Projects / United States · Announced
Holtec SMR-160 proposal at Savannah River Site (2012)
Holtec's SMR-160 at the Savannah River Site is a historical proposal from March 2012.
Current status
- How current
- General record check . Bounded evidence review . 1 of 3 listed sources has a publication or document date recorded here: 5 Mar 2012. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 2 tracked. Separately: 2 earlier-plan records. 96 tracked at announced across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Pressurized water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
In March 2012 Holtec's SMR, LLC signed a memorandum of agreement with DOE-Savannah River to situate its first 160 MWe SMR-160 at the site. No license application or construction is documented; cancellation is not inferred.
Key facts
- Design
- Holtec SMR-160 (SMR)
- Technology
- Pressurized water reactor (PWR) · light water. The IAEA's 2016 SMR booklet lists the SMR-160 among integral designs, but its 2020 edition describes a steam generator joined to the reactor vessel by a single connection; with these conflicting descriptions, the type is recorded as a pressurized water reactor without an integral claim.
- Operator(s)
- Not recorded
- Vendor for linked design
- Holtec International
- Location
- Savannah River Site · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Reservation point from the Wikipedia article for the Savannah River Site; DOE's 2012 agreements name the site but no plot on the 310-square-mile reservation, so this marks the reservation area (Hanford and Portsmouth precedent), shared by the three 2012 proposals. - Coordinates
- 33.25, -81.65 · site-area point (approximate)
- Electrical capacity
- 160 MWe (gross/net unspecified) · scope: module
- Thermal capacity
- Not recorded
- Inclusion basis
- Earlier-plan record (historical SMR program)
- Confidence
- medium
- Record reviewed
- 2 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Holtec SMR-160 proposal at Savannah River Site (2012) is recorded at Savannah River Site, South Carolina, United States. Operator: No operator is recorded. Recorded vendor: Holtec International. Stage: Announced. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Hyperion / Gen4 Module proposal at Savannah River Site (2012), NuScale plant proposal at Savannah River Site (2012).
Coordinate source: Wikipedia: Savannah River Site (article coordinates), Article coordinate 33.25, -81.65 on 'Savannah River Site', read 30 October 2026
Recorded electrical output is 160 MWe (gross/net unspecified), scope module. Modules planned: 1. Thermal output is not recorded on this project. The linked design record states 525 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerSMR, LLC (Holtec) · source
- Reactor supplier
- Vendor for the linked designHoltec International
- Fuel
- Fuel form stated for Holtec SMR-160UO2 pellet / square array
SMR, LLC's 12 July 2012 item says Holtec extended the SMR-160 core's cycle between refuellings to nearly four years, which is a design change. Neither it nor the Department of Energy's 2 March 2012 notice names a fuel manufacturer, allocation or delivery for a Savannah River SMR-160. SMR, LLC (Holtec): MOA to situate first SMR-160 at Savannah River Site
Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
- Customer or offtaker
The Department of Energy's 2 March 2012 notice and SMR, LLC's 2012 press-release index name no buyer of power from an SMR-160 at Savannah River. A June 2012 press conference listing state officials and SCE&G and AREVA executives as speakers does not say anyone agreed to buy power, and the site itself is not stated as an offtaker. SMR, LLC (Holtec): MOA to situate first SMR-160 at Savannah River Site
- Contractor
The Department of Energy's 2 March 2012 notice and SMR, LLC's 5 March 2012 item describe a memorandum of agreement between Holtec's SMR, LLC and the site host, DOE-Savannah River with Savannah River National Laboratory, to provide siting information and a framework for later land-use and site-services agreements. No engineering, licensing or construction contractor is named, and the item headline's 'protocol to build' is not a construction contract. DOE: Energy Department announces small modular reactor technology partnerships at Savannah River; SMR, LLC (Holtec): MOA to situate first SMR-160 at Savannah River Site
- Funding and government decisions
SMR, LLC's 2012 press index says the company partnered with NuHub in May 2012 to compete for a DOE grant for SMR-160 deployment in South Carolina and applied to the DOE small modular reactor funding announcement, which sought to award $452 million in total to two companies. Its 21 November 2012 item says DOE made only one award at that time. No award or payment to this proposal is stated, and DOE's 2 March 2012 notice says the siting memorandums were not a federal funding commitment. SMR, LLC (Holtec): MOA to situate first SMR-160 at Savannah River Site; DOE: Energy Department announces small modular reactor technology partnerships at Savannah River
- Comparable schedule revision
Comparable schedule revision not established. The Department of Energy's 2 March 2012 notice and SMR, LLC's 2012 press index date the siting memorandum and later grant, design and award items, but none states a construction or operation date for a Savannah River SMR-160. With no dated target, no schedule revision is shown. DOE: Energy Department announces small modular reactor technology partnerships at Savannah River; SMR, LLC (Holtec): MOA to situate first SMR-160 at Savannah River Site
Not recorded in SMRMap's reviewed evidence (3): Operator or intended licensed owner; Site host or owner; Programs and agreements naming the project
- Operator or intended licensed owner
- Site host or owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Assessments of the design (not of this site)
(1)
- CNSC vendor design review, Phase 1 (SMR-160) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · CNSC · completed Aug 2020
CNSC lists Phase 1 of its pre-licensing vendor design review of the SMR-160 by SMR, LLC (Holtec International) among completed reviews, with an executive summary dated August 2020. No later phase is listed. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
Sources: CNSC: vendor design review service agreements and completed reviews
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(5 notes, 1 not yet reviewed)
- Evidence review. The Department of Energy said on 2 March 2012 that Savannah River had entered memorandums with Hyperion, SMR, LLC (a Holtec subsidiary), and NuScale for information on potential SMR siting. The memorandums were not a federal funding commitment. Holtec's SMR, LLC page dates its own memorandum 5 March 2012 and says it was executed to situate the company's first 160 megawatt-electric SMR-160 at the Savannah River Site. No plot inside the site, license application or later cancellation is in these pages. The Hyperion and NuScale agreements on the DOE page are other proposals. Last checked 19 Oct 2026. DOE: Energy Department announces small modular reactor technology partnerships at Savannah River; SMR, LLC (Holtec): MOA to situate first SMR-160 at Savannah River Site
What would change this
A Holtec or DOE record that either selects a plot at Savannah River for the SMR-160 or records that the 2012 memorandum ended would change this record. Next scheduled check: 19 Jan 2027.
- Site location recorded as disclosed: Not disclosed in the reviewed evidence. Both pages name the Savannah River Site and facilities near Aiken. Neither names a plot inside the site. DOE describes potential siting information, not a selected parcel. Last checked 19 Oct 2026. DOE: Energy Department announces small modular reactor technology partnerships at Savannah River; SMR, LLC (Holtec): MOA to situate first SMR-160 at Savannah River Site
What would change this
A land-use or site-services agreement naming a parcel would settle the site. Next scheduled check: 19 Jan 2027.
- Permissions and public process. DOE's 2 March 2012 release says DOE, Savannah River Site and its national laboratory signed a memorandum of agreement with Holtec's SMR, LLC to help it obtain siting information and to provide a framework for land-use and site-services agreements. SMR, LLC's news page says it applied for DOE's 2012 SMR funding in May 2012 and that DOE made only one award in November 2012. A memorandum of agreement is not a permit, and the sources read record no NRC application for an SMR-160 at Savannah River. Last checked 23 Oct 2026. DOE: Energy Department announces small modular reactor technology partnerships at Savannah River; SMR, LLC (Holtec): MOA to situate first SMR-160 at Savannah River Site
What would change this
A record of an NRC filing for an SMR-160 at Savannah River. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). DOE's March 2012 release says the Savannah River memorandum of agreement with Holtec's SMR, LLC would help it obtain information on potential reactor siting and provide a framework for developing land-use and site-services agreements, using the site's land, energy facilities and nuclear expertise. That is a framework for future agreements; no land-use or site-services agreement, specific location or grid arrangement is recorded in the sources read. Last checked 23 Oct 2026. DOE: Energy Department announces small modular reactor technology partnerships at Savannah River
What would change this
A record of an executed land-use or site-services agreement for an SMR-160 at Savannah River. Next scheduled check: 23 Apr 2027.
- Next decision and prerequisites. Holtec's March 2012 release says it had begun working with DOE-Savannah River and Savannah River National Laboratory to evaluate and identify preferred construction sites at the Savannah River Site for the SMR-160, and the Department of Energy's 2 March 2012 notice calls the agreement a framework for developing land-use and site-services agreements. Those were the next steps stated in 2012. The sources reviewed record no selected site, land-use agreement, NRC application or later statement on this plan, so whether the steps happened is not recorded. Last checked 23 Oct 2026. DOE, Its South Carolina Entities, and Holtec Sign the Protocol to Build the Company's Small Modular Reactor at the Savannah River Site; DOE: Energy Department announces small modular reactor technology partnerships at Savannah River
What would change this
A DOE-Savannah River or Holtec statement on whether a site was selected or a land-use or site-services agreement signed for an SMR-160 at Savannah River, or that the 2012 agreement ended. Next scheduled check: 23 Apr 2027.
Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.
Evidence dates
(1 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- DOE: Energy Department announces small modular reactor technology partnerships at Savannah River (government, accessed 2 Oct 2026)
- SMR, LLC (Holtec): MOA to situate first SMR-160 at Savannah River Site (company, accessed 2 Oct 2026)
- DOE, Its South Carolina Entities, and Holtec Sign the Protocol to Build the Company's Small Modular Reactor at the Savannah River Site (company, published 5 Mar 2012, accessed 23 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Holtec SMR-160 proposal at Savannah River Site (2012) — https://smrmap.com/projects/holtec-smr-160-srs-2012/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Holtec SMR-160 proposal at Savannah River Site (2012)”. Record reviewed 2 Oct 2026. Data fingerprint ee4d3854cfaa29a74e5f3d1b06467a050a149754ff4e29a386fab03eb267b850; build 2026-11-18. https://smrmap.com/projects/holtec-smr-160-srs-2012/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.