuel.
- Next dated milestone
- Planned step: 2027 (target). Formal Pele system testing (BWXT plan, as early as). This is not an achieved milestone. Source: American Nuclear Society: Pele TRISO core (40,000 fuel compacts) delivered to INL TREAT facility (day per INL) (published 4 Dec 2025).
- Selected limitations
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage (reviewed: not disclosed in the reviewed evidence; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- High-temperature gas-cooled reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The office's record of decision, signed 5 April 2022 (87 FR 22521), chose to fabricate the prototype off-site and demonstrate it at INL; that is an environmental decision, not a safety authorization. DoD broke ground at INL in September 2024. DOE stated on 23 May 2026 that fuel was delivered to INL in November 2025. The Army's article of 3 December 2025 says INL received the first TRISO fuel delivery that week. The two official statements do not name the same month, and neither gives a calendar day. Delivery is not fuel loading or authorization to operate. Reactor manufacturing is in Lynchburg; BWXT's program page says core stacking was complete in June 2026 and that the reactor will ship to INL and be fueled there before demonstration tests, without a shipment date. That is a company statement. No DOE authorization to load fuel, start up or operate was opened. DOE's 2024 groundbreaking article said Pele could operate as early as 2026; that is a projection, and no startup is recorded. A defense.gov news search returned an access refusal (HTTP 403) and was not retried. Distinct from Aurora and canceled CFPP. BWXT's program page, read on 18 October 2026, says core barrel cartridge installation was complete in September 2026; the reactor is still to ship from Lynchburg to INL and be loaded with fuel there.
Key facts
- Design
- Project Pele microreactor (BWXT HTGR) (Microreactor)
- Technology
- High-temperature gas-cooled reactor (HTGR) · helium
- Operator(s)
- U.S. DoD Strategic Capabilities Office
- Vendor for linked design
- BWX Technologies
- Location
- INL CITRC Project Pele area · United States · precision: town or locality only
Project Pele is demonstrated at INL's Critical Infrastructure Test Range Complex; no published point for that complex was opened. The pin is the recorded OpenStreetMap point for the laboratory at its Central Facilities Area (43.5306324, −112.94046): a laboratory-wide point, not the test pad. - Coordinates
- 43.5306324, -112.94046 · town-level point (approximate)
- Electrical capacity
- 1.5 MWe (gross/net unspecified) · scope: module
- Thermal capacity
- Not recorded
- Purpose
- Research or test reactor
- Construction start
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- high
- Record reviewed
- 18 Oct 2026Evidence review 20 Oct 2026. How current names both.
Could not be confirmed on . Attempted official source: Army article on the first TRISO fuel delivery for Project Pele. This is an access or status observation only; the record review date is unchanged.
Site and capacity notes
Project Pele (INL microreactor demonstration) is recorded at INL CITRC Project Pele area, Idaho, United States. Operator: U.S. DoD Strategic Capabilities Office. Recorded vendor: BWX Technologies. Stage: Construction. Location precision: town or locality only; town-level point (approximate).
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: 'Idaho National Laboratory, East Ogden Avenue, Central Facilities Area' (amenity=research_institute), 43.5306324, −112.94046
Recorded electrical output is 1.5 MWe (gross/net unspecified), scope module. Modules planned: 1. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- Reactor supplier
- Vendor for the linked designBWX Technologies
- Customer or offtaker
Source-backed project statement The Energy Department's 23 May 2026 article says Project Pele is a mobile microreactor prototype designed to provide resilient power for military operations, led by DoW's Strategic Capabilities Office in partnership with BWXT, DOE, and INL. BWXT's program page says that once complete the reactor will deliver baseload power for the Department of War's mission-critical efforts. The record of decision signed 5 April 2022 says the prototype must be tested against DoD specifications, and it describes a demonstration of power for a grid separate from the public utility grid. Those pages name a demonstration purpose and a laboratory host, not an electricity buyer, a price, or a binding offtake. DOE: One Year After Executive Orders, U.S. Nuclear Energy Renaissance Is in Full Swing; BWXT Project Pele page; Record of Decision for the Final Construction and Demonstration of a Prototype Mobile Microreactor Environmental Impact Statement; DOE Project Pele groundbreaking article
- Contractor
- Construction contractorBWXT Advanced Technologies, LLC · sourceSelected by the DoD Strategic Capabilities Office (June 2022) to manufacture and deliver the Pele prototype microreactor to INL.
Source-backed project statement
BWXT's program page states a June 2022 award from the Strategic Capabilities Office to build and deliver the Pele prototype and names BWXT as the lead contractor, with design and manufacture at its campus in Lynchburg, Virginia. The Energy Department's 24 September 2024 article says the reactor will be manufactured by BWX Technologies. The record of decision signed 5 April 2022 says the final design was still a competitive down-select between two designs, so that environmental decision is not the manufacturing award. BWXT's award is to build and deliver a prototype that its page still places before shipment and loading, not a contract to operate it. BWXT Project Pele page; DOE Project Pele groundbreaking article; Record of Decision for the Final Construction and Demonstration of a Prototype Mobile Microreactor Environmental Impact Statement
- Fuel
- Fuel supplier named for this projectBWX Technologies · sourceManufacturing the Pele core under a $37 million INL award (2022) that also covers fuel for other reactors and NASA.
- Fuel form stated for Project Pele microreactor (BWXT HTGR)TRISO
- Enrichment stated for Project Pele microreactor (BWXT HTGR)HALEU
Source-backed project statement
BWXT's program page says TRISO fuel production for the initial core was completed in November 2025, and the Energy Department's 23 May 2026 article says the fuel was delivered to Idaho National Laboratory in November 2025; the Army's article of 3 December 2025 reports the first delivery that week. BWXT says loading is still ahead of the demonstration tests. The 2022 record of decision proposed fuel made from downblended highly enriched uranium and fabricated in Lynchburg. DOE: One Year After Executive Orders, U.S. Nuclear Energy Renaissance Is in Full Swing; Army article on the first TRISO fuel delivery for Project Pele; BWXT Project Pele page; Record of Decision for the Final Construction and Demonstration of a Prototype Mobile Microreactor Environmental Impact Statement
- Site host or owner
- Site hostIdaho National Laboratory · source
Not found in the sources we checked (2): Funding and government decisions; Comparable schedule revision
- Funding and government decisions
The record of decision signed 5 April 2022 says implementation of the proposed demonstration is subject to the availability of appropriations, and it says cost and schedule were considered without stating an amount. BWXT's program page states a June 2022 contract award to build and deliver the prototype and states no price or payment. The Energy Department articles of 24 September 2024 and 23 May 2026 and the Army article of 3 December 2025 also do not state a Project Pele disbursement. Sums elsewhere on the 23 May 2026 page are outside the Project Pele paragraph and are not treated as Pele funding. Record of Decision for the Final Construction and Demonstration of a Prototype Mobile Microreactor Environmental Impact Statement; BWXT Project Pele page; DOE Project Pele groundbreaking article; DOE: One Year After Executive Orders, U.S. Nuclear Energy Renaissance Is in Full Swing; Army article on the first TRISO fuel delivery for Project Pele
- Comparable schedule revision
Comparable schedule revision not established. The Energy Department's 24 September 2024 article says the project could operate as early as 2026 and that placement during the 2026 timeframe was planned for safety reviews and initial testing. BWXT's program page, which states no article date, lists September 2026 core barrel cartridge installation as complete and gives no date for shipment, loading, or demonstration tests. The record of decision signed 5 April 2022 says schedule was considered and states no operation date. The pages reviewed do not contain two dated forecasts of the same milestone. DOE Project Pele groundbreaking article; BWXT Project Pele page; Record of Decision for the Final Construction and Demonstration of a Prototype Mobile Microreactor Environmental Impact Statement
Not recorded in SMRMap's reviewed evidence (2): Project proposer or applicant; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Programs and agreements naming the project
Timeline
Recorded developments
- Company timeline · Recorded development
BWXT says Pele core barrel cartridge installation is complete - · Recorded development
Pele core stacking complete (BWXT) - · Recorded development
Army reports the first TRISO fuel delivery to INL that week - · Recorded development
Pele TRISO core (40,000 fuel compacts) delivered to INL TREAT facility (day per INL) - · Recorded development
Advanced nuclear fuel delivered to INL for Project Pele
Earlier developments (4)
- · Recorded development
BWXT core assembly production began - Reported · Groundbreaking
Department of Defense breaks ground for Project Pele at Idaho National Laboratory - Company timeline · Contract
BWXT awarded the contract to build and deliver the Pele prototype - · Environmental decision recorded
Environmental decision recorded: Project Pele record of decision (prototype mobile microreactor environmental impact statement)
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Formal Pele system testing (BWXT plan, as early as) - Target · Electricity generation
Pele first electricity at INL (BWXT plan, as soon as)
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Environmental decision
- Project Pele record of decision (prototype mobile microreactor environmental impact statement)
Environmental decision · Issued / approved · U.S. Department of Defense, Strategic Capabilities Office · decided 5 Apr 2022 · 87 FR 22521
Signed 5 April 2022 and published 15 April 2022 at 87 FR 22521. The Strategic Capabilities Office decided to implement the proposed action of its final environmental impact statement: fabricate the prototype mobile microreactor and its fuel at existing off-site commercial facilities and demonstrate it at the Idaho National Laboratory Site. This is a National Environmental Policy Act decision. This record addresses the environmental decision; it does not establish the status of any separate DOE safety authorization. No such authorization document was opened.
Sources: Federal Register 87 FR 22521 (15 Apr 2022): Record of Decision, Construction and Demonstration of a Prototype Mobile Microreactor
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(8 notes)
- Evidence review. DOE's article dated 24 September 2024 says DoD broke ground at Idaho National Laboratory on Project Pele, without giving the day, and described operation as early as 2026 as a possibility. The Army's article dated 3 December 2025 says INL received the first TRISO fuel delivery that week, while DOE later dated the delivery to November 2025; delivery is not fuel loading. The attached captures do not document a DOE safety authorization to load fuel, start up or operate, or an achieved criticality or generation date. The environmental decision and groundbreaking do not establish reactor operating permission. DOE explicitly describes a planned 1–5 MWe electrical-output range, without gross/net basis. No endpoint is selected as a scalar rating. DOE identifies a transportable high-temperature gas demonstrator at the Critical Infrastructure Test Range Complex, manufactured by BWXT; its separately described civil BANR is not substituted for Pele. DOD leads and DOE Idaho oversees safety. The record of decision, issued by the Strategic Capabilities Office, lists operating the reactor among the demonstration activities without saying who runs it. The stored operator, the Strategic Capabilities Office, is the office DOE says leads the demonstration; no opened source calls it the reactor's operator. Last checked 20 Oct 2026. DOE Project Pele groundbreaking article; Army article on the first TRISO fuel delivery for Project Pele
What would change this
A DOE authorization approving fuel loading, startup or operation, or BWXT/DOE evidence of shipment to INL and a dated reactor milestone. Next scheduled check: 20 Jan 2027.
- Permission evidence appropriate to stage: Not disclosed in the reviewed evidence. The attached readable project sources document groundbreaking and fuel delivery but do not identify a project-specific DOE safety authorization to load fuel, start up or operate. The environmental decision is not a reactor safety authorization. Last checked 20 Oct 2026. DOE Project Pele groundbreaking article
What would change this
DOE publishes the safety authorization and its fuel-loading, startup or operating scope. Next scheduled check: 20 Jan 2027.
- Construction start evidence. DOE reported that the Department of Defense broke ground at INL in September 2024. Reactor assembly continues at BWXT in Lynchburg; core barrel cartridge installation was complete in September 2026 per BWXT. Last checked 18 Oct 2026. DOE Project Pele groundbreaking article
What would change this
Reactor shipment to INL. Next scheduled check: 18 Jan 2027.
- Operation or grid target (type stated). BWXT's target is for Pele to power military equipment in 2028 as a fully tested advanced microreactor power system; the stored 2028 first-electricity target matches. It is not a grid connection or commercial operation. DOE's 2024 projection of operation as early as 2026 is out of date. Last checked 18 Oct 2026. BWXT Project Pele page
What would change this
Shipment to INL or a revised BWXT, Army or DoD schedule. Next scheduled check: 18 Jan 2027.
- Next decision and prerequisites. The Energy Department's 24 September 2024 article assigns safety oversight of the demonstration to the Idaho Operations Office and describes safety reviews as work still planned. BWXT's program page says the reactor will ship from Lynchburg to Idaho National Laboratory and be loaded before demonstration tests, and it gives no shipment date. The record of decision signed 5 April 2022 implements an environmental decision and does not authorize loading or operation. The decision left open by these pages is an authorization to load or operate, or a dated record that the reactor has shipped. Last checked 23 Oct 2026. DOE Project Pele groundbreaking article; BWXT Project Pele page; Record of Decision for the Final Construction and Demonstration of a Prototype Mobile Microreactor Environmental Impact Statement
What would change this
An Energy Department authorization to load or operate Project Pele, or a dated record that the reactor shipped from Lynchburg. Next scheduled check: 21 Jan 2027.
- Permissions and public process. The record of decision signed 5 April 2022 and published on 15 April 2022 selects off-site fabrication and demonstration at Idaho National Laboratory after public hearings on 20 October 2021, and it is an environmental decision. The Energy Department's 24 September 2024 article places the demonstration under the safety oversight of the Idaho Operations Office and still describes safety reviews as planned. The 23 May 2026 fuel sentence and the 3 December 2025 Army delivery article do not state an authorization to load fuel or to operate. Language in the record about permits is a reference to measures required by regulation, not an operating authorization. Last checked 23 Oct 2026. Record of Decision for the Final Construction and Demonstration of a Prototype Mobile Microreactor Environmental Impact Statement; DOE Project Pele groundbreaking article; DOE: One Year After Executive Orders, U.S. Nuclear Energy Renaissance Is in Full Swing; Army article on the first TRISO fuel delivery for Project Pele
What would change this
An Energy Department or defense authorization to load fuel or to operate Project Pele at Idaho National Laboratory. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). The record of decision signed 5 April 2022 identifies the Idaho National Laboratory Site as the preferred demonstration location, requires an independent isolable electrical system, and limits described land disturbance to two concrete pads and fencing. The Energy Department's 24 September 2024 article says the Department of Defense broke ground there, with operation planned at the Critical Infrastructure Test Range Complex and a connection to the laboratory microgrid. Those statements address the demonstration site and the electrical connection. They are not a land title, an interconnection agreement, or a water right; the record only finds no significant water impact. Last checked 23 Oct 2026. Record of Decision for the Final Construction and Demonstration of a Prototype Mobile Microreactor Environmental Impact Statement; DOE Project Pele groundbreaking article
What would change this
A land instrument, an interconnection agreement, or a water right for the Project Pele demonstration at Idaho National Laboratory. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. The record of decision signed 5 April 2022 includes temporary storage of the disassembled reactor at the Radioactive Scrap and Waste Facility or the Outdoor Radioactive Storage Area, plus potential spent-fuel examination and disposition, inside the proposed demonstration. The same decision says the office is not choosing which laboratory facility will provide that temporary storage. BWXT's program page says the design uses no refueling for up to three years, and the 24 September 2024 Energy Department article expects operation for a minimum of three years at the laboratory. None of these statements names a disposal site or a waste contract. Last checked 23 Oct 2026. Record of Decision for the Final Construction and Demonstration of a Prototype Mobile Microreactor Environmental Impact Statement; BWXT Project Pele page; DOE Project Pele groundbreaking article
What would change this
A decision that selects the Project Pele storage facility or names a spent-fuel disposition path. Next scheduled check: 21 Jan 2027.
Evidence dates
(2 of 8 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(8)
- DOE Project Pele groundbreaking article (government, accessed 1 Oct 2026)
- BWXT Project Pele page (company, accessed 18 Oct 2026)
- Federal Register 87 FR 22521 (15 Apr 2022): Record of Decision, Construction and Demonstration of a Prototype Mobile Microreactor (government, accessed 5 Oct 2026)
- DOE: One Year After Executive Orders, U.S. Nuclear Energy Renaissance Is in Full Swing (government, accessed 5 Oct 2026)
- Army article on the first TRISO fuel delivery for Project Pele (government, accessed 5 Oct 2026)
- BWXT: Project Pele programme page (company, accessed 9 Oct 2026)
- BWXT starts production of TRISO fuel for first U.S. Generation IV microreactor (company, published 7 Dec 2022, accessed 21 Oct 2026)
- Record of Decision for the Final Construction and Demonstration of a Prototype Mobile Microreactor Environmental Impact Statement (government, published 15 Apr 2022, accessed 23 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Project Pele (INL microreactor demonstration) — https://smrmap.com/projects/project-pele-inl/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Project Pele (INL microreactor demonstration)”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/project-pele-inl/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.