Projects / United States · Announced
Hyperion / Gen4 Module proposal at Savannah River Site (2012)
Hyperion Power Generation (renamed Gen4 Energy) proposed in March 2012 a first Hyperion reactor (25 MWe, 70 MWt) at the Savannah River Site, a proposal now recorded as historical.
Current status
- How current
- General record check . Bounded evidence review . 1 of 3 listed sources has a publication or document date recorded here: 24 Sep 2024. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Lead-cooled fast reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
It signed a memorandum of agreement with DOE-Savannah River and announced a commitment to deploy the reactor at the site. DatacenterDynamics reported in September 2024 that the proposed Hyperion and NuScale reactors never arrived. That report does not establish formal cancellation or whether the planned land-use and site-services agreements were executed. No license application or construction is documented.
Key facts
- Design
- G4M (SMR)
- Technology
- Lead-cooled fast reactor (LFR) · lead bismuth
- Operator(s)
- Not recorded
- Vendor for linked design
- Gen4 Energy Inc.
- Location
- Savannah River Site · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Reservation point from the Wikipedia article for the Savannah River Site; DOE's 2012 agreements name the site but no plot on the 310-square-mile reservation, so this marks the reservation area (Hanford and Portsmouth precedent), shared by the three 2012 proposals. - Coordinates
- 33.25, -81.65 · site-area point (approximate)
- Electrical capacity
- 25 MWe (gross/net unspecified) · scope: module
- Thermal capacity
- 70 MWth (nameplate; basis unspecified)
- Inclusion basis
- Earlier-plan record (historical SMR program)
- Confidence
- medium
- Record reviewed
- 2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Hyperion / Gen4 Module proposal at Savannah River Site (2012) is recorded at Savannah River Site, South Carolina, United States. Operator: No operator is recorded. Recorded vendor: Gen4 Energy Inc.. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Holtec SMR-160 proposal at Savannah River Site (2012), NuScale plant proposal at Savannah River Site (2012).
Coordinate source: Wikipedia: Savannah River Site (article coordinates), Article coordinate 33.25, -81.65 on 'Savannah River Site', read 30 October 2026
Recorded electrical output is 25 MWe (gross/net unspecified), scope module. Modules planned: 1. Recorded thermal output is 70 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerGen4 Energy Inc. · source
- Reactor supplier
- Vendor for the linked designGen4 Energy Inc.
- Fuel
- Fuel form stated for G4M (catalog profile as of 1 Jun 2024)Uranium nitride
Gen4 Energy's 5 March 2012 page says the Hyperion Power Module's design intent is uranium nitride fuel with a ten-year core life and no on-site refuelling. That is a design specification. Neither it nor the Department of Energy's 2 March 2012 notice names a fuel manufacturer, quantity or delivery for the Savannah River reactor. Gen4 Energy (formerly Hyperion): plans to deploy an advanced reactor at Savannah River
Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
- Customer or offtaker
Gen4 Energy's 5 March 2012 page and the Department of Energy's 2 March 2012 notice name no buyer of power from the first Hyperion reactor at Savannah River. The page lists classes of possible users, such as remote mines, oil and gas operations, government complexes and islands, which is design marketing, not an offtake, and the site is the deployment location rather than a stated buyer. Gen4 Energy (formerly Hyperion): plans to deploy an advanced reactor at Savannah River
- Contractor
The Department of Energy's 2 March 2012 notice and Gen4 Energy's 5 March 2012 page describe a memorandum of agreement between Hyperion and the site host, DOE-Savannah River with Savannah River National Laboratory, setting next steps towards land-use, site-services and technical-assistance agreements and NRC licensing. No such agreement, engineering contractor or construction contractor is named. Los Alamos National Laboratory is described as Hyperion's design collaborator generally, not for this site. DOE: Energy Department announces small modular reactor technology partnerships at Savannah River; Gen4 Energy (formerly Hyperion): plans to deploy an advanced reactor at Savannah River
- Funding and government decisions
Gen4 Energy's 5 March 2012 page describes the first Savannah River Hyperion reactor as privately funded, and the Department of Energy's 2 March 2012 notice says the siting memorandums are not a federal funding commitment. Neither names a funder, investor or amount for this reactor, and the notice's other sums concern Vogtle, AP1000 licensing and university grants. Gen4 Energy (formerly Hyperion): plans to deploy an advanced reactor at Savannah River; DOE: Energy Department announces small modular reactor technology partnerships at Savannah River
- Comparable schedule revision
Comparable schedule revision not established. The Department of Energy's 2 March 2012 notice and Gen4 Energy's 5 March 2012 page describe the same memorandum and say the parties would work towards target dates for later agreements, but print no construction or operation date. With no dated target, no schedule revision is shown. DOE: Energy Department announces small modular reactor technology partnerships at Savannah River; Gen4 Energy (formerly Hyperion): plans to deploy an advanced reactor at Savannah River
Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(5 notes, 1 not yet reviewed)
- Evidence review. Gen4 Energy's page, posted 5 March 2012, says Hyperion Power Generation, the Department of Energy Savannah River, and Savannah River National Laboratory committed to deploy a privately funded first Hyperion reactor at the Savannah River Site under a memorandum of agreement. The same page says the Hyperion Power Module design intent is 25 megawatts electric, uranium nitride fuel and lead-bismuth coolant. DOE's 2 March 2012 notice lists Hyperion as one of three potential-siting memorandums and says they are not a federal funding commitment. No plot, license or later cancellation is in these pages. The Holtec and NuScale memorandums are other proposals. The design identifier already on the record is used only as the existing link; no ARIS text or ARIS parameter is added. Last checked 19 Oct 2026. Gen4 Energy (formerly Hyperion): plans to deploy an advanced reactor at Savannah River; DOE: Energy Department announces small modular reactor technology partnerships at Savannah River
What would change this
A Gen4, Hyperion or DOE record naming a Savannah River parcel or ending this memorandum would change this record. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed: Not disclosed in the reviewed evidence. The pages name the Savannah River Site. They do not name a plot. DOE calls the subject potential siting. Last checked 19 Oct 2026. Gen4 Energy (formerly Hyperion): plans to deploy an advanced reactor at Savannah River; DOE: Energy Department announces small modular reactor technology partnerships at Savannah River
What would change this
A site-services agreement naming a parcel would settle the site. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites: Not disclosed in the reviewed evidence. DatacenterDynamics reported on 24 September 2024, when DOE was seeking new clean-energy projects at Savannah River, that the Hyperion Power Generation and NuScale SMRs announced in 2012 never arrived, although DOE completed an SMR siting study. The report identifies no next step for the Hyperion proposal. It does not establish whether the targeted land-use or site-services agreements were executed, and no formal cancellation notice was found. Last checked 23 Oct 2026. DOE looks for clean energy projects at Savannah River, South Carolina; could include data centers and SMRs
What would change this
A Gen4 Energy or DOE-Savannah River record formally ending the 2012 agreement, or a revived Hyperion/Gen4 proposal. Next scheduled check: 23 Apr 2027.
- Permissions and public process. Gen4 Energy's 5 March 2012 release says its memorandum of agreement with DOE-Savannah River and the site's national laboratory set next steps toward deployment, including target dates for land-use, site-services and technical-assistance agreements, with licensing to be done under NRC authority. DOE's March 2012 release describes the agreement as a framework. Neither records an NRC application or license for a Hyperion reactor at Savannah River. Last checked 23 Oct 2026. Gen4 Energy (formerly Hyperion): plans to deploy an advanced reactor at Savannah River; DOE: Energy Department announces small modular reactor technology partnerships at Savannah River
What would change this
A record of an NRC filing for a Hyperion/Gen4 module at Savannah River. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). Gen4 Energy's March 2012 release says the Savannah River agreement set work toward target dates for land-use and site-services agreements, and its CEO called it securing a first site. DOE's release describes the agreements as a framework for developing such arrangements. No executed land-use agreement, specific location or grid arrangement is recorded in these sources. Last checked 23 Oct 2026. Gen4 Energy (formerly Hyperion): plans to deploy an advanced reactor at Savannah River
What would change this
A record of an executed land-use agreement for a Hyperion module at Savannah River. Next scheduled check: 23 Apr 2027.
Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.
Evidence dates
(1 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- DOE: Energy Department announces small modular reactor technology partnerships at Savannah River (government, accessed 2 Oct 2026)
- Gen4 Energy (formerly Hyperion): plans to deploy an advanced reactor at Savannah River (company, accessed 2 Oct 2026)
- DOE looks for clean energy projects at Savannah River, South Carolina; could include data centers and SMRs (news report, published 24 Sep 2024, accessed 23 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Hyperion / Gen4 Module proposal at Savannah River Site (2012) — https://smrmap.com/projects/hyperion-srs-2012/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Hyperion / Gen4 Module proposal at Savannah River Site (2012)”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/hyperion-srs-2012/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.