Deployable Energy Unity full-power test in INL's DOME (2027)
NRIC selected Deployable Energy for a conditional 2027 full-power Unity test at the named DOME facility at INL, per INL’s 30 September 2026 release.
Current status
- How current
- General record check . Bounded evidence review . 1 of 3 listed sources has a publication or document date recorded here: 30 Sep 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Announced 30 Sep 2026 · Announcement: INL names DOME as host for Unity's planned 2027 full-power test. INL named DOME as the host for Unity's planned 2027 full-power test. Source: INL: Deployable Energy selected to test its nuclear battery at DOME (published 30 Sep 2026). Updates entry
More on this development
The self-funded slot is conditional on readiness, fuel and regulatory milestones. Selection is not authorization.
- Next dated milestone
- Planned step: 2027 (target). Unity full-power DOME test targeted. This is not an achieved milestone. Source: INL: Deployable Energy selected to test its nuclear battery at DOME (published 30 Sep 2026).
- Selected limitations
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 3 tracked: 1 commissioning, 1 siting, 1 announced. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
The design is 1 MWe, light-water-moderated and helium-cooled; thermal and gross/net electrical basis are not stated. The self-funded slot depends on readiness, fuel and regulatory-plan milestones. This is Siting at a named test host, not an accepted application or experiment authorization. Separate from the 30 June 2026 zero-power criticality experiment. The approximate pin marks the DOME building, not a reactor position.
Key facts
- Design
- Unity (Microreactor)
- Technology
- Other · helium
- Operator(s)
- Not recorded
- Vendor for linked design
- Deployable Energy
- Location
- DOME test bed, Idaho National Laboratory · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
DOE identifies DOME as the repurposed EBR-II containment. This reuses the recorded OpenStreetMap building center 43.59507,−112.65716. The shared facility point is approximate and does not separate reactor positions or establish permission. - Coordinates
- 43.59507, -112.65716 · site-area point (approximate)
- Electrical capacity
- 1 MWe (gross/net unspecified) · scope: module
- Thermal capacity
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 13 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Deployable Energy Unity full-power test in INL's DOME (2027) is recorded at DOME test bed, Idaho National Laboratory, Idaho, United States. Operator: No operator is recorded. Recorded vendor: Deployable Energy. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: eVinci DOME nuclear test reactor, Pylon / LOKI MMR experiment proposal for INL's DOME.
Coordinate source: OpenStreetMap Nominatim geocoder, OpenStreetMap Nominatim result: building center of the EBR-II containment (DOME) at the Materials and Fuels Complex, 43.59507, −112.65716
Recorded electrical output is 1 MWe (gross/net unspecified), scope module. Modules planned: 1. Thermal output is not recorded on this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerDeployable Energy · source
- Reactor supplier
- Vendor for the linked designDeployable Energy
- Funding and government decisions
Source-backed project statement INL's 30 September 2026 release, as carried by KIFI, says Deployable Energy's DOME testing campaign is self-funded. The American Nuclear Society reports that NRIC's award conditions center on schedule and funding information. No amount is stated. KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME; ANS: Deployable Energy next in line for testing in NRIC's DOME
- Fuel
- Fuel form stated for UnityUO2 annular pellets, Zircaloy cladding
- Enrichment stated for Unity4.95% U-235 (LEU)
INL's 30 September 2026 release lists fuel availability as a condition of the test timeline, and the American Nuclear Society's 2 October 2026 report gives DOME's enrichment limit and says Deployable achieved zero-power criticality earlier. Neither names a fuel supplier, quantity or delivery for the DOME test. KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME; ANS: Deployable Energy next in line for testing in NRIC's DOME
- Site host or owner
- Site hostIdaho National Laboratory · source
Not found in the sources we checked (3): Customer or offtaker; Contractor; Comparable schedule revision
- Customer or offtaker
INL's 30 September 2026 release, as carried by KIFI, and the American Nuclear Society's 2 October 2026 report describe a conditional 2027 full-power test of Deployable Energy's 1 MWe Unity reactor in DOME. Neither names a buyer or user of the test's power. KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME; ANS: Deployable Energy next in line for testing in NRIC's DOME
- Contractor
INL's 30 September 2026 release says NRIC selected Deployable Energy to test its reactor in DOME in 2027, and the American Nuclear Society says Deployable filled DOME's second slot. That is a test host selecting the vendor, not a contractor appointment. Neither source names an engineering, fabrication or construction contractor for the Unity test. KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME; ANS: Deployable Energy next in line for testing in NRIC's DOME
- Comparable schedule revision
Comparable schedule revision not established. INL's 30 September 2026 release gives one target, a 2027 full-power test in DOME. The zero-power criticality reported for an earlier date is a separate experiment, not a different date for the DOME test. No earlier and later targets for the same milestone appear. KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME; ANS: Deployable Energy next in line for testing in NRIC's DOME
Not recorded in SMRMap's reviewed evidence (2): Operator or intended licensed owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Programs and agreements naming the project
Timeline
Recorded developments
- Announced · Announcement
INL names DOME as host for Unity's planned 2027 full-power test
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Unity full-power DOME test targeted
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(4 notes, 1 not yet reviewed)
- Evidence review. The DOE's National Reactor Innovation Center selected Deployable Energy to test its Unity nuclear battery in the DOME test bed at Idaho National Laboratory in 2027, according to INL's 30 September 2026 release as carried by KIFI; INL's own page could not be opened when checked (access refused). The planned test is a full-power test of one light-water-moderated, helium-cooled transportable microreactor designed to generate 1 MWe; its thermal output and gross or net basis are not stated. The slot is self-funded and conditional: the timeline depends on technology readiness, fuel availability and regulatory approval plans, and Deployable must meet milestones to keep its DOME time. NRIC's selection is a test-bed allocation, not an authorization of the experiment, and no opened source records a DOE authorization for the DOME test. ANS reports the company's earlier zero-power criticality at INL on 1 July, while the stored summary, taken from the INL release, says 30 June 2026; the readable KIFI copy omits the date. The stored Unity design, Deployable Energy as vendor, one module at 1 MWe, empty operator list and siting stage stay. The next documentary decision is DOE's authorization of the Unity experiment in DOME. Last checked 19 Oct 2026. KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME; ANS: Deployable Energy next in line for testing in NRIC's DOME; INL: Deployable Energy selected to test its nuclear battery at DOME
What would change this
A DOE or NRIC authorization of the Unity DOME experiment (or a readable INL release giving its conditions), or news that Deployable lost its slot, would change this record. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. INL's September 2026 release says Deployable Energy plans a full-power Unity test in DOME in 2027, after Radiant's campaign, and must meet readiness, fuel and regulatory milestones to keep the slot. The 2027 date is a target; these sources give no month and do not show that fuel or DOE authorization for the test is in place. Last checked 23 Oct 2026. KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME
What would change this
Deployable Energy meeting its first DOME milestone, a DOE authorization, or a revised test date. Next scheduled check: 23 Jan 2027.
- Permissions and public process. INL's 30 September 2026 release, as carried by KIFI, says the National Reactor Innovation Center selected Deployable Energy for a 2027 full-power Unity test in DOME, with a timeline based on technology readiness, fuel availability and regulatory approval plans, and milestones the company must meet to keep its slot. A test-slot selection is not an authorization; these sources name no DOE safety approval for the DOME test and describe no public comment process. Last checked 23 Oct 2026. KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME
What would change this
A DOE approval of a safety analysis for the Unity DOME experiment. Next scheduled check: 23 Jan 2027.
- Site dependencies (land, grid, water). The test host is the DOME test bed at Idaho National Laboratory, which the American Nuclear Society's October 2026 report describes as built from the containment of the decommissioned EBR-II reactor and designed for test reactors up to 20 MWt using fuel below 20% enrichment. DOME opened in April 2026 and hosted Radiant's test first. These sources describe the host facility, not any Unity-specific grid, cooling or utility arrangement. Last checked 23 Oct 2026. ANS: Deployable Energy next in line for testing in NRIC's DOME; KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME
What would change this
A DOE or INL statement on Unity's installation in DOME or its site services. Next scheduled check: 23 Jan 2027.
Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.
Evidence dates
(1 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- KIFI: Deployable Energy selected by NRIC to test its nuclear battery at DOME (news report, accessed 2 Oct 2026)
- ANS: Deployable Energy next in line for testing in NRIC's DOME (news report, accessed 2 Oct 2026)
- INL: Deployable Energy selected to test its nuclear battery at DOME (government, published 30 Sep 2026, accessed 13 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Deployable Energy Unity full-power test in INL's DOME (2027) — https://smrmap.com/projects/unity-dome-2027/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Deployable Energy Unity full-power test in INL's DOME (2027)”. Record reviewed 13 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/unity-dome-2027/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.