Projects / Canada · Siting
SaskPower Rafferty SMR (Estevan area)
On 29 Sep 2026 Saskatchewan selected Rafferty near Estevan for further SMR study, aiming for at least 600 MW.
Current status
- How current
- General record check . Bounded evidence review . None of the 2 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 18 tracked: 1 construction, 4 licensing, 10 siting, 3 announced. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Boiling water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Earlier accounts named two alternative sites.
Key facts
- Design
- BWRX-300 (SMR)
- Technology
- Boiling water reactor (BWR) · light water
- Reactor vessel of this design
- 27 m tall, 4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 25.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Not recorded
- Vendor for linked design
- GE Vernova Hitachi Nuclear Energy
- Design origin
- United States: where the design's vendor is recorded, not where parts are made · See designs from this origin on a 3D globe
- Location
- Rafferty site near Estevan · Canada · precision: town or locality only
Saskatchewan named the Rafferty area near Estevan; no site point is published. The pin is the Estevan city point from its Wikipedia article, a town-level point, not the Rafferty site. Replaces an earlier hand-placed point that recorded no coordinate source. - Coordinates
- 49.13917, -102.98611 · town-level point (approximate)
- Electrical capacity
- 600 MWe (net) · scope: plant
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded
- Inclusion basis
- SMR by design class
- Confidence
- high
- Record reviewed
- 1 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
SaskPower Rafferty SMR (Estevan area) is recorded at Rafferty site near Estevan, Saskatchewan, Canada. Operator: No operator is recorded. Recorded vendor: GE Vernova Hitachi Nuclear Energy. Stage: Siting. Location precision: town or locality only; town-level point (approximate).
Coordinate source: Wikipedia: Estevan (article coordinates), Article coordinate 49.13917, -102.98611 on 'Estevan', read 30 October 2026
Recorded electrical output is 600 MWe (net), scope plant. Module count is not recorded. Thermal output is not recorded on this project. The linked design record states 870 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project. The linked design record states 300 MWe (net); the project figure is kept separate.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Reactor supplier
- Vendor for the linked designGE Vernova Hitachi Nuclear Energy
Not found in the sources we checked (5): Customer or offtaker; Contractor; Funding and government decisions; Fuel; Comparable schedule revision
- Customer or offtaker
Saskatchewan's 29 September 2026 release says SaskPower selected the Rafferty site near Estevan for further SMR study, aiming for at least 600 MW. It names no buyer of that power. The Bell AI data center appears in a supplier association quotation as an example of other provincial projects, not as a Rafferty offtaker. Saskatchewan Rafferty SMR selection
- Contractor
Saskatchewan's 29 September 2026 release says SaskPower selected Rafferty for further study, and quotes GE Vernova Hitachi saying it supports SaskPower's step toward the BWRX-300. That is a vendor quotation, not an engineering or construction award. The release names no contractor for Rafferty. Saskatchewan Rafferty SMR selection
- Funding and government decisions
Saskatchewan's 29 September 2026 release states no amount, funder or award for the Rafferty SMR study or plant. Saskatchewan Rafferty SMR selection
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
Saskatchewan's 29 September 2026 release quotes Cameco looking forward to competing for the province's nuclear business and GE Vernova Hitachi on the BWRX-300. Neither names a fuel supplier, quantity or delivery for Rafferty. Saskatchewan Rafferty SMR selection
- Comparable schedule revision
Comparable schedule revision not established. Saskatchewan's 29 September 2026 release gives no construction or operation date for Rafferty. Its 2042 date is for the first of two planned large reactors in northwest Saskatchewan and its 2050 date is a provincial capacity goal, both different scopes. Saskatchewan Rafferty SMR selection
Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Reviewed 20 Oct 2026: not disclosed in the reviewed evidence.
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Assessments of the design (not of this site)
(2)
- BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs - CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. Saskatchewan selected the Rafferty site near Estevan for further study, with a goal of at least 600 MW, and that GE Vernova Hitachi's quotation is about bringing the BWRX-300 to the province. No module count is stated. Stage stays siting. The same release's 2,600 MW provincial goal and northwest large-reactor plan are different from this Rafferty study. The participating organizations retain only their source-supported roles; a reactor operator is not assigned from the study, proposer, parent, existing-fleet or proposed-owner relationship. Last checked 20 Oct 2026. Saskatchewan Rafferty SMR selection
What would change this
A SaskPower notice that selects a Rafferty unit count or files a license application. Next scheduled check: 20 Jan 2027.
- Operator or intended licensed owner: Not disclosed in the reviewed evidence. The reviewed sources establish other participant roles, but do not appoint the recorded party as this reactor’s operator. The operator remains unassigned; this does not assert that no operator exists. Last checked 20 Oct 2026. Saskatchewan Rafferty SMR selection
What would change this
A project-specific filing, operating agreement or developer statement explicitly names the proposed reactor operator. Next scheduled check: 20 Jan 2027.
- Next decision and prerequisites. The September 2026 release says SaskPower will study the Rafferty site further and continue planning toward at least 600 MW of SMR capacity around Estevan. It names no decision date, technology selection or license filing as the next step. Last checked 23 Oct 2026. Saskatchewan Rafferty SMR selection
What would change this
A SaskPower decision on technology or site, or a CNSC license application. Next scheduled check: 21 Jan 2027.
- Permissions and public process: Not disclosed in the reviewed evidence. The 29 September 2026 provincial release selects the Rafferty site for further study and says engagement with Indigenous rights holders, municipalities and local leadership will continue as planning progresses. It names no license application, environmental assessment or consultation specific to Rafferty. Last checked 23 Oct 2026. Saskatchewan Rafferty SMR selection
What would change this
A CNSC license application, an impact-assessment registration or a consultation notice for the Rafferty site. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). SaskPower selected the Rafferty site near Estevan for further study in September 2026, with a goal of at least 600 MW of SMR capacity in the Estevan area. This is a study-stage selection. The release describes no land arrangement, grid connection or cooling-water source for the site. Last checked 23 Oct 2026. Saskatchewan Rafferty SMR selection
What would change this
A SaskPower site-evaluation report or license application describing land, transmission and water for Rafferty. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. SaskPower's public engagement page, which names the Rafferty Reservoir site, answers in 2026 that used fuel from its BWRX-300 would be stored on site in licensed facilities and later transferred to the deep geological repository being developed by the Nuclear Waste Management Organization, estimating fewer than 3,000 fuel assemblies over 60 years in about 30 dry casks. SaskPower says it must still show the regulator how all radioactive waste would be managed before operation. This is a stated plan, not a licensed storage facility or a disposal agreement. Last checked 23 Oct 2026. Planning for Nuclear Power
What would change this
A SaskPower license application, environmental assessment filing or agreement with the Nuclear Waste Management Organization for this facility would change this answer. Next scheduled check: 23 Apr 2027.
Evidence dates
(0 of 2 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(2)
- Saskatchewan Rafferty SMR selection (government, accessed 1 Oct 2026)
- Planning for Nuclear Power (company, accessed 23 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: SaskPower Rafferty SMR (Estevan area) — https://smrmap.com/projects/saskpower-rafferty-smr/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “SaskPower Rafferty SMR (Estevan area)”. Record reviewed 1 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/saskpower-rafferty-smr/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.