Designs

Holtec SMR-300

Holtec light-water SMR, about 300 MWe, proposed for the Palisades-area deployment. ONR's Holtec page, as read on 5 October 2026, says the UK reactor-design assessment was completed in March 2026 after Step 1 (October 2023 to August 2024) and Step 2 (August 2024 to March 2026). A Step 2 GDA statement was issued. The page does not record Step 3 or a Design Acceptance Confirmation. A completed Step 2 assessment is not permission for any site. ONR’s Step 2 reports describe a UK configuration targeting 320 MWe per reactor from 1,050 MWth; the electrical figure’s gross/net basis is unspecified. The turbine and steam-system modification increasing the target from 300 to 320 MWe was outside GDA scope and was not assessed by ONR. These figures do not replace the profile’s recorded 300 MWe net per-module rating or linked projects’ separately sourced ratings.

Reactor type
Pressurized water reactor. How it works, with a 3D view.
Projects
Licensing: Holtec Pioneer Units 1 and 2 (SMR-300 at Palisades). Furthest recorded stage of 5 using this design. Development status as stated: Detailed design.
Evidence
6 sources; first primary source: ONR, Holtec SMR-300 Generic Design Assessment. Record reviewed 13 Oct 2026.
Schematic of Rolls-Royce SMR, this type's example. On the left, a reactor vessel holds a core of fuel assemblies, with control rod drives above its head.
Schematic of Rolls-Royce SMR, this type's example.

Key facts

Class
SMR
Technology
Pressurized water reactor (PWR)
The 2024 SMR Technology Catalogue describes a two-loop pressurized water reactor, so no integral layout is recorded.
Coolant
Light water
Spectrum
Thermal
Developer / vendor(s)
Holtec International
Module electrical
300 MWe (net)
Fuel form
UO2 pellet / square array
Development status (as stated)
Detailed design
Inclusion basis
SMR by design class
Confidence
medium
Record reviewed
13 Oct 2026 (record review date, not proof of current availability or a deployment)

All fields

(1 without a known value)
Module thermal
Not recorded

Tracked deployment projects

Agreements naming this design (6)

Agreements, plans, studies and government programs whose sources name this design. They are not deployment projects.

Design sources

(6)

Evidence and open questions

(2 notes)
  • Evidence review. The 2024 SMR Technology Catalogue (third edition, June 2025) describes the SMR-300, developed by Holtec International, as a two-loop PWR with light water coolant and moderator, forced circulation by 2 pumps and 17x17 low-enriched UO2 fuel, rated 1050 MWth (nominal) with 366 MWe gross and 320 MWe net, primarily for electricity with optional cogeneration, and in 'Detailed Design' with construction planned by mid-2027 and commercial operation in 2030. ONR's SMR-300 GDA page names Holtec International as designer and records the UK reactor-design assessment as completed in March 2026 after Step 1 (October 2023 to August 2024) and Step 2 (August 2024 to March 2026); this is a design-stage instrument, not a site permission. The catalog milestones name Palisades as the FOAK site (the Palisades project), and the secondary EnergyNote 2026 map lists Holtec SMR-300 Palisades as 2 x 340 MWe with CP Part 1 filed December 31, 2025 and docketed February 27, 2026; no opened source names Oyster Creek, Blue Castle, Cottam or Brigham City. Stored vendor and light-water coolant stay; the stored 300 MWe net rating is not supported by any source that could be read when checked (catalog 320 MWe net, EnergyNote 340 MWe), no thermal rating is recorded, though the catalog gives 1050 MWth, and the thermal spectrum is not stated. The two attached ONR Step 2 DOCX reports were saved as raw DOCX binary, so their text could not be read or quoted. Last checked 19 Oct 2026. Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition); ONR, Holtec SMR-300 Generic Design Assessment; EnergyNote 2026 SMR licensing map
    What would change this

    The NRC's decision or safety evaluation on the Palisades SMR-300 construction permit application (Part 1), which would fix the licensed per-unit MWth/MWe and its basis; or a readable text extraction of the ONR Step 2 summary report. Next scheduled check: 19 Jan 2027.

  • Technology family. The 2024 SMR Technology Catalogue describes a two-loop pressurized water reactor, so no integral layout is recorded. Last checked 1 Nov 2026. Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition)
    What would change this

    A developer, regulator or IAEA document that states this design's primary-circuit layout. Next scheduled check: 1 Feb 2027.

Regulatory actions

(4)

Compare reviews and approvals across designs

Design assessment

  • Holtec SMR-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed 31 Mar 2026 · submitted Jan 2023
    Holtec submitted the design, then named SMR-160, to the UK government for entry into Generic Design Assessment in January 2023, according to the Environment Agency's Step 1 summary; it was renamed SMR-300 in January 2024. The UK regulators began a two-step Generic Design Assessment of Holtec's SMR-300 on 18 October 2023 at the government's request. Step 1 ran from October 2023 to August 2024 and Step 2 from August 2024 to March 2026. The Environment Agency records completing Step 2 on 31 March 2026, and ONR's page records the assessment as completed that month with no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
    Sources: Environment Agency: assessing new nuclear reactor designs; ONR, Holtec SMR-300 Generic Design Assessment; Environment Agency: GDA Step 1 of the Holtec SMR, statement of findings public summary

Construction applications and decisions

Environmental decision

Other applications and decisions

  • NRC exemption for specified Pioneer support-of-excavation walls before LWA — Holtec Pioneer Units 1 and 2 (SMR-300 at Palisades)
    Other regulatory action · Issued / approved · NRC · decided 28 Aug 2026 · docket 50-616, 50-617 · 91 FR 55628
    The NRC issued a narrow exemption on 28 August 2026 allowing specified permanent support-of-excavation walls at Pioneer Units 1 and 2 before a limited work authorization. The notice does not issue or commit to an LWA or construction permit. The exemption does not show that physical work began or authorize all construction.
    Sources: NRC exemption for specified Pioneer support-of-excavation walls