Projects / United States · Announced

First American Nuclear EAGL-1 energy park in Indiana (site not disclosed)

FANCO and the State of Indiana announced plans for an EAGL-1 energy park in Indiana on 4 November 2025.

Current status

Stage
Announced
How current
Record checked · Evidence reviewed · Next recheck due
Development and review dates

Newest recorded development . 5 of 10 listed sources have a publication or document date recorded here; the newest is 15 Apr 2026. A listed page was last updated 15 Sep 2026. Status not rechecked since the record check; this project is not covered by the nightly status check. Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
Announced 4 Nov 2025 · Announcement: First American Nuclear and Indiana announce an EAGL-1 energy park plan. FANCO and the State of Indiana announced plans for FANCO's headquarters, manufacturing facilities and one energy park in Indiana. Source: First American Nuclear announces Indiana EAGL-1 energy park plan (published 4 Nov 2025); ANS: Indiana partners with First American Nuclear (published 10 Nov 2025). Updates entry
More on this development

No county or site is named. Not a construction permit and not a module count. ANS reported the announcement on 10 November 2025.

Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • No map pin is shown for this record.
  • Not yet recorded for this stage: Site location recorded as disclosed (not stated in the sources read). Not recorded does not mean zero or that none exists; the description and sources may say more.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Reactor type
Lead-cooled fast reactor. How it works, with a 3D view.

Description

Its current FAQ says a first project will be announced when customer, site, commercial and disclosure requirements permit; it does not confirm that the Indiana plan is a selected first project or that the plan was canceled. FANCO's NRC pre-application engagement concerns the EAGL-1 design and a future construction-permit application; the NRC lists its regulatory engagement plan as "No review requested". That engagement is not a docketed application and names no site. FANCO's 15 April 2026 release says it is working with the State of Indiana on manufacturing, siting and workforce development; it names no site either. No county, municipality or site is named, and this record has no map pin. FANCO said in 2025 that it was weighing five locations; those are not five projects. The NEA edition 4.0 siting row labels the status as non-binding agreements with a site owner. That label is not a second project. The EAGL-1 design page states 240 MWe and 600 MWt per unit; those figures are not copied to this project because the park announcement does not state its configuration. No module count is stored.

Key facts

Design
EAGL-1 (SMR)
Technology
Lead-cooled fast reactor (LFR) · lead bismuth
Operator(s)
Not recorded
Vendor for linked design
First American Nuclear
Location
EAGL-1 energy park, Indiana (site not disclosed) · United States · precision: region only
Searchable without an invented map pin. Indiana is the state named in the announcement, not a host property.
Coordinates
Region only, no map pin
Electrical capacity
Not recorded · scope: plant
Thermal capacity
Not recorded
Modules planned
Not recorded
Record reviewed
11 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

First American Nuclear EAGL-1 energy park in Indiana (site not disclosed) is recorded at EAGL-1 energy park, Indiana (site not disclosed), Indiana, United States. Operator: No operator is recorded. Recorded vendor: First American Nuclear. Stage: Announced. Location precision: region only; region only, no map pin.

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project. The linked design record states 600 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Project proposer or applicant
Reactor supplier
Not found in the sources we checked (5): Customer or offtaker; Contractor; Funding and government decisions; Fuel; Comparable schedule revision
Customer or offtaker

First American Nuclear's 4 November 2025 announcement with the State of Indiana describes an EAGL-1 energy park but names no buyer of its power, and the company FAQ says a first project will be announced only when customer, site, commercial and disclosure requirements permit. ANS reported on 10 November 2025 that no details on locations or the partnership had been given. First American Nuclear FAQ; ANS: Indiana partners with First American Nuclear

Contractor

First American Nuclear's 4 November 2025 announcement and its FAQ name no engineering or construction contractor for the Indiana energy park. The FAQ says each project's scope would be delivered with unnamed qualified partners, and ANS lists a May 2026 company-level alliance with AtkinsRéalis only as a related headline, not tied to Indiana in the text read. First American Nuclear FAQ; ANS: Indiana partners with First American Nuclear

Funding and government decisions

First American Nuclear's FAQ says it can work with financing and development partners to structure capital project by project, and ANS reported on 10 November 2025 that no costs had been given. No funder, amount or financing is stated for the Indiana energy park. First American Nuclear FAQ; ANS: Indiana partners with First American Nuclear

Fuel
No fuel form or enrichment is recorded on the linked design profile.No project-specific fuel supply arrangement is recorded as a structured fact.

First American Nuclear's FAQ says EAGL-1's initial configuration is being developed around HALEU uranium-oxide fuel, with HALEU supply and fabrication still open workstreams, and the November 2025 announcement describes on-site reprocessing as the park's aim. These are design and fuel-cycle intentions. No fuel supplier, fabrication contract or delivery for the Indiana park is named. First American Nuclear FAQ; First American Nuclear announces Indiana EAGL-1 energy park plan

Comparable schedule revision

Comparable schedule revision not established. First American Nuclear's 4 November 2025 announcement and FAQ give no construction or operation date for the Indiana energy park, and ANS reported on 10 November 2025 that no timelines had been provided. With no dated target, no revision is shown. ANS: Indiana partners with First American Nuclear

Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
Operator or intended licensed owner
Site host or owner
Programs and agreements naming the project

Timeline

Recorded developments

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(6 notes)
  • Evidence review. First American Nuclear said on 4 November 2025 that it and the State of Indiana announced plans for the company's headquarters, manufacturing and an energy park in Indiana, including on-site reprocessing of spent fuel. Its FAQ says it will announce a first project when customer, site, commercial and disclosure requirements permit, so the Indiana announcement is not a selected site. The EAGL-1 product page describes the reactor as 240 MWe; that is a design description, not an Indiana plant total, and it is not stored. The NRC pre-application page does not name Indiana in the text searched. The Journal Gazette page returned an access refusal (HTTP 429) and was not read. The stored EAGL-1 design, FANCO as proposer and announced stage stay. Last checked 19 Oct 2026. First American Nuclear announces Indiana EAGL-1 energy park plan; First American Nuclear FAQ; First American Nuclear: EAGL-1; Journal Gazette: First American Nuclear headquarters and Indiana energy park
    What would change this

    A FANCO announcement that names the Indiana site, or a statement that the Indiana park will not proceed, would change this record. Next recheck due .

  • Site location recorded as disclosed: Not disclosed in the reviewed evidence. The November 2025 announcement places an energy park in Indiana and does not name a town or plot. The FAQ says the first project will be announced when site requirements permit. Last checked 19 Oct 2026. First American Nuclear announces Indiana EAGL-1 energy park plan; First American Nuclear FAQ
    What would change this

    The first-project announcement FANCO says it will make when a site can be disclosed would settle the site. Next recheck due .

  • Next decision and prerequisites. FANCO's FAQ says the next step is announcing a first project once customer, site, commercial and disclosure requirements permit, while commercial, site, engineering, financing and regulatory work proceeds in parallel; the NRC page shows pre-application work toward a construction permit application. No date for either step is given. Last checked 23 Oct 2026. First American Nuclear FAQ
    What would change this

    FANCO's first-project announcement or a construction permit application filing. Next recheck due .

  • Permissions and public process. The NRC's First American Nuclear page says the NRC has been in pre-application activities with the company since December 2025 on a future construction permit application, and lists its regulatory engagement plan. FANCO's FAQ says that, as of February 2026, it is in pre-application engagement with the NRC. Neither source ties that engagement to a named Indiana site, and no application, permit or public process for the Indiana energy park is recorded. Last checked 23 Oct 2026. NRC: First American Nuclear pre-application activities; First American Nuclear FAQ
    What would change this

    A FANCO construction permit application naming an Indiana site, or an announced first project. Next recheck due .

  • Site dependencies (land, grid, water): Not disclosed in the reviewed evidence. FANCO and Indiana's November 2025 announcement says the state will host the company's headquarters, manufacturing and an energy park, but names no county or site. FANCO's FAQ says it will announce a first project when customer, site, commercial and disclosure requirements permit. No site, land, grid or water arrangement for the Indiana energy park is disclosed in these sources. Last checked 23 Oct 2026. First American Nuclear announces Indiana EAGL-1 energy park plan; First American Nuclear FAQ
    What would change this

    A FANCO announcement naming the Indiana energy park site or a land or interconnection agreement. Next recheck due .

  • Spent fuel, waste and closure: Sources conflict. FANCO and Indiana's November 2025 announcement says the energy park is designed to reprocess and reuse spent fuel on site in a closed fuel cycle. FANCO's later FAQ says initial EAGL-1 deployments do not depend on fuel recycling and would manage used fuel under the applicable U.S. regulatory framework, with recycling a longer-term option. Both are company statements of intent, not a storage, reprocessing or disposal arrangement, and they differ on whether on-site reprocessing is part of the first plant. Last checked 23 Oct 2026. First American Nuclear announces Indiana EAGL-1 energy park plan; First American Nuclear FAQ
    What would change this

    A license application or FANCO statement fixing used-fuel management for the Indiana energy park. Next recheck due .

Evidence dates

(5 of 10 sources with a publication or document date)
Latest dated listed source publication: First American Nuclear: regulatory engagement plan submitted for EAGL-1: 15 Apr 2026.Latest dated recorded event: First American Nuclear and Indiana announce an EAGL-1 energy park plan: 4 Nov 2025.5 of 10 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(10)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: First American Nuclear EAGL-1 energy park in Indiana (site not disclosed) — https://smrmap.com/projects/fanco-eagl1-indiana/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “First American Nuclear EAGL-1 energy park in Indiana (site not disclosed)”. Record reviewed 11 Oct 2026. https://smrmap.com/projects/fanco-eagl1-indiana/ (accessed [date]).

“Record reviewed” is the record review date; the evidence review, individual sources and later additions keep their own dates. Add the date you read the page; save a PDF if you need a copy of it.