Projects / United States · Operating
Valar Atomics Ward 250
Research reactor at the Utah San Rafael Energy Research Center in Orangeville, Emery County.
Current status
- How current
- General record check . Bounded evidence review . 5 of 11 listed sources have a publication or document date recorded here; the newest is 19 Jun 2026. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: DOE categorical exclusion CX-271015 for the Ward250 research reactor (22 Apr 2026). All permissions and applications
- Latest development
- 2 Jul 2026 · Electricity generation: Ward 250 reaches 100 kW thermal with electricity generation (DOE update). DOE's Reactor Pilot Program update of July 2026 lists 2 July 2026 as the day Ward 250 achieved full power of 100 kW thermal, with electricity generation. Source: DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212). Updates entry
More on this development
Valar's own statement dates electricity generation to 1 July 2026. The 250 kW thermal rating stored for this reactor comes from DOE's categorical exclusion; the update's full-power figure is 100 kW thermal.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- The mapped point is not an exact surveyed coordinate.
- Expected for this stage but not recorded as a structured fact: Permission evidence appropriate to stage. A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- High-temperature gas-cooled reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
DOE categorical exclusion CX-271015, identification DOE-ID-26-005, was signed on 22 Apr 2026 and describes Ward250 as a 250 kWth high-temperature gas-cooled reactor using TRISO fuel, helium coolant, and graphite moderator and reflector. The determination says the facility will operate under DOE authorization, DOE later called it a DOE-authorized reactor, and Valar says it operates under that authorization; the determination states no authorization number and no electrical output. Electrical power supplied by USREL infrastructure is site power, not a finding that the reactor produces no electricity. Zero-power fueled criticality was reported on 18 Jun 2026. Valar states that the reactor generated electricity on 1 July 2026 and that the electricity directly powered an NVIDIA chip. DOE's Reactor Pilot Program update of July 2026 lists the documented safety analysis as approved on 23 April 2026 and full power of 100 kW thermal on 2 July 2026, with the electricity used to power an NVIDIA Spark. Both dates are kept. Neither statement is a grid connection or a stored electrical rating. It is a research reactor, not a commercial power plant. The IAEA's September 2026 microreactor outlook places Ward 250 at 0.100 to 0.250 MWth and 'Operation' and says it subsequently operated at full power and completed a pressurised loss-of-forced-cooling demonstration, without a date. The dated DOE presentation establishes a full-power demonstration and electricity generation, without a numerical electrical rating. The operating label records demonstrated experimental operation, not proof that the reactor is running continuously today. No commercial operation is inferred. DOE's environmental determination describes a 24-month research program of about 12 months of reactor operation, then six months of in-vessel cooldown and six months of decommissioning. Valar dates the groundbreaking to 17 September 2025 and says it built and now operates the reactor.
Key facts
- Design
- Ward 250 (Microreactor)
- Technology
- High-temperature gas-cooled reactor (HTGR) · helium
- Operator(s)
- Valar Atomics
- Vendor for linked design
- Valar Atomics
- Location
- Utah San Rafael Energy Lab · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Center of the map embedded on the lab's own About page, labeled 'San Rafael Energy Research Center' (39.2394, -111.0893). Lab-area point, not a surveyed reactor pad. Replaces an earlier road-centroid geocode. - Coordinates
- 39.2394, -111.0893 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: module
- Thermal capacity
- 0.25 MWth (nameplate; basis unspecified)
- Purpose
- Research or test reactor
- Construction start
- Not recorded
- Inclusion basis
- Labeled microreactor
- Confidence
- medium
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Valar Atomics Ward 250 is recorded at Utah San Rafael Energy Lab, Utah, United States. Operator: Valar Atomics. Recorded vendor: Valar Atomics. Stage: Operating. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Nuclea Morpheus test reactor siting at the Utah San Rafael Energy Lab, NuCube test microreactor at the Utah San Rafael Energy Lab.
Coordinate source: Utah San Rafael Energy Lab: about us (embedded map), Center of the map embedded on the lab's About page, labeled 'San Rafael Energy Research Center' (39.2394, -111.0893)
Electrical output is not recorded on this project. Modules planned: 1. Recorded thermal output is 0.25 MWth (nameplate; basis unspecified).
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Operator or intended licensed owner
- OperatorValar Atomics
- Reactor supplier
- Vendor for the linked designValar Atomics
- Contractor
- Construction contractorKiewit Nuclear Solutions Co. · sourceReported as the project's engineering, procurement and construction contractor (POWER, 19 June 2026).
Source-backed project statement
The Utah Office of Energy Development's 17 September 2025 groundbreaking release, as published by ETV News, says Valar chose Kiewit for engineering and construction, Goree for architecture and design, and Sprung for the building. POWER reported on 19 June 2026 that Kiewit Nuclear Solutions served as the engineering, procurement and construction contractor. The reactor has since operated. These are construction roles, not a later operating contract. Valar Atomics site groundbreaking reported by ETV News; POWER: Valar Atomics' Ward 250 becomes second reactor to go critical under DOE pilot program
- Funding and government decisions
- Listed under a government program; not a disbursement; in effectDOE Reactor Pilot Program · sourceDOE lists this reactor's criticality demonstration under the Reactor Pilot Program.
DOE's 18 June 2026 article and the 17 September 2025 groundbreaking release say Ward 250 was selected for the Reactor Pilot Program and later reached criticality under it. The 22 April 2026 environmental determination describes the research program and states no sum of money. Selection and official support are participation, not project money paid. Valar Atomics site groundbreaking reported by ETV News; DOE: Valar Atomics Ward 250 criticality; DOE categorical exclusion CX-271015 PDF: Ward250 research reactor
- Fuel
- Fuel form stated for Ward 250TRISO coated particle fuel
- Enrichment stated for Ward 25019.75 wt%
DOE's 22 April 2026 determination says Ward 250 uses TRISO coated particle fuel, and POWER reported on 19 June 2026 that a co-located fabrication facility is designed to make such fuel. POWER also said fuel-sourcing details were not yet available. A fuel form and a described fabrication facility are not a named supplier or a delivery. DOE categorical exclusion CX-271015 PDF: Ward250 research reactor; POWER: Valar Atomics' Ward 250 becomes second reactor to go critical under DOE pilot program
- Programs and agreements naming the project
- Government program; activeDOE Reactor Pilot Program (DOE-authorized advanced test reactors)
Not found in the sources we checked (2): Customer or offtaker; Comparable schedule revision
- Customer or offtaker
Valar's Castle Country page says Ward 250 is a research reactor whose job is to test and validate, and that on 1 July 2026 it generated electricity in a live demonstration that directly powered an NVIDIA chip. DOE's 18 June 2026 article describes that reactor's zero-power criticality under the Reactor Pilot Program at the Utah San Rafael Energy Lab. Neither source names a buyer or a research-service agreement; the chip demonstration is not an offtake. Valar Atomics: Castle Country and Ward 250; DOE: Valar Atomics Ward 250 criticality
- Comparable schedule revision
Comparable schedule revision not established. The 17 September 2025 state release says the Reactor Pilot Program aimed for criticality of three reactors by 4 July 2026, and DOE reported Ward 250's criticality on 18 June 2026. Meeting that program aim is performance against a target. No source read states an earlier and a later forecast for the same Ward 250 milestone. Valar Atomics site groundbreaking reported by ETV News; DOE: Valar Atomics Ward 250 criticality
Not recorded in SMRMap's reviewed evidence (2): Project proposer or applicant; Site host or owner
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Site host or owner
Timeline
Recorded developments
- · Electricity generation
Ward 250 reaches 100 kW thermal with electricity generation (DOE update) - · Electricity generation
Ward 250 first electricity - · Recorded development
Ward 250 passive-safety demonstration: shutdown with all active cooling off and simulated total loss of power - · First criticality
Ward 250 zero-power criticality - · Recorded development
DOE approves the Ward 250 documented safety analysis
Earlier developments (5)
- · Environmental decision recorded
Environmental decision recorded: DOE categorical exclusion CX-271015 for the Ward250 research reactor - · Recorded development
Operation Windlord: Ward 250 modules airlifted by C-17 to Hill AFB, then trucked to Emery County - · Recorded development
DOE approves the Ward 250 preliminary documented safety analysis - · Recorded development
Project Nova: Valar zero-power test core operated by Los Alamos at NCERC (Nevada) - Groundbreaking · Groundbreaking
Valar breaks ground on Ward 250 at the Utah San Rafael Energy Lab
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Environmental decision
- DOE categorical exclusion CX-271015 for the Ward250 research reactor
Environmental decision · Issued / approved · U.S. Department of Energy, Office of Nuclear Energy · decided 22 Apr 2026
Signed 22 April 2026 under NEPA identification DOE-ID-26-005. Determines that the 250 kWth Ward250 research reactor at USREL fits a categorical exclusion. It states no authorization number and no electrical output, and it does not confirm the company's later electricity claim.
Sources: DOE categorical exclusion CX-271015 PDF: Ward250 research reactor
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(8 notes)
- Evidence review. Ward 250 is Valar Atomics' research reactor at the Utah San Rafael Energy Research Center (USREL) in Orangeville, Emery County, Utah. USREL is a state-operated energy research facility. DOE's NEPA determination DOE-ID-26-005, signed 22 April 2026, describes a 250 kWth helium-cooled, graphite-moderated HTGR using TRISO fuel, operating under DOE authorization. It plans a 24-month research program: about 12 months of operation, six months of in-vessel cooldown and six months of decommissioning. It says construction stayed within the existing site with minimal excavation. Valar dates the groundbreaking to 17 September 2025. Kiewit was named as engineering and construction firm (ETV News, 17 September 2025). The reactor modules were factory-built and airlifted. No separate nuclear-construction milestone is dated. DOE's July 2026 slides list the preliminary documented safety analysis as approved in February 2026 and the documented safety analysis on 23 April 2026. They give zero-power criticality on 18 June 2026 and full power of 100 kWt, with electricity powering an NVIDIA Spark, on 2 July 2026. DOE's 18 June release calls it the first DOE-authorized reactor built outside a national laboratory. Valar says it built and operates the reactor, completed an operational readiness review, and demonstrated passive cooling after shutdown on 26 June 2026. It dates first electricity to 1 July 2026. The 1 and 2 July dates are both kept. The IAEA's September 2026 microreactor booklet says Ward-250 operated at full power after criticality and completed a loss-of-forced-cooling demonstration. Criticality, full power and electricity generation are separate milestones here. There is no grid connection, no electrical rating and no commercial service. Valar calls it a research reactor, not a commercial power plant. DOE's slides list further higher-power demonstrations in 2026 to 2027 at locations to be decided. Output: the stored 250 kWth follows the DOE determination, while DOE's slides call 100 kWt full power. The difference is unresolved, and no DOE authorization instrument has been opened. Last checked 19 Oct 2026. DOE categorical exclusion CX-271015 PDF: Ward250 research reactor; DOE: Valar Atomics Ward 250 criticality; DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); Valar Atomics: Castle Country and Ward 250; Valar Atomics: Ward 250 page; Valar Atomics site groundbreaking reported by ETV News; IAEA: Microreactors: Advances in Technology Development (2026 Outlook), IAEA/PAT/016
What would change this
A DOE or Valar notice of the end of Ward 250 operations, the start of cooldown or decommissioning, or a DOE authorization or determination for higher-power tests. Next scheduled check: 19 Jan 2027.
- Construction start evidence. Valar dates the Ward 250 groundbreaking to 17 September 2025, matching ETV News's dateline. DOE's April 2026 determination says construction was confined to the existing USREL site with minimal excavation. This resolves the earlier 17 versus 11 September question in favor of 17 September. Last checked 18 Oct 2026. Valar Atomics: Ward 250 page; DOE categorical exclusion CX-271015 PDF: Ward250 research reactor
What would change this
A Utah Office of Energy Development record giving a different date. Next scheduled check: 18 Jan 2027.
- Permission evidence appropriate to stage. Ward 250 operates under DOE authorization, not an NRC operating license. DOE's 18 June 2026 release calls it the first DOE-authorized reactor built outside a national laboratory, and DOE's environmental determination DOE-ID-26-005 (signed 22 April 2026) says the facility will operate under DOE authorization; both were re-read on 13 November 2026. DOE's July 2026 slides list the preliminary safety analysis as approved in February 2026 and the documented safety analysis on 23 April 2026, and Valar says it completed an operational readiness review; both are carried from the 19 October 2026 review. No DOE authorization-to-operate instrument or safety-analysis approval letter was found among the sources read, so no operating-authority record is stored; whether DOE publishes these instruments is not established. Last checked 13 Nov 2026. DOE: Valar Atomics Ward 250 criticality; DOE categorical exclusion CX-271015 PDF: Ward250 research reactor; DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); Valar Atomics: Castle Country and Ward 250
What would change this
DOE publishes the Ward 250 DSA approval or authorization to operate, or a determination for higher-power tests. Next scheduled check: 12 Feb 2027.
- Electricity generation or commercial service evidence. DOE's July 2026 update reports full power of 100 kW thermal on 2 July 2026, with the electricity used to power an NVIDIA Spark. Valar says the reactor first generated electricity on 1 July 2026. No electrical rating, grid connection or commercial service is stated. It is a research reactor, and DOE's determination plans about 12 months of operation. Last checked 18 Oct 2026. DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212); Valar Atomics: Castle Country and Ward 250
What would change this
DOE or Valar reports the end of operations, cooldown or decommissioning, or higher-power tests. Next scheduled check: 18 Jan 2027.
- Next decision and prerequisites. The 22 April 2026 determination describes a 24-month research program of about 12 months of operation, then six months of in-vessel cooldown and six months of decommissioning under DOE requirements. DOE reported criticality on 18 June 2026 and Valar reported first electricity on 1 July 2026, so operation has started. No further license decision is named; the next stated change is the end of the research mission and decommissioning. Last checked 23 Oct 2026. DOE categorical exclusion CX-271015 PDF: Ward250 research reactor; DOE: Valar Atomics Ward 250 criticality; Valar Atomics: Castle Country and Ward 250
What would change this
A DOE decision ending the Ward 250 research mission or authorizing decommissioning. Next scheduled check: 21 Jan 2027.
- Permissions and public process. DOE's determination DOE-ID-26-005, signed 22 April 2026, categorically excluded the Ward 250 research reactor from further NEPA review. That is an environmental decision, not an operating authorization. DOE's 18 June 2026 article calls the criticality the first DOE-authorized reactor built outside a national laboratory, and Valar says the reactor operates under DOE authorization with approved safety documentation. The texts do not quote an authorization number or a Nuclear Regulatory Commission license. Last checked 23 Oct 2026. DOE categorical exclusion CX-271015 PDF: Ward250 research reactor; DOE: Valar Atomics Ward 250 criticality; Valar Atomics: Castle Country and Ward 250
What would change this
A published DOE authorization instrument for Ward 250, including its number and scope. Next scheduled check: 21 Jan 2027.
- Site dependencies (land, grid, water). The 22 April 2026 determination places Ward 250 at the existing state-operated Utah San Rafael Energy Research Center in Orangeville and says land disturbance stays on that site. It also says domestic water use is under 1000 gallons a day and that electrical power comes from the center's infrastructure. No lease, grid-export agreement or named water right is stated; the water and power sentences describe host-site utilities. Last checked 23 Oct 2026. DOE categorical exclusion CX-271015 PDF: Ward250 research reactor
What would change this
A lease, grid-export agreement or water-right instrument for the Ward 250 site. Next scheduled check: 21 Jan 2027.
- Spent fuel, waste and closure. The 22 April 2026 determination says spent fuel will be transferred to dry storage for transport to a DOE-approved facility, solid radioactive waste will go to a licensed disposal facility, and decommissioning will return the site to unrestricted use. It does not name the receiving facilities or a waste contract. The path is the action DOE reviewed, not a shown contract. Last checked 23 Oct 2026. DOE categorical exclusion CX-271015 PDF: Ward250 research reactor
What would change this
A named receiving facility or waste contract for Ward 250 spent fuel. Next scheduled check: 21 Jan 2027.
Evidence dates
(5 of 11 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(11)
- DOE: Valar Atomics Ward 250 criticality (government, published 18 Jun 2026, accessed 1 Oct 2026)
- Utah San Rafael Energy Lab about page (government, accessed 1 Oct 2026)
- DOE EM note on four Reactor Pilot criticality reviews (government, accessed 1 Oct 2026)
- DOE celebrates second advanced reactor achieving criticality (government, published 18 Jun 2026, accessed 2 Oct 2026)
- Valar Atomics: Castle Country and Ward 250 (company, accessed 15 Oct 2026)
- DOE categorical exclusion CX-271015 PDF: Ward250 research reactor (government, dated 22 Apr 2026, accessed 4 Oct 2026)
- DOE Office of Nuclear Energy: Reactor Pilot Program Update, slides filed with the NRC (ADAMS ML26198A212) (government, accessed 15 Oct 2026)
- IAEA: Microreactors: Advances in Technology Development (2026 Outlook), IAEA/PAT/016 (IAEA/NEA, accessed 6 Oct 2026)
- Valar Atomics site groundbreaking reported by ETV News (news report, published 17 Sep 2025, accessed 17 Oct 2026)
- Valar Atomics: Ward 250 page (company, accessed 18 Oct 2026)
- POWER: Valar Atomics' Ward 250 becomes second reactor to go critical under DOE pilot program (news report, published 19 Jun 2026, accessed 21 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Valar Atomics Ward 250 — https://smrmap.com/projects/valar-ward-250/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Valar Atomics Ward 250”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/valar-ward-250/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.