Projects / United States · Licensing

Blue Energy BWRX-300 at Port of Victoria

Blue Energy plans up to five BWRX-300 units at the Port of Victoria in the United States and filed the first part of an NRC construction permit application in September 2026.

Current status

Stage
Licensing
How current
General record check . Bounded evidence review . 4 of 12 listed sources have a publication or document date recorded here; the newest is 8 Oct 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
Under review: Blue Energy Center–Port of Victoria Nuclear Unit 1 phased construction permit application, Part 1 (with limited work authorization request). An application under review is not a permit. All permissions and applications
Latest development
Announced 16 Sep 2026 · Announcement: Blue Energy says it submitted Part 1 of an NRC construction permit application. Blue Energy statements say the first part of a construction permit application for the Port of Victoria project was submitted to the NRC. Source: Blue Energy construction permit application announcement; GE Vernova on Blue Energy's Port of Victoria application; NRC pre-application activities: Blue Energy. Updates entry
More on this development

A submitted application part is not a permit.

Next dated milestone
Regulatory step: 2027 (target). Blue Energy target: submit the remaining construction permit application (Part 2) in 2027. This is not an achieved milestone. Source: GE Vernova on Blue Energy's Port of Victoria application.
Selected limitations
  • Thermal output is not recorded on this project.
  • No map pin is shown for this record.
Same design
18 tracked: 1 construction, 4 licensing, 10 siting, 3 announced. 19 tracked at licensing across all designs. Recorded stages, not proof of current activity.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Boiling water reactor. How it works, with a 3D view.
Schematic of BWRX-300. A tall reactor vessel with, from bottom to top, control rods and drives, the core, a tall chimney, steam separators and a steam dryer.
Schematic of BWRX-300.

Description

Blue Energy’s 13 August 2026 statement describes a Port of Victoria plan for about 1 GW from two gas turbines in 2030 and another 1.5 GW from up to five BWRX-300 units beginning in 2032, subject to a planned 2027 final investment decision. These are company targets; gross versus net is unstated. On 15 September 2026, Blue Energy Global Inc. tendered Construction Permit Application Part 1 for Nuclear Unit 1, with Sister 1 LLC as owner and GE Vernova Hitachi Nuclear Energy Americas LLC as reactor designer. The public non-proprietary Enclosure 9 names Blue Energy Global Inc. as the intended operator and says Sister 1 LLC was a wholly owned subsidiary through Blue Energy DevCo LLC and River 1 LLC, formed for project ownership, development and financing. These are the applicant’s stated roles as of filing, not an NRC determination or evidence of reactor operation. Part 1 requests a limited work authorization for deep foundation work and a crane pad; construction-permit review of the preliminary safety analysis report is reserved for Part 2. The applicant requested acceptance review of specified items by 20 November 2026; that is not an NRC commitment. The NRC’s 8 October 2026 Federal Register notice records receipt of Part 1 filed 15 September and says later notices will address acceptability for docketing. It is not acceptance, docketing, a construction permit, a limited work authorization or an operating license. The applicant describes Unit 1 as a BWRX-300 with a nominal net electrical output of approximately 300 MWe; the application covers that initial unit, and the 1.5 GW figure is a company plan for up to five units.

Key facts

Design
BWRX-300 (SMR)
Technology
Boiling water reactor (BWR) · light water
Reactor vessel of this design
27 m tall, 4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 25.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Operator(s)
Blue Energy
Vendor for linked design
GE Vernova Hitachi Nuclear Energy
Location
Port of Victoria · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
The 15 September 2026 application letter places Nuclear Unit 1 at the Port of Victoria site in Texas. No parcel point is published. The port authority's office address is not used as a pin. Not the 2010 Exelon Victoria County early site permit point. Searchable without an invented map pin.
Coordinates
Named site, no map pin
Electrical capacity
1500 MWe (gross/net unspecified) · scope: plant
Thermal capacity
Not recorded
Modules planned
5
Inclusion basis
SMR by design class
Confidence
medium
Record reviewed
18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Blue Energy BWRX-300 at Port of Victoria is recorded at Port of Victoria, Texas, United States. Operator: Blue Energy. Recorded vendor: GE Vernova Hitachi Nuclear Energy. Stage: Licensing. Location precision: site area (named plant, laboratory, base, port, campus or parcel); named site, no map pin.

Recorded electrical output is 1500 MWe (gross/net unspecified), scope plant. Modules planned: 5. Thermal output is not recorded on this project. The linked design record states 870 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project. The linked design record states 300 MWe (net); the project figure is kept separate.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Operator or intended licensed owner
Reactor supplier
Customer or offtaker
  • Prospective customer / offtaker (binding offtake not established)Crusoe · sourcePartnership announced 30 Oct 2025 for Blue Energy to supply power to Crusoe-developed AI factories on a nearby site; no power purchase agreement or binding terms stated.
Source-backed project statement

Crusoe's 30 October 2025 announcement says Blue Energy would develop a plant of up to 1.5 GW at the Port of Victoria and deliver power to Crusoe-developed AI factories on a nearby site. Crusoe is a prospective customer under that partnership. Blue Energy's 15 September 2026 filing says it intends to finance the nuclear phase like other power projects, backed by a long-term power purchase agreement, and names no executed offtake, so no binding offtake is shown. Crusoe: Blue Energy and Crusoe partner to develop nuclear-powered AI data center; Blue Energy Construction Permit Application Part 1, non-proprietary Enclosure 9 (ADAMS ML26265A376)

Contractor

Source-backed project statement Blue Energy's 15 September 2026 filing says major-equipment cost inputs come from agreements with GE Vernova Hitachi, including an Early Works Agreement, and that Blue Energy plans to engage an architect-engineer for a front-end engineering study. The synthetic EPC module contracts in the same filing are a financing model, not named awards. No construction contractor is named. Blue Energy Construction Permit Application Part 1, non-proprietary Enclosure 9 (ADAMS ML26265A376)

Funding and government decisions

Source-backed project statement Blue Energy's 15 September 2026 filing says the company has raised about 450 million dollars of equity and debt across its capital raises. It says those funds included long-lead equipment orders for the project before a final investment decision, as part of broader business growth. The filing does not state that the whole sum was spent on Unit 1, and it does not state the amount spent on the project. Blue Energy Construction Permit Application Part 1, non-proprietary Enclosure 9 (ADAMS ML26265A376)

Comparable schedule revision

Source-backed project statement Blue Energy and Crusoe said on 30 October 2025 that the Port of Victoria project would supply power as early as 2028 and move to expected nuclear generation by 2031. DatacenterDynamics reported on 17 August 2026 that Blue Energy intended to supply about 1 GW from two gas turbines in 2030, followed by up to 1.5 GW from as many as five BWRX-300s starting in 2032, which ANS also reported. The expected start of nuclear supply therefore moved from 2031 to 2032, and gas supply from as early as 2028 to 2030. Both are company targets subject to a 2027 investment decision, not achieved dates. Crusoe: Blue Energy and Crusoe partner to develop nuclear-powered AI data center; Blue Energy, GE Vernova Hitachi advance 2.5GW gas-plus-nuclear plant in Texas, to power up to 1.5GW data center; ANS: Agreement advances Texas gas-plus-nuclear concept

Not found in the sources we checked (1): Fuel
Fuel
No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.

Blue Energy's 15 September 2026 filing lists an initial fuel load as a redacted cost line and says the fuel cycle will be covered in Part 2's environmental report. No fuel supplier, fabrication or delivery for Unit 1 is named in the public text. Blue Energy Construction Permit Application Part 1, non-proprietary Enclosure 9 (ADAMS ML26265A376)

Not recorded in SMRMap's reviewed evidence (2): Site host or owner; Programs and agreements naming the project
Site host or owner
Programs and agreements naming the project

Timeline

Recorded developments

Targets

Planned, target and estimated dates are not achievements or commitments.

Permissions and applications

Construction applications and decisions

Assessments of the design (not of this site)

(2)
  • BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
    The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
    Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs
  • CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
    CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(7 notes)

Evidence dates

(4 of 12 sources with a publication or document date)
Latest dated listed source publication: Federal Register 91 FR 64409 (8 Oct 2026), govinfo copy: Blue Energy Center–Port of Victoria Nuclear Unit 1 phased construction permit application, notice of receipt: 8 Oct 2026.Latest dated recorded event: Blue Energy states it submitted the first part of an NRC construction permit application: 16 Sep 2026.8 of 12 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(12)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Blue Energy BWRX-300 at Port of Victoria — https://smrmap.com/projects/blue-energy-port-of-victoria/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Blue Energy BWRX-300 at Port of Victoria”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/blue-energy-port-of-victoria/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.