Projects / Russia · Construction
BREST-OD-300 Seversk
Lead-cooled fast demonstration reactor at Seversk.
Current status
- How current
- General record check . Bounded evidence review . 4 of 12 listed sources have a publication or document date recorded here; the newest is 19 Jun 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Reported 7 Oct 2026 · Recorded development: BREST-OD-300 turbine hall receives separator-superheaters. Rosatom said two separator-superheaters were installed in the turbine hall; concreting of the turbine foundation began in May 2026. Source: World Nuclear News: Key equipment installed in BREST-OD-300 turbine hall (7 October 2026). Updates entry
More on this development
This is non-nuclear turbine-hall work; it does not change the operation schedule.
- Next dated milestone
- Planned commercial operation: 2028 (target). Planned step: 2027 (target). Concreting of the BREST-OD-300 reactor vessel to finish (company target). These are not commitments or achieved milestones. Source: Atomic Energy 2.0 (relaying TVEL/SKhK release): First stage of BREST-OD-300 reactor-vessel concreting completed (14 September 2026).
- Selected limitations
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage (reviewed: source unavailable; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Lead-cooled fast reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
IAEA PRIS dates its construction license to 10 February 2021 and construction start to 8 June 2021. Live PRIS lists 700 MWth, 300 MWe gross and 281 MWe net, while the IAEA’s printed 2026 reactor tables list 306 MWe gross and 300 MWe net; the 300 MWe recorded here follows live PRIS as gross, and the conflict is preserved. PRIS gives 31 December 2028 as the expected commercial-operation date; that is a planned date, not an achievement. A TVEL release of 14 September 2026 says the first stage of concreting the reactor-vessel inner cavity was complete, with concreting to finish in winter 2027, and World Nuclear News reported on 7 October 2026, relaying Rosatom, that turbine-hall equipment was being installed with the turbine foundation due by the end of 2026. These are company statements; the earlier 2026 start-up target has not been met. IAEA PRIS names Siberian Chemical Plant JSC as operator and owner. Rosatom put the site's nitride-fuel fabrication module into pilot-industrial operation in December 2024, making mock-up assemblies with depleted uranium; production of uranium-plutonium nitride fuel for the first core awaited regulatory approval to handle plutonium.
Key facts
- Design
- BREST-OD-300 (SMR)
- Technology
- Lead-cooled fast reactor (LFR) · lead
- Reactor vessel of this design
- 17.5 m tall, 26 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 277.the section calls the vessel metal-concrete; that names this body and does not add a numeric qualifier The section describes a metal-concrete reactor vessel, not a conventional steel cylinder.SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Intended operator(s)
- Siberian Chemical Plant JSC (Siberian Chemical Combine)
- Vendor for linked design
- Rosatom
- Location
- Seversk BREST-OD-300 site · Russia · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for Seversk unit 1 (BREST-OD-300) in the Siberian Chemical Combine area (CC BY 4.0, derived from GEM's tracker); not a surveyed plot. Replaces an earlier hand-rounded point. - Coordinates
- 56.6583, 84.9482 · site-area point (approximate)
- Electrical capacity
- 300 MWe (gross) · scope: module
- Thermal capacity
- 700 MWth (nameplate; basis unspecified)
- Purpose
- Power plant
- Construction start
- 8 Jun 2021BREST-OD-300 construction start (IAEA PRIS)
- Inclusion basis
- SMR by design class
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
BREST-OD-300 Seversk is recorded at Seversk BREST-OD-300 site, Tomsk Oblast, Russia. Intended operator: Siberian Chemical Plant JSC (Siberian Chemical Combine). Recorded vendor: Rosatom. Stage: Construction. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'seversk-nuclear-power-plant-1' (56.6583, 84.9482)
Recorded electrical output is 300 MWe (gross), scope module. Modules planned: 1. Recorded thermal output is 700 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- Intended operatorSiberian Chemical Plant JSC (Siberian Chemical Combine)
- Intended licensed ownerSiberian Chemical Plant JSC (Siberian Chemical Combine) · source
- Reactor supplier
- Vendor for the linked designRosatom
- Contractor
- Construction contractorTitan-2 · sourceRUB26.3 billion construction and installation contract (reactor building, turbine hall, infrastructure) awarded by Siberian Chemical Combine in December 2019.
Source-backed project statement
World Nuclear News reported on 5 December 2019 that Siberian Chemical Combine awarded Titan-2 a RUB 26.3 billion contract for construction and installation works on BREST-OD-300, covering the reactor building, turbine hall and related infrastructure. A TVEL release reprinted on 14 September 2026 says Titan-2 has been concreting the reactor vessel's inner cavity, so the awarded contractor is doing the work. Construction is under way, not complete. WNN: Russia awards contract to build BREST reactor; Atomic Energy 2.0 (relaying TVEL/SKhK release): First stage of BREST-OD-300 reactor-vessel concreting completed (14 September 2026)
- Funding and government decisions
- Government or regulator decision naming the project; not a reactor permit; in effectRussia: General Scheme for the placement of electric power facilities to 2042 (Government Order No. 4153-r, 2024) · sourceThe General Scheme lists the pilot demonstration unit at Seversk (Tomsk Oblast) with BREST-OD-300 among planned nuclear units.
World Nuclear News' 2019 report gives the value of Siberian Chemical Combine's construction contract with Titan-2, RUB 26.3 billion, which is a contract price, not a funding source. The saved WNN, TVEL and PRIS texts name no funder, budget allocation or financing instrument for BREST-OD-300. WNN: Russia awards contract to build BREST reactor
- Fuel
- Fuel form stated for BREST-OD-300mixed uranium-plutonium mononitride (U-Pu)N
- Enrichment stated for BREST-OD-300up to 14.5%
Source-backed project statement
Rosatom's industry media center said on 25 December 2024 that the site's fuel fabrication module had entered pilot-industrial operation, making mock-up BREST-OD-300 assemblies from depleted uranium under a license of 29 March 2024, and that production of mixed uranium-plutonium nitride fuel can begin once the regulator approves plutonium handling. More than 200 such assemblies are needed for the first core. The first core's fuel is therefore to be made on site by Siberian Chemical Combine, with production of the real fuel still awaiting approval in that source. Atom Media (Rosatom press release): Rosatom puts the fuel plant for the BREST-OD-300 reactor into pilot-industrial operation (25 December 2024)
- Comparable schedule revision
Source-backed project statement Nuclear Engineering International reported on 19 June 2026 that Rosatom originally planned to launch BREST-OD-300 in 2026 and that, after additional research and development, the launch had been postponed to 2029. World Nuclear News on 7 October 2026 also reports an initial operation target of 2026. The reported launch target changed from 2026 to 2029; launch is not defined as criticality, grid connection or commercial operation. First concrete for BREST turbine - Nuclear Engineering International; World Nuclear News: Key equipment installed in BREST-OD-300 turbine hall (7 October 2026)
Not found in the sources we checked (1): Customer or offtaker
- Customer or offtaker
The IAEA PRIS record lists BREST-OD-300 at Seversk as under construction with Siberian Chemical Combine as operator and owner, and World Nuclear News' 7 October 2026 report describes the reactor within the site's closed fuel-cycle complex. Neither names a buyer or supply arrangement for the plant's electricity. IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026; World Nuclear News: Key equipment installed in BREST-OD-300 turbine hall (7 October 2026)
Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Site host or owner; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- Reported · Recorded development
BREST-OD-300 turbine hall receives separator-superheaters - Release dated · Recorded development
TVEL: first stage of concreting BREST-OD-300 reactor-vessel inner cavity completed - Announced · Recorded development
Fuel plant for BREST-OD-300 enters pilot operation - · Construction start
BREST-OD-300 construction start (IAEA PRIS) - · Regulatory step
Rostekhnadzor construction license for BREST-OD-300 issued to Siberian Chemical Combine
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Concreting of the BREST-OD-300 reactor vessel to finish (company target)
Dates on the project record: Planned commercial operation: 2028 (target).
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. BREST-OD-300 is a lead-cooled fast-neutron demonstration power unit, the main facility of the Pilot Demonstration Energy Complex of Rosatom's Proryv closed-fuel-cycle project at the Siberian Chemical Combine site in Seversk, Tomsk region (World Nuclear News, 11 February 2021 and 7 October 2026). World Nuclear News reported on 11 February 2021 that Rostekhnadzor had issued the Siberian Chemical Combine a license to construct the reactor, and live IAEA PRIS (captured 9 October 2026) gives a construction-license date of 10 February 2021, construction start on 8 June 2021, status under construction, 700 MWth, 300 MWe gross and 281 MWe net, Siberian Chemical Plant JSC as operator and owner, no operating-license date, and a commercial-operation date of 31 December 2028; the Rostekhnadzor license itself was not opened. Site and conventional-island work is separate from nuclear construction: Titan-2 holds a December 2019 contract to build the reactor building, turbine hall and infrastructure, turbine-generator foundation concreting began in May 2026 with completion due by the end of 2026, and two separator-superheaters were installed by October 2026; on the nuclear side, the four peripheral cavity shells were installed by the end of 2025 with the reactor vessel reported about 70 percent assembled, the primary-circuit piping between the cavities was completed earlier in 2026, and a TVEL release of 14 September 2026 says the first stage of concreting the reactor-vessel inner cavity is complete, with concreting to finish in winter 2027. The initial operation target of 2026 was missed; an undated Rosatom newsletter page gives operation in 2027, while PRIS gives 31 December 2028, so the target is not consistent across sources. The on-site fuel module made depleted-uranium mock-up assemblies under a Rostekhnadzor license of 29 March 2024, and uranium-plutonium nitride fuel for the first core awaits regulator approval to handle plutonium (Rosatom, 25 December 2024). Stored values (300 MWe gross, 700 MWth, one unit, Siberian Chemical Combine as operator, PRIS construction start and 2028 target) match PRIS; the IAEA printed-table figures of 306 MWe gross and 300 MWe net noted in the summary could not be tied to a quotable row in the captured RDS-2 text. At that review the record had no participant roles; roles recorded since are listed on this page. Last checked 19 Oct 2026. IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026; World Nuclear News: Rostekhnadzor construction licence for BREST-OD-300 issued to Siberian Chemical Combine; World Nuclear News: Key equipment installed in BREST-OD-300 turbine hall (7 October 2026); Atomic Energy 2.0 (relaying TVEL/SKhK release): First stage of BREST-OD-300 reactor-vessel concreting completed (14 September 2026); Atom Media (Rosatom press release): Rosatom puts the fuel plant for the BREST-OD-300 reactor into pilot-industrial operation (25 December 2024); Rosatom BREST construction
What would change this
A Rostekhnadzor operating license or plutonium-handling approval for the first-core fuel, a readable copy of the 2021 construction license, or a Rosatom statement of a new start-up date. Next scheduled check: 19 Jan 2027.
- Permission evidence appropriate to stage: Source unavailable. The February 2021 Rostekhnadzor construction license for BREST-OD-300 is known from IAEA PRIS (license date 10 February 2021) and World Nuclear News (signed by the regulator's chairman). Rostekhnadzor's website returned an access refusal (HTTP 403) and no other official copy or license number was found, so no regulatory action is recorded. Last checked 19 Oct 2026. IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026; World Nuclear News: Rostekhnadzor construction licence for BREST-OD-300 issued to Siberian Chemical Combine
What would change this
A readable Rostekhnadzor register entry or Rosatom/SKhK page giving the construction-license number and date. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The September 2026 TVEL release says concreting of the BREST-OD-300 reactor vessel will continue in stages until winter 2027, and IAEA PRIS lists 31 December 2028 as the expected commercial-operation date. Fuel for the first core depends on the regulator approving plutonium handling at the on-site fabrication module, as the December 2024 Rosatom release states. The earlier 2026 operation target has passed; 2027 and 2028 are targets, not achievements. Last checked 23 Oct 2026. Atomic Energy 2.0 (relaying TVEL/SKhK release): First stage of BREST-OD-300 reactor-vessel concreting completed (14 September 2026); IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026; World Nuclear News: Key equipment installed in BREST-OD-300 turbine hall (7 October 2026)
What would change this
Completion of reactor-vessel concreting, a plutonium-handling approval for the fuel module, or a revised PRIS date. Next scheduled check: 23 Apr 2027.
- Permissions and public process. World Nuclear News reported on 11 February 2021 that Rostekhnadzor issued Siberian Chemical Combine a license to construct the BREST-OD-300 unit at Seversk. A December 2024 Rosatom release says the on-site fuel fabrication module works with depleted uranium under a Rostekhnadzor license of 29 March 2024, and that making uranium-plutonium fuel awaits the regulator's approval to handle plutonium. These sources describe no operating license and no public hearing. Last checked 23 Oct 2026. World Nuclear News: Rostekhnadzor construction licence for BREST-OD-300 issued to Siberian Chemical Combine; Atom Media (Rosatom press release): Rosatom puts the fuel plant for the BREST-OD-300 reactor into pilot-industrial operation (25 December 2024)
What would change this
A Rostekhnadzor decision approving plutonium handling at the fuel module or an operating license for the BREST-OD-300 unit. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). The September 2026 TVEL release relayed by Atomic Energy 2.0 says the pilot demonstration energy complex is being built on the territory of the Siberian Chemical Combine in Seversk, Tomsk region, and World Nuclear News reported in October 2026 that turbine-hall equipment was being installed. These sources place the unit on the combine's existing site but do not describe its grid connection or cooling-water arrangements. Last checked 23 Oct 2026. Atomic Energy 2.0 (relaying TVEL/SKhK release): First stage of BREST-OD-300 reactor-vessel concreting completed (14 September 2026); World Nuclear News: Key equipment installed in BREST-OD-300 turbine hall (7 October 2026)
What would change this
A Rosatom or grid-operator statement on connecting the BREST-OD-300 unit to the regional grid, or a published description of its cooling arrangements. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure. World Nuclear News reported in February 2021 that the Seversk complex will demonstrate an on-site closed fuel cycle with a fuel fabrication facility and a used-fuel reprocessing facility, and a December 2024 Rosatom release lists the reprocessing module as one of the complex's three facilities. This is a planned on-site arrangement: the fabrication module has started trial work, but these sources do not say the reprocessing module is licensed or built, or where residual waste will be disposed of. Last checked 23 Oct 2026. World Nuclear News: Rostekhnadzor construction licence for BREST-OD-300 issued to Siberian Chemical Combine; Atom Media (Rosatom press release): Rosatom puts the fuel plant for the BREST-OD-300 reactor into pilot-industrial operation (25 December 2024)
What would change this
A Rosatom or Rostekhnadzor statement on licensing or construction of the Seversk reprocessing module, or on disposal of its residual waste. Next scheduled check: 23 Apr 2027.
Evidence dates
(4 of 12 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(12)
- World Nuclear Association — Small Nuclear Power Reactors (directory or tracker, accessed 1 Oct 2026)
- EnergyNote 2026 SMR licensing map (news report, accessed 1 Oct 2026)
- Global Energy Monitor Global Nuclear Power Tracker (directory or tracker, accessed 2 Oct 2026)
- Rosatom BREST construction (company, accessed 1 Oct 2026)
- World Nuclear News: Key equipment installed in BREST-OD-300 turbine hall (7 October 2026) (news report, accessed 9 Oct 2026)
- IAEA PRIS statistics: reactors by country code (Russia), captured 9 October 2026 (IAEA/NEA, accessed 18 Oct 2026)
- IAEA: Nuclear Power Reactors in the World, Reference Data Series No. 2, 2026 edition (IAEA-RDS-2/46, September 2026) (IAEA/NEA, accessed 9 Oct 2026)
- Atomic Energy 2.0 (relaying TVEL/SKhK release): First stage of BREST-OD-300 reactor-vessel concreting completed (14 September 2026) (news report, accessed 9 Oct 2026)
- Atom Media (Rosatom press release): Rosatom puts the fuel plant for the BREST-OD-300 reactor into pilot-industrial operation (25 December 2024) (company, dated 25 Dec 2024, accessed 18 Oct 2026)
- World Nuclear News: Rostekhnadzor construction licence for BREST-OD-300 issued to Siberian Chemical Combine (news report, published 11 Feb 2021, accessed 14 Oct 2026)
- WNN: Russia awards contract to build BREST reactor (news report, published 5 Dec 2019, accessed 21 Oct 2026)
- First concrete for BREST turbine - Nuclear Engineering International (news report, published 19 Jun 2026, accessed 21 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: BREST-OD-300 Seversk — https://smrmap.com/projects/brest-od-300/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “BREST-OD-300 Seversk”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/brest-od-300/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.