Projects / Russia · Licensing
Yakutia land-based RITM-200N (Ust-Kuyga)
This named land-based RITM-200N proposal covers two units at Ust-Kuyga in Yakutia, Russia, and is in licensing, with Rosenergoatom as operating organization.
Current status
- How current
- General record check . Bounded evidence review . 9 of 14 listed sources have a publication or document date recorded here; the newest is 3 Mar 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Announced 27 Feb 2026 · Announcement: Yakutia: Units 1 and 2 siting-material hearings reported. Atomnaya energiya reports that public hearings on siting-license supporting materials for Units 1 and 2 took place on 26 February 2026. Source: Atomnaya energiya 2.0: hearings on Yakutia SMR units 1 and 2 (published 27 Feb 2026). Updates entry
More on this development
The event date here is the report publication. A hearing is not a siting or construction license. The linked operator original was inaccessible on this review.
- Next dated milestone
- Planned step: 2031 (target). Yakutia: reported operation target. This is not an achieved milestone. Source: Atomnaya energiya 2.0: hearings on Yakutia SMR units 1 and 2 (published 27 Feb 2026); Atom Media: Russian Federation and Uzbekistan sign contract for small nuclear power plant construction (published 27 May 2024).
- Selected limitations
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage (reviewed: source unavailable; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
- Same design
- 3 tracked: 1 construction, 1 licensing, 1 announced. 19 tracked at licensing across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Integral pressurized water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Its 55 MWe module rating has no established gross/net basis. Rosatom's 2 February 2024 release names Rosenergoatom as operating organization and technical customer, and Rusatom Overseas as developer. Camp and road work is preparatory work. On 23 May 2024, Atom Media reported a positive environmental-expert conclusion on Unit 1 construction-license supporting materials; that is not the nuclear construction license. February 2026 public hearings covered siting-license materials for Units 1 and 2. The later reported operation target remains 2031, not the older 2028 schedule. Rostekhnadzor's Lena department confirmed on 17 January 2024 that a placement license for Unit 1 was issued to Rosenergoatom in 2023. The notice gives no license number, precise issue day or expiry. It establishes neither construction nor operating permission; its current applicability and relationship to the later hearings remain unresolved. Rosatom's corporate newspaper separately dates a siting license to 21 April 2023. Rosatom's Engineering Division is named as general designer and general construction contractor, and Rusatom Overseas as developer. The separate 2021 license reported for Rusatom Overseas is not treated as a unit construction license.
Key facts
- Design
- RITM-200N (SMR)
- Technology
- Integral pressurized water reactor (iPWR) · light water
- Reactor vessel of this design
- 7.5 m tall, 3.4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 71.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Rosenergoatom
- Vendor for linked design
- Rosatom
- Location
- Ust-Kuyga (Yakutia land-based RITM-200N) · Russia · precision: site area (named plant, laboratory, base, port, campus or parcel)
Coordinates from NuclearChain sites.csv (CC BY 4.0; site name Ust-Kuyga nuclear power plant). - Coordinates
- 69.99634, 135.5713 · site-area point (approximate)
- Electrical capacity
- 55 MWe (gross/net unspecified) · scope: module
- Thermal capacity
- Not recorded
- Inclusion basis
- SMR by design class
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 20 Oct 2026. How current names both.
Site and capacity notes
Yakutia land-based RITM-200N (Ust-Kuyga) is recorded at Ust-Kuyga (Yakutia land-based RITM-200N), Sakha (Yakutia), Russia. Operator: Rosenergoatom. Recorded vendor: Rosatom. Stage: Licensing. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain data downloads (CC BY 4.0), NuclearChain sites.csv row 'ust-kuyga-nuclear-power-plant' (69.99634, 135.5713)
Recorded electrical output is 55 MWe (gross/net unspecified), scope module. Modules planned: 2. Thermal output is not recorded on this project. The linked design record states 190 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerRusatom Overseas · source
- Operator or intended licensed owner
- OperatorRosenergoatom
- Reactor supplier
- Vendor for the linked designRosatom
- Customer or offtaker
- Prospective customer / offtaker (binding offtake not established)Seligdar · sourceEnergy supply and consumption agreement with Rusatom Overseas reported 21 January 2022: 40 years from mid-2028, at least 35 MW; a binding supply contract is not recorded.
Source-backed project statement
World Nuclear News reported on 21 January 2022 that Rusatom Overseas and Seligdar signed an agreement to supply and consume energy from a RITM-200N plant for the Kyuchus deposit, for 40 years from mid-2028, with Seligdar using at least 35 MW. The report gives no price and is not the agreement text, so it is not treated as a confirmed binding offtake. Rosatom's 2 February 2024 release names Rosenergoatom as technical customer and operating organization, which is a project role, not this electricity buyer. That release says the station is meant to supply the Kyuchus development and does not restate the Seligdar quantity. WNN: Deal signed for nuclear to power Russian gold mine; Atom Media: Rosenergoatom receives operating-organisation status for the Yakutia plant (2 February 2024)
- Contractor
- Planned construction contractorRosatom Engineering Division · source
Source-backed project statement
The 27 February 2026 hearings report names Rosatom's Engineering Division as general designer and general construction contractor in its sentence on the unit 1 and unit 2 siting materials. Rosatom's 2 February 2024 release names Rusatom Overseas as the developer, Rosenergoatom as the operating organization, and OKBM Afrikantov and the State Specialized Design Institute as co-executors. These are stated roles, not a priced award and not a statement that operation has begun. The 2024 developer is not called the general construction contractor in that release. Atomnaya energiya 2.0: hearings on Yakutia SMR units 1 and 2; Atom Media: Rosenergoatom receives operating-organisation status for the Yakutia plant (2 February 2024)
- Funding and government decisions
- Government or regulator decision naming the project; not a reactor permit; in effectRussia: General Scheme for the placement of electric power facilities to 2042 (Government Order No. 4153-r, 2024) · sourceThe General Scheme lists the Yakutsk small nuclear plant at Ust-Kuyga (Ust-Yansky ulus) with RITM-200N units among planned nuclear plants.
Snob reported on 6 August 2021 that Rosatom and the Yakutia government agreed in December 2020 on principles for an electricity tariff, and that report states no tariff and no payment. The 21 January 2022 supply report states a 40-year term and a minimum quantity and no price. The 21 April 2023 siting report, Rosatom's 2 February 2024 release, and the 27 February 2026 hearings report also state no project sum. Snob: Rostekhnadzor allows a Rosatom company to build small reactors for the Yakutia NPP (6 August 2021); WNN: Deal signed for nuclear to power Russian gold mine; Strana Rosatom: Yakutia siting licence reported (21 April 2023); Atom Media: Rosenergoatom receives operating-organisation status for the Yakutia plant (2 February 2024); Atomnaya energiya 2.0: hearings on Yakutia SMR units 1 and 2
- Programs and agreements naming the project
Not found in the sources we checked (2): Fuel; Comparable schedule revision
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
Rosatom's 23 May 2024 release and the 27 February 2026 hearings report say fuel for the small plant is needed once every five years. That interval is not a named supplier, a delivery, or a fuel contract. The 2 February 2024 release and the 21 April 2023 siting report do not add a fuel commitment. Icebreaker reactors cited as operating experience are not a fuel supply for this plant. Atom Media: Yakutia SMR environmental-expert conclusion reported (23 May 2024); Atomnaya energiya 2.0: hearings on Yakutia SMR units 1 and 2; Atom Media: Rosenergoatom receives operating-organisation status for the Yakutia plant (2 February 2024); Strana Rosatom: Yakutia siting licence reported (21 April 2023)
- Comparable schedule revision
Comparable schedule revision not established. Strana Rosatom on 21 April 2023 quotes a plan to commission the first land-based RITM-200N station in 2028, and Rosatom's 2 February 2024 release again says commissioning of the first land-based small station is planned for 2028. The 27 February 2026 hearings report says commissioning of the object is planned for 2031, in an article about siting materials for units 1 and 2. The 2031 sentence does not say whether that date is unit 1, the first unit, or both units, so no revision of one milestone is shown. Snob's 6 August 2021 report says project completion was planned for 2028, which is a different word from commissioning and is not paired as the same milestone. Strana Rosatom: Yakutia siting licence reported (21 April 2023); Atom Media: Rosenergoatom receives operating-organisation status for the Yakutia plant (2 February 2024); Atomnaya energiya 2.0: hearings on Yakutia SMR units 1 and 2; Snob: Rostekhnadzor allows a Rosatom company to build small reactors for the Yakutia NPP (6 August 2021); WNN: Deal signed for nuclear to power Russian gold mine
Not recorded in SMRMap's reviewed evidence (1): Site host or owner
- Site host or owner
Timeline
Recorded developments
- Announced · Announcement
Yakutia: Units 1 and 2 siting-material hearings reported - Announced · Announcement
Yakutia: environmental-expert conclusion on Unit 1 license materials reported - · Regulatory step
Rostekhnadzor issues Rosenergoatom a siting license for the Yakutia land-based SMR (Ust-Yansky ulus) (reported) - Reported · Regulatory step
Rusatom Overseas reports a Rostekhnadzor construction-activity license
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Yakutia: reported operation target
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(7 notes)
- Evidence review. The Rosatom reading gives a 55 MW RITM-200N without gross or net. The regulator's 17 January 2024 notice confirms a placement license issued in 2023 for Unit 1, but the license instrument, number, precise issue day, expiry and current applicability remain unverified. The relationship to the 2026 hearings on placement materials for two units remains unresolved. The environmental conclusion and preparatory road and camp work do not establish construction or operating permission. This historical correction does not refresh the broad project review date. Last checked 20 Oct 2026. Atom Media: Rosenergoatom receives operating-organisation status for the Yakutia plant (2 February 2024); Strana Rosatom: Yakutia siting licence reported (21 April 2023); WNN: Preparatory work for Russia's first land-based SMR (Yakutia); Atomnaya energiya 2.0: hearings on Yakutia SMR units 1 and 2; Atom Media: Yakutia SMR environmental-expert conclusion reported (23 May 2024); Atomic-energy.ru: 2025 results for the Yakutia plant (12 January 2026); EPRussia: Rosatom small nuclear projects; Snob: Rostekhnadzor allows a Rosatom company to build small reactors for the Yakutia NPP (6 August 2021); Rostekhnadzor Lena department: licences issued to Rosenergoatom in 2023
What would change this
The Unit 1 placement-license instrument or register entry clarifying validity and the later hearings, or a unit construction license opened from the regulator. Next scheduled check: 20 Jan 2027.
- Plant capacity (scope qualified): Not disclosed in the reviewed evidence. Rosatom's 2024 release describes the plant as based on a 55 MW RITM-200N, without saying gross or net. The February 2026 hearings cover Units 1 and 2 but give no plant total. No plant total is recorded. Last checked 18 Oct 2026. Atom Media: Rosenergoatom receives operating-organisation status for the Yakutia plant (2 February 2024); Atomnaya energiya 2.0: hearings on Yakutia SMR units 1 and 2
What would change this
A Rosatom/Rosenergoatom statement or license giving the two-unit plant output and its basis. Next scheduled check: 18 Jan 2027.
- Permission evidence appropriate to stage: Source unavailable. Rostekhnadzor's Lena department notice of 17 January 2024 confirms that a placement license for Yakutia Unit 1 was issued to Rosenergoatom in 2023. The license instrument remains unavailable: the notice gives no number, precise issue day or expiry. Its current applicability and relationship to the February 2026 hearings remain unresolved. The notice is not a construction or operating license, and the separately reported 2021 Rusatom Overseas license is not treated as a unit construction license. Last checked 18 Oct 2026. Strana Rosatom: Yakutia siting licence reported (21 April 2023); Snob: Rostekhnadzor allows a Rosatom company to build small reactors for the Yakutia NPP (6 August 2021); Rostekhnadzor Lena department: licences issued to Rosenergoatom in 2023
What would change this
The Unit 1 placement-license instrument or register entry establishing its number, precise issue date, validity and relationship to the 2026 hearings; or a later unit construction license. Next scheduled check: 18 Jan 2027.
- Next decision and prerequisites. The regulator's 17 January 2024 notice confirms a 2023 placement license for Unit 1. The February 2026 hearings concern siting-license materials for Units 1 and 2; their relationship to the earlier Unit 1 license is not established by these documents. Rosatom's 23 May 2024 release records an environmental conclusion on Unit 1 construction-license materials, not that license. The next evidence needed is the placement instrument or register entry clarifying validity and scope, a decision on the later hearing materials, or a Unit 1 construction license. Last checked 23 Oct 2026. Atomnaya energiya 2.0: hearings on Yakutia SMR units 1 and 2; Atom Media: Yakutia SMR environmental-expert conclusion reported (23 May 2024); Strana Rosatom: Yakutia siting licence reported (21 April 2023); Rostekhnadzor Lena department: licences issued to Rosenergoatom in 2023
What would change this
The Unit 1 placement-license instrument or register entry clarifying validity and the later hearing materials, a Unit 2 siting decision, or a Unit 1 construction license. Next scheduled check: 21 Jan 2027.
- Permissions and public process. Rostekhnadzor's Lena department confirmed on 17 January 2024 that a placement license for Unit 1 was issued to Rosenergoatom in 2023, without stating its number, precise issue day or expiry. Strana Rosatom separately dates a siting license to 21 April 2023. Rosatom's 23 May 2024 release records an environmental conclusion on Unit 1 construction-license materials, not the license itself. Public hearings on 26 February 2026 covered siting-license materials for Units 1 and 2; their relationship to the earlier Unit 1 license remains unresolved. The separate 2021 Rusatom Overseas license is not treated as a unit construction license. Last checked 23 Oct 2026. Strana Rosatom: Yakutia siting licence reported (21 April 2023); Atom Media: Yakutia SMR environmental-expert conclusion reported (23 May 2024); Atomnaya energiya 2.0: hearings on Yakutia SMR units 1 and 2; Snob: Rostekhnadzor allows a Rosatom company to build small reactors for the Yakutia NPP (6 August 2021); Rostekhnadzor Lena department: licences issued to Rosenergoatom in 2023
What would change this
The Unit 1 placement-license instrument or register entry clarifying validity and scope, a decision on the later hearing materials, or a unit construction license. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). Rosatom's 2 February 2024 release says preparatory work at Ust-Kuyga includes a completed 250-person camp and the start of a 12 km road from the settlement to the plant site. The 23 May 2024 release says an access road from Ust-Kuyga was still being built and that December 2023 hearings presented land-planning schemes. Those schemes and the road works are not a land title. The 2026 report's power line to other settlements is described as part of a wider mining area, not an interconnection agreement, and no page states a water right. Last checked 23 Oct 2026. Atom Media: Rosenergoatom receives operating-organisation status for the Yakutia plant (2 February 2024); Atom Media: Yakutia SMR environmental-expert conclusion reported (23 May 2024); Atomnaya energiya 2.0: hearings on Yakutia SMR units 1 and 2
What would change this
A land instrument, an interconnection agreement, or a water right for the Ust-Kuyga plant site. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. Bellona's account of the June 2021 hearings for the original Yakutia proposal reports a plan to cool spent fuel for four years in a station pool, load it into TK-18 casks and ship it for reprocessing. Presenters described no long-term spent-fuel storage or disposal at the site. This is an attributed historical hearing plan, not an opened environmental assessment or a contracted destination. Its applicability to later project revisions remains unconfirmed. Last checked 23 Oct 2026. Общественные слушания по АСММ в Якутии; В Усть-Куйге обсудили строительство атомной станции
What would change this
The published environmental assessment (OVOS) or license-justification materials for the Yakutia plant, or the Rostekhnadzor construction license conditions. Next scheduled check: 21 Jan 2027.
Evidence dates
(9 of 14 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(14)
- Rosatom: Rosenergoatom operating organization for Yakutia SNPP (company, accessed 1 Oct 2026)
- WNN: Preparatory work for Russia's first land-based SMR (Yakutia) (news report, accessed 1 Oct 2026)
- NuclearChain data downloads (CC BY 4.0) (directory or tracker, accessed 1 Oct 2026)
- Atomnaya energiya 2.0: hearings on Yakutia SMR units 1 and 2 (news report, published 27 Feb 2026, accessed 13 Oct 2026)
- EPRussia: Rosatom small nuclear projects (news report, accessed 2 Oct 2026)
- Atom Media: Rosenergoatom receives operating-organisation status for the Yakutia plant (2 February 2024) (company, published 2 Feb 2024, accessed 13 Oct 2026)
- Atomic-energy.ru: 2025 results for the Yakutia plant (12 January 2026) (news report, accessed 6 Oct 2026)
- Atom Media: Yakutia SMR environmental-expert conclusion reported (23 May 2024) (company, published 23 May 2024, accessed 13 Oct 2026)
- Strana Rosatom: Yakutia siting licence reported (21 April 2023) (company, published 21 Apr 2023, accessed 13 Oct 2026)
- Snob: Rostekhnadzor allows a Rosatom company to build small reactors for the Yakutia NPP (6 August 2021) (news report, published 6 Aug 2021, accessed 18 Oct 2026)
- WNN: Deal signed for nuclear to power Russian gold mine (news report, published 21 Jan 2022, accessed 21 Oct 2026)
- Общественные слушания по АСММ в Якутии (news report, published 15 Jul 2021, accessed 23 Oct 2026)
- В Усть-Куйге обсудили строительство атомной станции (news report, published 3 Mar 2026, accessed 23 Oct 2026)
- Rostekhnadzor Lena department: licences issued to Rosenergoatom in 2023 (regulator, published 17 Jan 2024, accessed 26 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Yakutia land-based RITM-200N (Ust-Kuyga) — https://smrmap.com/projects/yakutia-ust-kuyga-ritm-200n/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Yakutia land-based RITM-200N (Ust-Kuyga)”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/yakutia-ust-kuyga-ritm-200n/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.