Projects / United States · Licensing
Holtec Pioneer Units 1 and 2 (SMR-300 at Palisades)
Holtec proposes two SMR-300 units, Pioneer 1 and 2, at the existing Palisades plant area in Michigan.
Current status
- How current
- General record check . Bounded evidence review . 11 of 21 listed sources have a publication or document date recorded here; the newest is 10 Nov 2026. Status not rechecked since then; the nightly status check covers this project.
Development and review dates
Newest recorded development . Next general check: . Next evidence or detail review: .
- Permissions
- Recorded: NRC exemption for specified Pioneer support-of-excavation walls before LWA (28 Aug 2026); NRC environmental assessment and FONSI for Pioneer excavation-wall exemption (25 Aug 2026). Under review: Pioneer Units 1 and 2 phased construction permit application (with limited work authorization request). An application under review is not a permit. All permissions and applications
- Latest development
- 30 Sep 2026 · Recorded development: Holtec says Pioneer safety analysis report completes permit application part 2. Holtec reported that the preliminary safety analysis report completed the second part of its phased construction-permit application for Pioneer Units 1 and 2. Source: Holtec: Major regulatory developments in the Palisades Pioneer Unit 1 & 2 program (30 September 2026); World Nuclear News: second part of construction permit application submitted for Pioneer SMRs (October 2026); NRC Pioneer Units 1 and 2 LWA page (page updated 30 Oct 2026); Federal Register 91 FR 72577 (10 Nov 2026): Pioneer Units 1 and 2, receipt of construction permit application (Part 2), first of four weekly notices (published 10 Nov 2026). Updates entry
More on this development
No limited work authorization or construction permit is recorded.
- Next dated milestone
- Planned step: 31 Dec 2026 (target). Applicant-requested date for LWA and 10 CFR 50.10(d) exemption issuance. This is not an achieved milestone. Source: Pioneer Units 1 and 2 application, General and Financial Information (ML25365A986).
- Selected limitations
- Thermal output is not recorded on this project.
- The mapped point is not an exact surveyed coordinate.
- Same design
- 5 tracked: 1 licensing, 4 announced. 19 tracked at licensing across all designs. Recorded stages, not proof of current activity.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Pressurized water reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
Holtec states the two units are designed to provide 680 MWe together, and the NRC describes each unit as approximately 340 MWe; neither says whether the figures are gross or net. The linked SMR-300 design record states 300 MWe net per module; the figures are kept separate. On 2 December 2025 DOE selected Holtec Government Services, LLC for up to $400 million in federal cost-shared funding (Holtec: 'valued at $400 million') to deploy two SMR-300 reactors at the Palisades site. SMR, LLC, acting for Palisades SMR, LLC, filed part of a construction-permit application, including a limited-work-authorization request, on 31 December 2025. The NRC accepted it for docketing in February 2026 and began weekly notices of receipt on 1 October 2026. An environmental assessment and finding of no significant impact for the requested excavation-wall exemption were available on 24 August 2026. On 28 August the NRC issued a narrow exemption allowing specified permanent support-of-excavation walls before an LWA. The environmental finding and exemption are not an LWA or construction permit; neither has been issued. They do not establish that physical work began. The NRC lists a draft safety evaluation report with information gaps as completed on 31 August 2026. Its page, updated 30 October 2026, lists the draft environmental impact statement's date as TBD, where it earlier showed a 31 October 2026 target. Its target dates are 31 January 2027 for an advanced safety evaluation report and 31 March 2027 for the final safety evaluation and environmental impact statements. These are review targets, not permissions. Holtec reported on 30 September 2026 that the preliminary safety analysis report, completing the second part of the application, had been submitted, and the NRC's notice of receipt (91 FR 72577, published 10 November 2026) confirms it received Part 2 on 30 September; the notice says the NRC staff was then undertaking its acceptance review, and no acceptance or docketing of Part 2 is recorded. The filing identifies Palisades SMR, LLC as intended licensed owner, Palisades Energy, LLC as expected future operator, Holtec Palisades, LLC as current site owner, and Hyundai Engineering & Construction through Hyundai America as planned general contractor. Neither the new units nor their intended owner or operator has an operating license for these units.
Key facts
- Design
- Holtec SMR-300 (SMR)
- Technology
- Pressurized water reactor (PWR) · light water. The 2024 SMR Technology Catalogue describes a two-loop pressurized water reactor, so no integral layout is recorded.
- Operator(s)
- Palisades Energy, LLC
- Vendor for linked design
- Holtec International
- Location
- Palisades Nuclear Plant area · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
NuclearChain reactors export point for the Palisades SMR-300 entry on the existing plant campus (CC BY 4.0, derived from GEM's Global Nuclear Power Tracker); not a confirmed as-built pin. - Coordinates
- 42.323, -86.3146 · site-area point (approximate)
- Electrical capacity
- 680 MWe (gross/net unspecified) · scope: plant
Holtec states the two Pioneer units are designed to provide 680 MWe together, and the NRC's January 2026 release describes each SMR-300 unit as approximately 340 MWe. - Thermal capacity
- Not recorded
- Inclusion basis
- SMR by design class
- Confidence
- high
- Record reviewed
- 18 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Holtec Pioneer Units 1 and 2 (SMR-300 at Palisades) is recorded at Palisades Nuclear Plant area, Michigan, United States. Operator: Palisades Energy, LLC. Recorded vendor: Holtec International. Stage: Licensing. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate).
Coordinate source: NuclearChain reactors.csv export (unit coordinates), NuclearChain reactors.csv row 'palisades-nuclear-power-plant-2' (42.323, -86.3146)
Recorded electrical output is 680 MWe (gross/net unspecified), scope plant. Holtec states the two Pioneer units are designed to provide 680 MWe together, and the NRC's January 2026 release describes each SMR-300 unit as approximately 340 MWe. Modules planned: 2. Thermal output is not recorded on this project. The linked design record states 300 MWe (net); the project figure is kept separate.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Project proposer or applicant
- Project proposerHoltec International · source
- Application filing entitySMR, LLC (Holtec) · source
- Operator or intended licensed owner
- OperatorPalisades Energy, LLC
- Intended licensed ownerPalisades SMR, LLC · source
- Reactor supplier
- Vendor for the linked designHoltec International
- Customer or offtaker
Source-backed project statement Holtec states that the power purchase agreements for the Palisades restart contain an option for Wolverine and Hoosier to buy power from additional SMR units at the site; no agreement to buy Pioneer 1 and 2 output is recorded. Holtec's release of 12 September 2023 says its power purchase agreement with Wolverine Power Cooperative (Hoosier Energy to purchase the balance of Palisades output) "also contains a contract expansion provision to include up to two small modular reactors (SMRs rated at 300 MWe each)" that Holtec intends to build and commission at the site. The applicant's December 2025 Environmental Report restates this as an option for Wolverine and Hoosier to purchase power from the additional SMRs, citing that 2023 release, describes Palisades SMR as a merchant generator, and says Holtec anticipates that Wolverine and/or Hoosier would engage in good faith negotiations to establish long-term power purchase agreements for Pioneer Units 1 and 2. DOE's 2 December 2025 release describes Holtec as pursuing the role of electricity merchant selling the power to near-by utilities and end-users. These are Holtec's statements of an option and an expectation, not a signed agreement to buy Pioneer 1 and 2 power. The restart agreements' own text was not reviewed, and no executed agreement, price, volume or term for the new units, and no exercise of the option, was found in the application, the Environmental Report, Holtec's 2023 release or DOE's release. This replaces the earlier not-disclosed note, which rested on the general and financial volume alone. Holtec and Wolverine Ink Historic Power Purchase Agreement for the Palisades Power Plant (12 Sep 2023); Pioneer Units 1 and 2 application, Enclosure III, Environmental Report (ML25365A988); DOE selects TVA and Holtec to advance deployment of US SMRs (2 Dec 2025)
- Contractor
- Planned construction contractorHyundai Engineering & Construction · source
Source-backed project statement
SMR, LLC's December 2025 construction-permit filing says Holtec has teamed with Hyundai Engineering & Construction to support site-specific engineering and balance-of-plant design and to serve, through Hyundai America, as general construction contractor for Pioneer 1 and 2; the Environmental Report adds that Hyundai Engineering & Construction "has been selected as the engineering and construction partner". DOE's December 2025 release describes Holtec as constructor "in partnership with Hyundai Engineering & Construction", and ANS (2 April 2026) reports the units are planned "in collaboration with" Hyundai Engineering & Construction and Mitsubishi Electric. The 30 September 2026 Part 2 transmittal says the Part 1 general and financial information is incorporated by reference. This is a planned appointment: no executed construction contract was found, and no construction permit or limited work authorization has been issued. The filing also names Framatome for fuel design and supply and Mitsubishi Electric for instrumentation and control platform integration as supply-chain vendors, and cites Sargent & Lundy analysis for transmission cost estimates. Pioneer Units 1 and 2 application, General and Financial Information (ML25365A986); Pioneer Units 1 and 2 application, Enclosure III, Environmental Report (ML25365A988); DOE selects TVA and Holtec to advance deployment of US SMRs (2 Dec 2025); Holtec hits milestones in Palisades restart, new reactor projects -- ANS / Nuclear Newswire; Holtec transmittal 300-USNRC-26018 of Part 2 of the Pioneer construction permit application (ML26273A417)
- Funding and government decisions
- Funder or lender named for this projectHoltec International · sourcePlans to fund the private share, expected to be $400 million, of the DOE cost-shared funding for which the project was selected (award agreement not finalized), per the Dec 2025 permit application.
- Public award or selection; not a disbursement; selected — award terms not recorded as finalGen III+ SMR selection: Holtec (Palisades SMR-300) · sourceDOE names two SMR-300 reactors at the Palisades site.
Source-backed project statement
DOE announced on 2 December 2025 that it selected Holtec Government Services, LLC for up to $400 million of cost-shared funding (Holtec: 'valued at $400 million') for the two SMR-300 units; Holtec describes it as milestone-based support intended to advance licensing, pre-construction and supply-chain mobilization. The December 2025 permit application says the award is subject to finalization of the award agreement and is expected to reflect 50/50 cost sharing, with Holtec funding the $400 million private portion, and that Palisades SMR plans to finance up to 80 percent of construction through a loan, with a DOE Title XVII loan guarantee as the currently expected path (the part I application is complete and part II is being prepared). ANS reported on 2 April 2026 that, according to Holtec, the grant will become effective after conditions are met, including negotiation and execution of a funding agreement. The applicant also proposed a license condition that funding documentation be available for NRC inspection before limited and full construction begin, and asked for an exemption from identifying specific funding sources at this stage. The Michigan Strategic Fund's 30 September 2025 report concerns the Palisades restart: it says the state's $300 million incentive was allocated to that project and disbursed to Holtec Palisades, LLC, and it does not mention the SMR units; state funding for Pioneer 1 and 2 was not researched. No executed DOE agreement, loan-guarantee commitment or disbursement for Pioneer 1 and 2 is established. Holtec's earlier $148 million advanced reactor award supported SMR-300 design development. DOE selects TVA and Holtec to advance deployment of US SMRs (2 Dec 2025); Pioneer Units 1 and 2 application, General and Financial Information (ML25365A986); Holtec release: Tier 1 First Mover Award from the USDOE for the dual-unit SMR-300 plant at Palisades (2 Dec 2025); Holtec hits milestones in Palisades restart, new reactor projects -- ANS / Nuclear Newswire; Pioneer Units 1 and 2 application, Enclosure V, Proposed License Conditions (ML25365A990); Michigan Strategic Fund, FY25 targeted energy investment status report (30 Sep 2025)
- Fuel
- Fuel supplier named for this projectFramatome · sourceNamed in the construction permit application (Dec 2025) for fuel design and supply; fuel costs validated by a Framatome quotation; no contract signature stated.
- Fuel form stated for Holtec SMR-300UO2 pellet / square array
Source-backed project statement
SMR, LLC's December 2025 construction-permit filing names Framatome as the project's vendor for fuel design and supply and says fuel costs were validated through a Framatome quotation. The Environmental Report describes a reactor core of 69 Framatome-trademarked GAIA fuel assemblies and, for its transport analysis, assumes fresh fuel is shipped by truck from Framatome's Richland, Washington facility. These are a design basis, a cost quotation and an analytical assumption. No fuel supply contract signature, quantity or delivery schedule for Pioneer 1 and 2 is stated. Pioneer Units 1 and 2 application, General and Financial Information (ML25365A986); Pioneer Units 1 and 2 application, Enclosure III, Environmental Report (ML25365A988)
- Site host or owner
- Current site ownerHoltec Palisades, LLC · source
- Programs and agreements naming the project
- Feasibility or siting study; activeHoltec plan to use its retired nuclear plant sites (Pilgrim, Indian Point, Big Rock Point) for future SMR-300 units
Not found in the sources we checked (1): Comparable schedule revision
- Comparable schedule revision
Comparable schedule revision not established. World Nuclear News reported on 5 December 2023 that Holtec said it would commission its first two SMR-300 units at Palisades by 2030, with the first SMR-300 plant targeted for mid-2030, subject to regulatory reviews and oversight. Holtec's own release of 2 December 2025 says its "Mission 2030" contemplates the Pioneer reactors being brought online in the first years of the 2030s, and ANS reported on 2 April 2026 that Holtec has targeted the early 2030s for commissioning the two reactors. The applicant's December 2025 Environmental Report (Table 1.4-1, "estimated dates, subject to change") gives quarter-level dates for differently named milestones: Pioneer Unit 1 full power operation in the fourth quarter of 2031 and full commercial operation in the fourth quarter of 2031 or first quarter of 2032; Pioneer Unit 2 full power operation in the second quarter of 2032 and full commercial operation in the second or third quarter of 2032. No source states that the earlier target was changed, and the 2023 report does not define "commission" or say whether "first plant" means one unit or both, so it is not equated with any table milestone or unit: this note records no same-milestone schedule revision and no delay. The 2023 figure is trade-press reporting of a company statement; Holtec's own December 2023 release was not captured. The permit filing's construction-completion target (end of 2031) is a separate milestone. These are company targets, not NRC decisions or completed milestones. Palisades SMR programme is under way: Holtec - World Nuclear News; Holtec release: Tier 1 First Mover Award from the USDOE for the dual-unit SMR-300 plant at Palisades (2 Dec 2025); Pioneer Units 1 and 2 application, Enclosure III, Environmental Report (ML25365A988); Holtec hits milestones in Palisades restart, new reactor projects -- ANS / Nuclear Newswire
Timeline
Recorded developments
- · Recorded development
Holtec says Pioneer safety analysis report completes permit application part 2 - · Recorded development
NRC completes draft safety evaluation report for Pioneer, with information gaps - · Other regulatory action recorded
NRC allows specified Pioneer excavation walls before a limited work authorization - · Environmental decision recorded
NRC finds no significant environmental impact for Pioneer excavation-wall exemption - · Regulatory step
NRC finds Part 1 of the Pioneer phased CP application (with LWA request) acceptable for docketing
Earlier developments (3)
- · Application submitted
Application submitted: Pioneer Units 1 and 2 phased construction permit application (with limited work authorization request) - Announced · Recorded development
DOE selects Holtec for $400 million in cost-shared funding for two SMR-300s at Palisades - · Selections announced
Selections announced: Gen III+ SMR selection: Holtec (Palisades SMR-300)
Targets
Planned, target and estimated dates are not achievements or commitments.
- Target · Planned step · Date passed; not recorded as met
NRC target for Pioneer draft environmental impact statement - Target · Planned step
Applicant-requested date for LWA and 10 CFR 50.10(d) exemption issuance - Target · Planned step
NRC target for Pioneer advanced safety evaluation report - Target · Planned step
NRC target for Pioneer final environmental impact statement - Target · Planned step
NRC target for Pioneer final safety evaluation report - Target · Construction start
Start of full-scope nuclear construction (applicant expectation) - Target · Planned step
Construction of both Pioneer units completed (applicant expectation)
This project’s dated entries are in Updates, filtered to this project. New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
Construction applications and decisions
- Pioneer Units 1 and 2 phased construction permit application (with limited work authorization request)
Construction permission sought · Under review · NRC · submitted 31 Dec 2025 · docket 50-616, 50-617 · 91 FR 62565 · 91 FR 66740 · 91 FR 72577
Holtec filed Part 1 of a phased construction permit application for two SMR-300 units (Pioneer 1 and 2) at the Palisades Energy Center on 31 December 2025, including a limited work authorization request. The NRC accepted it for docketing in February 2026 and began weekly notices of receipt on 1 October 2026. Its fourth notice, published 22 October, again records receipt and availability; it does not grant an LWA or construction permit. Part 2 (a complete preliminary safety analysis report, with an updated Quality Assurance Topical Report and exemption requests) was filed on 30 September 2026, according to the NRC's notice of receipt dated 5 November and published 10 November 2026 (91 FR 72577; ADAMS package ML26273A416), which began a second series of four weekly notices. The notice says the NRC staff was then undertaking its acceptance review of Part 2; no acceptance or docketing of Part 2 is recorded. The application remains recorded as under review; this receipt notice is not a new permission decision.
Sources: Federal Register 91 FR 62565 (1 Oct 2026): Pioneer Units 1 and 2 phased construction permit application with limited work authorization request; NRC news 26-008 Holtec Pioneer LWA; Holtec: Major regulatory developments in the Palisades Pioneer Unit 1 & 2 program (30 September 2026); NRC fourth weekly notice of receipt and availability: Pioneer Units 1 and 2 phased construction permit application; Federal Register 91 FR 72577 (10 Nov 2026): Pioneer Units 1 and 2, receipt of construction permit application (Part 2), first of four weekly notices; NRC Pioneer Units 1 and 2 LWA pageCould not be confirmed on . Attempted official source: NRC fourth weekly notice of receipt and availability: Pioneer Units 1 and 2 phased construction permit application. This is an access or status observation only; the record review date is unchanged.
Environmental decision
- NRC environmental assessment and FONSI for Pioneer excavation-wall exemption
Environmental decision · Issued / approved · NRC · decided 25 Aug 2026 · docket 50-616, 50-617 · 91 FR 54890
The NRC made an environmental assessment and finding of no significant impact available on 24 August 2026; its later exemption notice describes the finding as issued on 25 August. It addresses environmental effects of the requested support-of-excavation-wall exemption; it is not the 28 August exemption and does not issue an LWA or construction permit.
Sources: NRC environmental assessment and FONSI for Pioneer excavation-wall exemption; NRC exemption for specified Pioneer support-of-excavation walls
Other applications and decisions
- NRC exemption for specified Pioneer support-of-excavation walls before LWA
Other regulatory action · Issued / approved · NRC · decided 28 Aug 2026 · docket 50-616, 50-617 · 91 FR 55628
The NRC issued a narrow exemption on 28 August 2026 allowing specified permanent support-of-excavation walls at Pioneer Units 1 and 2 before a limited work authorization. The notice does not issue or commit to an LWA or construction permit. The exemption does not show that physical work began or authorize all construction.
Sources: NRC exemption for specified Pioneer support-of-excavation walls
Assessments of the design (not of this site)
(1)
- Holtec SMR-300 UK Generic Design Assessment (two steps) — applies to the design, not to a site
Design assessment · Review completed (not an approval) · ONR/EA (UK) · completed 31 Mar 2026 · submitted Jan 2023
Holtec submitted the design, then named SMR-160, to the UK government for entry into Generic Design Assessment in January 2023, according to the Environment Agency's Step 1 summary; it was renamed SMR-300 in January 2024. The UK regulators began a two-step Generic Design Assessment of Holtec's SMR-300 on 18 October 2023 at the government's request. Step 1 ran from October 2023 to August 2024 and Step 2 from August 2024 to March 2026. The Environment Agency records completing Step 2 on 31 March 2026, and ONR's page records the assessment as completed that month with no Step 3 and no Design Acceptance Confirmation. The assessment is not permission for any site, construction or operation.
Sources: Environment Agency: assessing new nuclear reactor designs; ONR, Holtec SMR-300 Generic Design Assessment; Environment Agency: GDA Step 1 of the Holtec SMR, statement of findings public summary
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(6 notes)
- Evidence review. SMR, LLC's application of December 2025, filed on behalf of Palisades SMR, LLC, requests a limited work authorization to begin construction of a dual-unit SMR-300 plant, Pioneer Units 1 and 2, at the Palisades Energy Center in Covert, Michigan, as Part 1 of a phased construction permit application. The filing says Palisades SMR, LLC was formed to serve as the NRC-licensed owner and Palisades Energy, LLC is expected to serve as licensed operator after completion. The NRC accepted Part 1 and published a notice of acceptance and opportunity for hearing on 27 February 2026; Holtec says it submitted the preliminary safety analysis report on 30 September 2026, completing the second phase of the application. No limited work authorization or construction permit has been issued: the NRC page (updated 30 October 2026, read 3 November) lists a draft safety evaluation report with information gaps on 31 August 2026, the draft environmental impact statement's date as TBD where it earlier showed 31 October 2026, and targets of 31 January 2027 (advanced safety evaluation) and 31 March 2027 (final safety evaluation and environmental impact statement). On 28 August 2026 the NRC issued a narrow exemption allowing permanent support-of-excavation walls before a limited work authorization, which it says is not a commitment to issue a limited work authorization or construction permit; Holtec says it is performing non-construction activities, and no opened source says the excavation walls or any nuclear construction have begun. The applicant asked for the limited work authorization by 31 December 2026 for limited construction in 2027 and expects full-scope nuclear construction from the fourth quarter of 2028, with both units complete by the end of 2031; these are targets. Holtec says the two units together are designed to provide 680 MW, and the NRC's release of 13 January 2026 gives approximately 340 MWe per unit, both without a gross or net basis; World Nuclear News (2 October 2026) describes the SMR-300 design as about 300 MWe, which differs from the Pioneer-specific per-unit figure. The licensing stage, two units, 680 MWe plant output with unspecified basis, and Palisades Energy as intended operator stay stored. Last checked 19 Oct 2026. Holtec: Major regulatory developments in the Palisades Pioneer Unit 1 & 2 program (30 September 2026); NRC news 26-008 Holtec Pioneer LWA; Pioneer Units 1 and 2 application, General and Financial Information (ML25365A986); NRC exemption for specified Pioneer support-of-excavation walls; NRC Pioneer Units 1 and 2 LWA page; World Nuclear News: second part of construction permit application submitted for Pioneer SMRs (October 2026)
What would change this
The NRC's draft environmental impact statement (the NRC's page lists no date), its safety evaluation or decision on the Pioneer limited work authorization (the applicant asked for issuance by 31 December 2026), or an NRC notice docketing Part 2 of the construction permit application. Next scheduled check: 14 Jan 2027.
- Plant capacity (scope qualified). Holtec states the two Pioneer units are designed to provide 680 MWe together, and the NRC's January 2026 release describes each SMR-300 unit as approximately 340 MWe. Neither source states whether the figures are gross or net. The SMR-300 design record lists about 300 MWe per module; the project figure follows the Pioneer-specific sources. Last checked 18 Oct 2026. Holtec: Major regulatory developments in the Palisades Pioneer Unit 1 & 2 program (30 September 2026); NRC news 26-008 Holtec Pioneer LWA
What would change this
The public preliminary safety analysis report or an NRC safety evaluation states a Pioneer power rating, or Holtec states a net or gross basis. Next scheduled check: 18 Jan 2027.
- Next decision and prerequisites. The NRC's Pioneer page, last updated 30 October 2026 and re-read on 13 November, still lists the draft environmental impact statement date as TBD, an advanced safety evaluation report target of 31 January 2027, and final safety evaluation report and final environmental impact statement targets of 31 March 2027. The applicant asked for the limited work authorization to be issued by 31 December 2026; the page lists no limited work authorization decision date. On Part 2, the next NRC step is the acceptance review that the 10 November 2026 receipt notice says is underway (the notice gives no date for it): if Part 2 is accepted for docketing, later notices will say so. These are regulator targets and an applicant request. No limited work authorization or construction permit decision has been made. Last checked 13 Nov 2026. NRC Pioneer Units 1 and 2 LWA page; Pioneer Units 1 and 2 application, General and Financial Information (ML25365A986); Federal Register 91 FR 72577 (10 Nov 2026): Pioneer Units 1 and 2, receipt of construction permit application (Part 2), first of four weekly notices
What would change this
NRC acceptance and docketing of Part 2, issue of the draft environmental impact statement (the NRC page lists no date), or an NRC decision on the limited work authorization (the applicant asked for issuance by 31 December 2026). Next scheduled check: 14 Jan 2027.
- Permissions and public process. The NRC accepted Part 1 of Holtec's phased construction permit application, which includes the limited work authorization request, for docketing; its letter is dated 13 February 2026. The 27 February 2026 notice (91 FR 9892) set 28 April 2026 as the deadline for hearing requests and petitions to intervene and said an uncontested (mandatory) hearing will be held at a time and place to be set in the future by the presiding officer; this review did not establish whether any hearing request was filed. A 15 June 2026 notice opened environmental impact statement scoping (comments by 15 July 2026), with the Army Corps of Engineers a cooperating agency. The NRC issued a narrow exemption on 28 August 2026 for permanent support-of-excavation walls, after an environmental assessment; that exemption is not a limited work authorization or construction permit. For Part 2 (the preliminary safety analysis report, an updated quality assurance topical report and exemption requests, filed 30 September 2026 with a request that the NRC docket and review it), the NRC began four weekly notices of receipt on 10 November 2026 (91 FR 72577) and says its staff is undertaking the acceptance review; the notice says that if Part 2 is accepted for docketing, later notices will address its acceptability for docketing and public participation. No limited work authorization or construction permit has been issued. Last checked 13 Nov 2026. govinfo.gov: NRC finds Part 1 of the Pioneer phased CP application (with LWA request) acceptable for docketing; Palisades SMR, LLC; Pioneer Units 1 and 2; Phased Construction Permit Application; Limited Work Authorization; Notice of Intent to Conduct Scoping Process and P; NRC exemption for specified Pioneer support-of-excavation walls; Holtec transmittal 300-USNRC-26018 of Part 2 of the Pioneer construction permit application (ML26273A417); Federal Register 91 FR 72577 (10 Nov 2026): Pioneer Units 1 and 2, receipt of construction permit application (Part 2), first of four weekly notices; NRC Pioneer Units 1 and 2 LWA page
What would change this
An NRC notice accepting or declining to docket Part 2, publication of the draft environmental impact statement and its comment period, or an NRC decision on the limited work authorization. Next scheduled check: 13 Jan 2027.
- Site dependencies (land, grid, water). The applicant's Environmental Report (December 2025) describes the plan for the approximately 432-acre Palisades Energy Center site. Land: the property is owned by Holtec Palisades, LLC; the general and financial volume says that, before nuclear construction begins, Holtec Palisades "will ensure" that Palisades SMR, LLC has the appropriate rights with respect to the project site, subject to NRC rules for the existing plant and any loan covenants to DOE on the restart financing, so no site-rights arrangement for the new units is shown as in place. The report expects 110 to 123 acres to be disturbed and says the existing dry fuel storage building is planned to be demolished so it can be relocated, while elsewhere saying it may be reconstructed with its location not yet defined. Water: the new units would use mechanical draft cooling towers supplied through three new Lake Michigan intake pipes (each up to about 20,000 gpm, about 60,000 gpm together; 16,714 gpm site makeup in the parameter table) and a new offshore outfall (about 20,000 gpm maximum diluted discharge); the report lists the Michigan EGLE cooling-water intake (CWA section 316(b)) application as planned for 2026, concurrent with the NPDES permit. Grid: the existing switchyard is expected to be expanded and the report says no new transmission line pathway is required; it also says Holtec "has submitted an application to MISO for connection to the electrical grid in 2026, which would add the SMR-300 units to MISO's interconnection queue in 2026" (an application, not an interconnection agreement; the tense and year are unclear in a December 2025 document). These are the applicant's design and permitting plans. The NRC's independent environmental review (draft statement date TBD) and any state permit decisions were not found, and no transfer of site rights is shown. Last checked 13 Nov 2026. Pioneer Units 1 and 2 application, General and Financial Information (ML25365A986); Pioneer Units 1 and 2 application, Enclosure III, Environmental Report (ML25365A988); NRC Pioneer Units 1 and 2 LWA page
What would change this
The NRC draft environmental impact statement, EGLE intake or discharge permit actions, a MISO interconnection milestone for the units, or a filed transfer of site rights to Palisades SMR, LLC. Next scheduled check: 13 May 2027.
- Spent fuel, waste and closure. The applicant's Environmental Report (Part 1 of the construction permit application, December 2025) says Pioneer Units 1 and 2 would use onsite interim dry storage of spent fuel in Holtec's HI-STORM UMAX underground system, after discharge to a spent fuel pool that it says can hold 240 fuel assemblies, and that the existing Palisades spent fuel storage installation is planned to sit inside the new units' protected area. It says low-level waste would be held onsite about 90 days before transport to an external facility, that the new units would have their own radioactive waste facilities and systems, that a spent fuel contract with the Department of Energy is to be in place during operations before DOE takes possession of the fuel, and that no decommissioning method has been selected, with the actions needed for decommissioning funding assurance anticipated in support of the operating license application. These are the applicant's plans. They do not establish an NRC-approved storage installation, an executed DOE contract, an offsite destination or a decommissioning plan. Last checked 13 Nov 2026. Pioneer Units 1 and 2 application, Enclosure III, Environmental Report (ML25365A988)
What would change this
The NRC draft environmental impact statement or safety evaluation addressing Pioneer spent fuel storage, an executed DOE spent fuel contract, or a decommissioning plan or funding filing for Pioneer 1 and 2. Next scheduled check: 13 Apr 2027.
Evidence dates
(11 of 21 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(21)
- NRC news 26-008 Holtec Pioneer LWA (regulator, accessed 18 Oct 2026)
- NRC Pioneer Units 1 and 2 LWA page (regulator, page updated 30 Oct 2026, accessed 13 Nov 2026)
- Federal Register 91 FR 62565 (1 Oct 2026): Pioneer Units 1 and 2 phased construction permit application with limited work authorization request (regulator, accessed 3 Oct 2026)
- NRC environmental assessment and FONSI for Pioneer excavation-wall exemption (regulator, accessed 9 Oct 2026)
- NRC exemption for specified Pioneer support-of-excavation walls (regulator, accessed 9 Oct 2026)
- Holtec: Major regulatory developments in the Palisades Pioneer Unit 1 & 2 program (30 September 2026) (company, accessed 18 Oct 2026)
- World Nuclear News: second part of construction permit application submitted for Pioneer SMRs (October 2026) (news report, accessed 6 Oct 2026)
- Pioneer Units 1 and 2 application, General and Financial Information (ML25365A986) (regulator, accessed 18 Oct 2026)
- DOE selects TVA and Holtec to advance deployment of US SMRs (2 Dec 2025) (government, accessed 3 Nov 2026)
- Palisades SMR programme is under way: Holtec - World Nuclear News (news report, published 5 Dec 2023, accessed 21 Oct 2026)
- Holtec hits milestones in Palisades restart, new reactor projects -- ANS / Nuclear Newswire (news report, published 2 Apr 2026, accessed 21 Oct 2026)
- Palisades SMR, LLC; Pioneer Units 1 and 2; Phased Construction Permit Application; Limited Work Authorization; Notice of Intent to Conduct Scoping Process and P (regulator, published 15 Jun 2026, accessed 23 Oct 2026)
- Pioneer Units 1 and 2 environmental review (EIS) page (regulator, accessed 23 Oct 2026)
- Federal Register 91 FR 72577 (10 Nov 2026): Pioneer Units 1 and 2, receipt of construction permit application (Part 2), first of four weekly notices (regulator, published 10 Nov 2026, accessed 13 Nov 2026)
- Pioneer Units 1 and 2 application, Enclosure III, Environmental Report (ML25365A988) (regulator, dated Dec 2025, accessed 13 Nov 2026)
- Holtec and Wolverine Ink Historic Power Purchase Agreement for the Palisades Power Plant (12 Sep 2023) (company, published 12 Sep 2023, accessed 13 Nov 2026)
- Holtec transmittal 300-USNRC-26018 of Part 2 of the Pioneer construction permit application (ML26273A417) (regulator, dated 30 Sep 2026, accessed 13 Nov 2026)
- Holtec release: Tier 1 First Mover Award from the USDOE for the dual-unit SMR-300 plant at Palisades (2 Dec 2025) (company, dated 2 Dec 2025, accessed 13 Nov 2026)
- Pioneer Units 1 and 2 application, Enclosure V, Proposed License Conditions (ML25365A990) (regulator, dated Dec 2025, accessed 13 Nov 2026)
- Michigan Strategic Fund, FY25 targeted energy investment status report (30 Sep 2025) (government, dated 30 Sep 2025, accessed 13 Nov 2026)
- govinfo.gov: NRC finds Part 1 of the Pioneer phased CP application (with LWA request) acceptable for docketing (regulator, published 27 Feb 2026, accessed 14 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Holtec Pioneer Units 1 and 2 (SMR-300 at Palisades) — https://smrmap.com/projects/holtec-smr-300-palisades/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Holtec Pioneer Units 1 and 2 (SMR-300 at Palisades)”. Record reviewed 18 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/holtec-smr-300-palisades/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.