Projects / United States · Siting

Aalo commercial proposal at Texas A&M-RELLIS

Aalo Atomics' commercial pod proposal at Texas A&M-RELLIS in the United States, at the siting stage, is distinct from Aalo-X at INL.

Current status

Stage
Siting
How current
General record check . Bounded evidence review . None of the 2 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates

Newest recorded development . Next general check: . Next evidence or detail review: .

Permissions
No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
Latest development
Announced 4 Feb 2025 · Announcement: Texas A&M offers RELLIS land to four reactor companies. Chancellor announced agreements to pursue Kairos, Natura, Terrestrial, and Aalo projects at RELLIS. Source: Texas A&M System Goes Nuclear. Updates entry
Next dated milestone
No next milestone date is recorded.
Selected limitations
  • Electrical output is not recorded.
  • Thermal output is not recorded on this project.
  • No operator is recorded.
  • The mapped point is not an exact surveyed coordinate.

A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.

Description

On 4 Feb 2025 Texas A&M said Aalo could build up to six pods at RELLIS under the Energy Proving Ground. Texas A&M has a campus-wide NRC early-site-permit pre-application; it is not an Aalo-specific application or a permit. A future licensed operator is not named. Committed module count and capacity remain unknown.

Key facts

Design
Aalo pod (commercial proposal) (SMR)
Technology
Other · sodium
Operator(s)
Not recorded
Vendor for linked design
Aalo Atomics
Location
Texas A&M-RELLIS Energy Proving Ground · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Shared campus pin for distinct company proposals. Coordinate is the NuclearChain CC BY 4.0 sites export pin for the Aalo Texas A&M discovery row (position_approximate=1), which sits on the RELLIS campus. It is not a reactor-building survey and is not a headquarters pin.
Coordinates
30.6420749, -96.4682751 · site-area point (approximate)
Electrical capacity
Not recorded · scope: unknown
Thermal capacity
Not recorded
Modules planned
Not recorded
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Record reviewed
9 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes

Aalo commercial proposal at Texas A&M-RELLIS is recorded at Texas A&M-RELLIS Energy Proving Ground, Texas, United States. Operator: No operator is recorded. Recorded vendor: Aalo Atomics. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Kairos commercial proposal at Texas A&M-RELLIS, Natura MSR-100 proposal at Texas A&M-RELLIS, Terrestrial Energy IMSR at Texas A&M-RELLIS, Last Energy PWR-5 pilot at Texas A&M-RELLIS.

Coordinate source: NuclearChain data exports, NuclearChain sites.csv row 'aalo-atomics-texas-a-and-m-nuclear-power-plant' (30.6420749, -96.4682751)

Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project.

Who is involved

Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.

More on reading these answers

Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.

Reactor supplier
Fuel
  • Fuel form stated for Aalo pod (commercial proposal)UO₂ ceramic
  • Enrichment stated for Aalo pod (commercial proposal)8 % LEU+
No project-specific fuel supply arrangement is recorded as a structured fact.

The 4 February 2025 Texas A&M System announcement and the NRC pre-application page, last reviewed 15 September 2026, name no fuel supplier, fabrication, allocation or delivery for Aalo's pods at RELLIS. The announcement does not discuss fuel at all. Texas A&M System Goes Nuclear

Site host or owner
Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
Customer or offtaker

The 4 February 2025 Texas A&M System announcement and the NRC pre-application page, last reviewed 15 September 2026, name no power or heat buyer, quantity or agreement for Aalo's pods at RELLIS. Aalo's remark that its technology will ultimately power data centers, and the statement that proving-ground power could supply the ERCOT grid, are general aims, not offtake agreements. Texas A&M is the site host, not a customer. Texas A&M System Goes Nuclear

Contractor

The 4 February 2025 Texas A&M System announcement and the NRC pre-application page, last reviewed 15 September 2026, name no engineering, licensing or construction contractor for Aalo's pods at RELLIS. The announcement says Aalo agreed to work with the System, the site host, to bring reactors to RELLIS and that the System had begun a campus early-site-permit process, which covers the campus rather than Aalo specifically. Texas A&M System Goes Nuclear

Funding and government decisions

The 4 February 2025 Texas A&M System announcement and the NRC pre-application page, last reviewed 15 September 2026, state no amount, grant, loan, investment or cost share for Aalo's RELLIS project. The early-site-permit process is a regulatory step, not a funding instrument, and the land offer is not stated as money. Texas A&M System Goes Nuclear

Comparable schedule revision

Comparable schedule revision not established. The 4 February 2025 Texas A&M System announcement says the first RELLIS reactors could be built within five years, and the NRC pre-application page, last reviewed 15 September 2026, still shows a campus early-site-permit submittal planned for the fourth quarter of 2025. Each target is stated once and they concern different milestones, so neither source revises a date for Aalo's pods. NRC pre-application activities: Texas A&M University System; Texas A&M System Goes Nuclear

Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Operator or intended licensed owner; Programs and agreements naming the project
Project proposer or applicant
No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
Operator or intended licensed owner
Programs and agreements naming the project

Timeline

Recorded developments

Permissions and applications

Selected jurisdiction context

Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.

Evidence and open questions

(4 notes, 1 not yet reviewed)
  • Evidence review. The Texas A&M University System's release of 4 February 2025 says the Chancellor offered System land near the Texas A&M campus to four reactor companies for the Energy Proving Ground at the 2,400-acre RELLIS campus in Bryan, Texas, and quotes Aalo Atomics' chief executive saying the company could build up to six Aalo Pods at the site. The instrument is that announcement of agreements with the four companies; no Aalo-specific application, license, unit commitment or capacity is published. The NRC's pre-application page (last updated 15 September 2026) records campus-wide early site permit pre-application activity by the Texas A&M University System for multiple advanced reactors rated 10-1000 MWe gross, with ESP submittal planned for the fourth quarter of 2025; it names no vendor. The next documentary decision is the System's ESP application and NRC docketing, or an Aalo filing or agreement for the site. The stored Aalo pod design, Aalo as vendor and the siting stage stay; module count and capacity stay unknown because 'up to six' is a ceiling. The NRC page still shows the fourth-quarter 2025 plan, so the opened sources do not establish that the ESP application was submitted. Last checked 19 Oct 2026. Texas A&M System Goes Nuclear; NRC pre-application activities: Texas A&M University System
    What would change this

    Texas A&M University System's early site permit application and the NRC's acceptance or docketing notice, or an Aalo-specific agreement or filing stating the module count at RELLIS. Next scheduled check: 19 Jan 2027.

  • Next decision and prerequisites. The next consequential step shown is Texas A&M filing its early site permit application for RELLIS; the NRC page, updated 15 September 2026, still lists only pre-application activities and gives no filing date. The February 2025 announcement says the first reactors at the proving ground could be built within five years. That is a stated possibility, not a Aalo construction schedule. Last checked 23 Oct 2026. NRC pre-application activities: Texas A&M University System; Texas A&M System Goes Nuclear
    What would change this

    Texas A&M's ESP filing, or a Aalo construction or license decision for RELLIS. Next scheduled check: 23 Apr 2027.

  • Permissions and public process. The NRC's Texas A&M University System page, updated 15 September 2026, says the NRC is in pre-application activities with the System on a future early site permit for multiple advanced reactors at the RELLIS campus. Texas A&M's February 2025 announcement says the System began that process for the site where Aalo Atomics proposed up to six Aalo Pods. This campus-wide pre-application is not a filed application, a permit or a Aalo-specific license, and these sources record no public consultation. Last checked 23 Oct 2026. NRC pre-application activities: Texas A&M University System; Texas A&M System Goes Nuclear
    What would change this

    Texas A&M's early site permit application for RELLIS, or a Aalo license application naming the site. Next scheduled check: 23 Apr 2027.

  • Site dependencies (land, grid, water). Texas A&M's February 2025 announcement says the System offered land at the 2,400-acre RELLIS campus in Bryan, Texas, to four reactor companies including Aalo Atomics, and that power from the proving ground could supply the ERCOT grid. An offer of land under a cooperation agreement is not a lease, and the sources read state no Aalo-specific plot, interconnection or cooling-water arrangement. Last checked 23 Oct 2026. Texas A&M System Goes Nuclear
    What would change this

    A ground lease or site agreement for Aalo Atomics at RELLIS, or an ERCOT interconnection request. Next scheduled check: 23 Apr 2027.

Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.

Evidence dates

(0 of 2 sources with a publication or document date)
Latest dated listed source publication: no date recorded.Latest dated recorded event: Texas A&M offers RELLIS land to four reactor companies: 4 Feb 2025.2 of 2 listed sources have no publication or document date recorded here.

Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.

Sources

(2)

Suggest an update

If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.

No email program? Write to corrections@smrmap.com and include the project name and link: Aalo commercial proposal at Texas A&M-RELLIS — https://smrmap.com/projects/aalo-rellis/. Suggestions are checked against sources before anything changes; see how corrections work.

Cite or share this page

SMRMap. “Aalo commercial proposal at Texas A&M-RELLIS”. Record reviewed 9 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/aalo-rellis/ (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.