Projects / United States · Siting
Elementl Letart Township BWRX-300 proposal
Elementl announced an up-to-1.5-GW BWRX-300 development at Letart Township on 18 June 2026.
Current status
- How current
- General record check . Bounded evidence review . 3 of 4 listed sources have a publication or document date recorded here; the newest is 26 Oct 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- Announced 26 Oct 2026 · Announcement: Elementl announces proposed partnership of up to $750 million. Elementl said a consortium led by DS Investment Partners would fund a portion of a partnership supporting up to three projects, including Ohio. Source: Elementl: proposed development partnership with DS Investment Partners and Samsung C&T (published 26 Oct 2026). Updates entry
More on this development
A preliminary agreement subject to definitive documents and approvals. It is not a final investment decision or committed funding.
- Next dated milestone
- Planned step: 2030 (target). Elementl target for starting construction of the first Letart unit. This is not an achieved milestone. Source: Elementl announces Southeast Ohio BWRX-300 proposal (published 18 Jun 2026); Elementl Power: Ohio Advanced Nuclear Project fact sheet (revised 1 Sep 2026).
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 18 tracked: 1 construction, 4 licensing, 10 siting, 3 announced. 65 tracked at siting across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Boiling water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
It signed an early works agreement and agreed to buy the property. Its project fact sheet, revised 1 September 2026, describes five BWRX-300 reactors of 300 MW nameplate each. An initial 600 MW interconnection request is a development step, not capacity already built or permitted. Elementl expects construction of the first unit to begin in 2030, subject to a final investment decision and NRC and Ohio Power Siting Board approvals, with completion anticipated in 2034; these are company targets. Elementl is the proposer; neither source names an intended licensed operator. Elementl said on 26 October 2026 that it signed a letter of intent and term sheet for a proposed development partnership of up to $750 million with a consortium led by DS Investment Partners, with Samsung C&T as a potential strategic investor. The partnership would fund part of the pre-investment-decision capital for up to three projects, including this one; it is not a final investment decision or committed project funding.
Key facts
- Design
- BWRX-300 (SMR)
- Technology
- Boiling water reactor (BWR) · light water
- Reactor vessel of this design
- 27 m tall, 4 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 25.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Not recorded
- Vendor for linked design
- GE Vernova Hitachi Nuclear Energy
- Location
- Letart Township, Meigs County · United States · precision: town or locality only
Approximate NuclearChain export point (derived from GEM's tracker) for this same Elementl Letart BWRX-300 project; represents the Letart Township riverside area, not a survey of the ~700-acre parcel. - Coordinates
- 38.8944, -81.8963 · town-level point (approximate)
- Electrical capacity
- Not recorded · scope: plant
- Thermal capacity
- Not recorded
- Inclusion basis
- SMR by design class
- Confidence
- medium
- Record reviewed
- 11 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Elementl Letart Township BWRX-300 proposal is recorded at Letart Township, Meigs County, Ohio, United States. Operator: No operator is recorded. Recorded vendor: GE Vernova Hitachi Nuclear Energy. Stage: Siting. Location precision: town or locality only; town-level point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'letart-nuclear-power-plant-1' (38.8944111, -81.8962768)
Electrical output is not recorded on this project. Modules planned: 5. Thermal output is not recorded on this project. The linked design record states 870 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerElementl Power · source
- Reactor supplier
- Vendor for the linked designGE Vernova Hitachi Nuclear Energy
- Contractor
Source-backed project statement Elementl's 18 June 2026 release says it signed an Early Works Agreement with GE Vernova Hitachi Nuclear Energy to use the BWRX-300 for the Letart Township project. That is an explicit preparatory contract with the reactor vendor whose work scope is not described. It is not an engineering, procurement and construction award, and no construction contractor is named. Elementl announces Southeast Ohio BWRX-300 proposal
- Funding and government decisions
Source-backed project statement Elementl's 18 June 2026 release says that, as a private development project, Elementl plans to finance the cost of the proposed Letart Township plant and that it will not be funded through electric customer rates, and the fact sheet revised 1 September 2026 repeats that it will be privately financed. This is a stated financing plan by the developer itself, with no amount, lender, investor or financial close disclosed. Elementl announces Southeast Ohio BWRX-300 proposal; Elementl Power: Ohio Advanced Nuclear Project fact sheet
Not found in the sources we checked (3): Customer or offtaker; Fuel; Comparable schedule revision
- Customer or offtaker
Elementl's 18 June 2026 release and its Meigs County fact sheet revised 1 September 2026 name no buyer, quantity or power purchase agreement for the Letart Township plant. American Municipal Power is named as the seller of the site, and the PJM filing is an interconnection request for the first 600 MW, not a sale of power. Elementl announces Southeast Ohio BWRX-300 proposal
- Fuel
- No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.
Elementl's 18 June 2026 release and its fact sheet revised 1 September 2026 name the GE Vernova Hitachi BWRX-300 technology but no fuel supplier, enrichment contract, fabrication or delivery for the Letart Township units. Neither document mentions fuel. Elementl Power: Ohio Advanced Nuclear Project fact sheet
- Comparable schedule revision
Comparable schedule revision not established. Elementl's 18 June 2026 announcement and its fact sheet revised 1 September 2026 both say construction of the first Letart unit is expected to begin in 2030, subject to a final investment decision and regulatory approvals, with completion in 2034. The same targets restated are not a revision. Elementl announces Southeast Ohio BWRX-300 proposal; Elementl Power: Ohio Advanced Nuclear Project fact sheet
Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Site host or owner
- Programs and agreements naming the project
Timeline
Recorded developments
- Announced · Announcement
Elementl announces proposed partnership of up to $750 million - Announced · Announcement
Elementl announces Letart BWRX-300 proposal
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step
Elementl target for starting construction of the first Letart unit
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Assessments of the design (not of this site)
(2)
- BWRX-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed Dec 2025
The UK regulators began a two-step Generic Design Assessment of the GE Vernova Hitachi BWRX-300 on 25 January 2024 at the government's request. Step 1 ran from January to December 2024 and Step 2 from December 2024 to December 2025, when ONR issued its Step 2 GDA statement and the Environment Agency and Natural Resources Wales their Step 2 summary of findings. ONR's page records no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
Sources: ONR, GE Vernova Hitachi BWRX-300 Generic Design Assessment; Environment Agency: assessing new nuclear reactor designs - CNSC vendor design review, Phases 1 and 2 (BWRX-300) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · CNSC · completed Mar 2023
CNSC lists a combined Phase 1 and 2 pre-licensing vendor design review of GE Hitachi's BWRX-300 among its completed reviews, with an executive summary dated March 2023. CNSC entered into the agreement with GE Hitachi to conduct the review on 11 December 2019; that is an agreement date, not an application or a decision. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions. The Darlington license to construct is a separate, site-specific permission.
Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: GE Hitachi BWRX-300 vendor design review executive summary
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(5 notes)
- Evidence review. Elementl's 18 June 2026 release gives an up-to-1.5-GW BWRX-300 proposal at Letart Township; its factsheet revised 1 September expressly describes five 300 MW nameplate reactors. The five-unit planned configuration is supported, while gross/net basis is unspecified and the up-to plant figure is not stored as a fixed rating. A filed initial 600 MW PJM request remains in the study phase, not an approved connection or achieved plant output. Elementl is the developer, GE Vernova Hitachi the early-works/technology counterparty, and American Municipal Power the land-sale counterparty. A purchase agreement is not a completed land transfer; an early-works agreement is not a full EPC award. Neither source expressly names a nuclear operating entity or electricity offtaker. The factsheet identifies NRC and Ohio siting approvals as required, not already filed or granted. Unit 1 construction is targeted for 2030 subject to final investment decision and approvals, with completion targeted for 2034; completion is not expressly first criticality or commercial operation. Private financing is planned, not demonstrated financial close. No broad record-review date changes. Last checked 19 Oct 2026. Elementl announces Southeast Ohio BWRX-300 proposal; Elementl Power: Ohio Advanced Nuclear Project fact sheet
What would change this
A PJM outcome, project-specific NRC or Ohio siting application/decision, investment decision, or executed project-level fuel, construction or offtake contract. No sequence or decision date is inferred. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. Elementl's June 2026 release says PJM was expected to respond to its interconnection request later in 2026, and that construction of the first unit is expected to begin in 2030, subject to a final investment decision and regulatory approvals, with completion in 2034. The 2030 and 2034 dates are company targets; no final investment decision or approval has been reported. Last checked 23 Oct 2026. Elementl announces Southeast Ohio BWRX-300 proposal
What would change this
PJM's response to the interconnection request, an NRC filing, or a final investment decision. Next scheduled check: 23 Apr 2027.
- Permissions and public process. Elementl's 18 June 2026 release says that, if it moves forward, the Letart Township site will need approvals from multiple state and federal agencies, including the NRC and the Ohio Power Siting Board; its fact sheet revised 1 September 2026 repeats this. Neither source reports any application filed with the NRC or the Siting Board, any permit, or any public hearing or community agreement. Last checked 23 Oct 2026. Elementl announces Southeast Ohio BWRX-300 proposal; Elementl Power: Ohio Advanced Nuclear Project fact sheet
What would change this
An NRC pre-application or application filing, or an Ohio Power Siting Board application, for the Letart site. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). Elementl's June 2026 release says it agreed to buy the nearly 700-acre Letart Township property along the Ohio River from American Municipal Power, and filed a PJM interconnection request for the first 600 MW. The September 2026 fact sheet says the request is in PJM's study phase. A purchase agreement and a pending interconnection request are not completed land ownership or a secured grid connection, and no cooling-water arrangement is stated. Last checked 23 Oct 2026. Elementl announces Southeast Ohio BWRX-300 proposal; Elementl Power: Ohio Advanced Nuclear Project fact sheet
What would change this
Completion of the AMP site purchase or a PJM interconnection study result or agreement. Next scheduled check: 23 Apr 2027.
- Spent fuel, waste and closure. Elementl's Meigs County project page states that spent fuel from the facility would be stored on site in dry casks under NRC requirements. This is a project-specific developer plan, not proof of a licensed or implemented storage arrangement. The page does not identify an offsite destination or disposal contract. Confirm the plan and responsibilities against a project licensing or environmental filing when available. Last checked 23 Oct 2026. Advanced nuclear: Meigs County, Ohio project page (questions and answers)
What would change this
An early site permit or construction permit application with an environmental report for the Meigs County plant, or a change to the developer's stated storage plan. Next scheduled check: 21 Jan 2027.
Evidence dates
(3 of 4 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(4)
- Elementl announces Southeast Ohio BWRX-300 proposal (company, published 18 Jun 2026, accessed 11 Oct 2026)
- Elementl Power: Ohio Advanced Nuclear Project fact sheet (company, revised 1 Sep 2026, accessed 11 Oct 2026)
- Advanced nuclear: Meigs County, Ohio project page (questions and answers) (company, accessed 23 Oct 2026)
- Elementl: proposed development partnership with DS Investment Partners and Samsung C&T (company, published 26 Oct 2026, accessed 11 Nov 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Elementl Letart Township BWRX-300 proposal — https://smrmap.com/projects/elementl-letart-bwrx300/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Elementl Letart Township BWRX-300 proposal”. Record reviewed 11 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/elementl-letart-bwrx300/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.