Projects / United States · Siting
Kairos commercial proposal at Texas A&M-RELLIS
Kairos told Texas A&M it could bring one or more commercial deployments to RELLIS.
Current status
- How current
- General record check . Bounded evidence review . None of the 3 listed sources has a publication or document date recorded here. Status not rechecked since then; this project is not covered by the nightly status check.
Development and review dates
No dated development is recorded. Next general check: . Next evidence or detail review: .
- Permissions
- No separate project-specific permission or application entry is recorded here. The description and evidence notes may report steps not yet entered separately; this is not a finding that none exists.
- Latest development
- No actual dated development is recorded.
- Next dated milestone
- No next milestone date is recorded.
- Selected limitations
- Electrical output is not recorded.
- Thermal output is not recorded on this project.
- No operator is recorded.
- The mapped point is not an exact surveyed coordinate.
A review date is not proof of current activity. An announcement records the announcement, not necessarily the physical step it describes.
- Reactor type
- Fluoride salt-cooled high-temperature reactor. How it works, with a 3D view.
View on the map · View on the 3D globe · Key facts · Who is involved · Timeline · Permissions and applications · Evidence dates · Sources and check dates · Suggest an update
Description
This is not Hermes 1 or Hermes 2 at Oak Ridge. Texas A&M has a campus-wide NRC early-site-permit pre-application, not a Kairos-specific application or permit. A future licensed operator, module count and capacity are not stated.
Key facts
- Design
- KP-FHR commercial plant (SMR)
- Technology
- Fluoride-salt-cooled high-temperature reactor (FHR) · molten salt
- Reactor vessel of this design
- 7.2 m tall, 3.9 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 349.150 MWe stays a two-reactor block and is not one module The electrical output stated for two reactors is not assigned to this one vessel.SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale - Operator(s)
- Not recorded
- Vendor for linked design
- Kairos Power
- Location
- Texas A&M-RELLIS Energy Proving Ground · United States · precision: site area (named plant, laboratory, base, port, campus or parcel)
Shared campus pin for distinct company proposals. Coordinate is the NuclearChain CC BY 4.0 sites export pin for the Aalo Texas A&M discovery row (position_approximate=1), which sits on the RELLIS campus. It is not a reactor-building survey and is not a headquarters pin. - Coordinates
- 30.6420749, -96.4682751 · site-area point (approximate)
- Electrical capacity
- Not recorded · scope: unknown
- Thermal capacity
- Not recorded
- Modules planned
- Not recorded
- Inclusion basis
- Vendor SMR claim, capacity checked
- Confidence
- medium
- Record reviewed
- 9 Oct 2026Evidence review 19 Oct 2026. How current names both.
Site and capacity notes
Kairos commercial proposal at Texas A&M-RELLIS is recorded at Texas A&M-RELLIS Energy Proving Ground, Texas, United States. Operator: No operator is recorded. Recorded vendor: Kairos Power. Stage: Siting. Location precision: site area (named plant, laboratory, base, port, campus or parcel); site-area point (approximate). Other records at this site: Aalo commercial proposal at Texas A&M-RELLIS, Natura MSR-100 proposal at Texas A&M-RELLIS, Terrestrial Energy IMSR at Texas A&M-RELLIS, Last Energy PWR-5 pilot at Texas A&M-RELLIS.
Coordinate source: NuclearChain data exports, NuclearChain sites.csv row 'aalo-atomics-texas-a-and-m-nuclear-power-plant' (30.6420749, -96.4682751)
Electrical output is not recorded on this project. Module count is not recorded. Thermal output is not recorded on this project. The linked design record states 320 MWth (nameplate; basis unspecified) (module); that figure is not copied onto this project.
Who is involved
Every project is asked the same questions. An answer names only what a cited source supports: a proposal, letter of intent or program listing is not a contract, a payment or a permit. “Not recorded” is not a finding that none exists. Compare who is involved across projects.
More on reading these answers
Company-level money counts only when its source ties it to the project, and the note then says it is company-level. Contractor answers distinguish preparatory partners from construction appointments, and retain the source's terms. An answer not found in the sources we checked stays unknown, and a question with no completed source review stays unreviewed.
- Reactor supplier
- Vendor for the linked designKairos Power
- Fuel
- Fuel form stated for KP-FHR commercial plantTRISO particles in graphite pebble matrix / pebble bed
The NRC's Hermes page describes TRISO pebble fuel with HALEU for the separate Oak Ridge test reactor, which is not a RELLIS fuel arrangement. The 4 February 2025 Texas A&M System announcement and the NRC campus pre-application page name no fuel supplier, fabrication or delivery for Kairos at RELLIS. NRC Kairos Hermes construction permit materials
- Site host or owner
- Site hostThe Texas A&M University System · source
Not found in the sources we checked (4): Customer or offtaker; Contractor; Funding and government decisions; Comparable schedule revision
- Customer or offtaker
The 4 February 2025 Texas A&M System announcement says Kairos could bring one or more commercial deployments to RELLIS and that proving-ground power could supply the ERCOT grid, but it names no buyer, quantity or agreement. The NRC's campus pre-application page, last reviewed 15 September 2026, and its Hermes page for the separate Oak Ridge test reactor name no customer either. Texas A&M System Goes Nuclear
- Contractor
The 4 February 2025 Texas A&M System announcement and the NRC's campus pre-application page name no engineering, licensing or construction contractor for a Kairos deployment at RELLIS. The announcement says Kairos agreed to work with the System, the site host, and the System began a campus early-site-permit process. The NRC's December 2023 Hermes construction permit is for a separate test reactor at Oak Ridge, Tennessee. Texas A&M System Goes Nuclear; NRC Kairos Hermes construction permit materials
- Funding and government decisions
The 4 February 2025 Texas A&M System announcement and the NRC's campus pre-application page, last reviewed 15 September 2026, state no amount, grant, loan or investment for Kairos at RELLIS. The campus early-site-permit process is regulatory, and the Hermes construction permit at Oak Ridge is neither funding nor this site. Texas A&M System Goes Nuclear
- Comparable schedule revision
Comparable schedule revision not established. The 4 February 2025 Texas A&M System announcement says the first RELLIS reactors could be built within five years, and the NRC's campus page still shows an early-site-permit submittal planned for the fourth quarter of 2025. The Hermes dates belong to the Oak Ridge test reactor. No source read gives two dates for the same Kairos milestone at RELLIS. NRC pre-application activities: Texas A&M University System; Texas A&M System Goes Nuclear; NRC Kairos Hermes construction permit materials
Not recorded in SMRMap's reviewed evidence (3): Project proposer or applicant; Operator or intended licensed owner; Programs and agreements naming the project
- Project proposer or applicant
- No separate project proposer or applicant is recorded. The operator and supplier answers may identify who is developing the project; no role is inferred from them.
- Operator or intended licensed owner
- Programs and agreements naming the project
Timeline
This timeline has no entries yet. Other dated information may appear in the description and checking notes.
New developments for every project appear in the site-wide monthly digests and RSS feed; there is no separate feed for one project.
Permissions and applications
- No separate permission or application entries are recorded for this project. Its description, sources and evidence notes may report steps not yet entered separately.
Selected jurisdiction context
Browse related records by location. A jurisdiction measure does not by itself approve this project, and location alone does not establish eligibility for funding or support.
Evidence and open questions
(4 notes, 1 not yet reviewed)
- Evidence review. The Texas A&M University System's 4 February 2025 release says the chief executives of Kairos Power, Natura Resources, Terrestrial Energy and Aalo Atomics agreed to work with the System to bring reactors to the 2,400-acre Texas A&M-RELLIS campus in Bryan, Texas (the Energy Proving Ground), and quotes Kairos's chief executive saying the company could bring one or more commercial deployments to the site. The release names no Kairos design, unit count, capacity or operator for RELLIS; the stored KP-FHR commercial-plant design rests on the NRC's Hermes page, which describes Kairos as developing the KP-FHR (fluoride salt-cooled, high-temperature, TRISO pebble fuel) but concerns the 35 MWt Hermes test reactor at Oak Ridge, Tennessee, not RELLIS. The instrument is the System's announced agreements with the four companies, and the System said it had begun the NRC early site permit process. The NRC's pre-application page (last updated 15 September 2026) records campus-wide ESP pre-application activity for multiple advanced reactors rated 10-1000 MWe gross, with submittal planned for the fourth quarter of 2025, and names no vendor. The next documentary decision is the System's ESP application and NRC docketing, or a Kairos-specific agreement or filing for RELLIS. The stored Kairos vendor and siting stage stay; the KP-FHR design link is an inference from Kairos's technology rather than a RELLIS-specific statement, and module count, capacity and operator stay unknown. Last checked 19 Oct 2026. Texas A&M System Goes Nuclear; NRC Kairos Hermes construction permit materials; NRC pre-application activities: Texas A&M University System
What would change this
Texas A&M University System's early site permit application and the NRC's docketing notice, or a Kairos Power agreement or filing for RELLIS stating the design, unit count and output. Next scheduled check: 19 Jan 2027.
- Next decision and prerequisites. The next consequential step shown is Texas A&M filing its early site permit application for RELLIS; the NRC page, updated 15 September 2026, still lists only pre-application activities and gives no filing date. The February 2025 announcement says the first reactors at the proving ground could be built within five years. That is a stated possibility, not a Kairos construction schedule. Last checked 23 Oct 2026. NRC pre-application activities: Texas A&M University System; Texas A&M System Goes Nuclear
What would change this
Texas A&M's ESP filing, or a Kairos construction or license decision for RELLIS. Next scheduled check: 23 Apr 2027.
- Permissions and public process. The NRC's Texas A&M University System page, updated 15 September 2026, says the NRC is in pre-application activities with the System on a future early site permit for multiple advanced reactors at the RELLIS campus. Texas A&M's February 2025 announcement says the System began that process for the site where Kairos Power proposed one or more commercial Kairos deployments. This campus-wide pre-application is not a filed application, a permit or a Kairos-specific license, and these sources record no public consultation. Last checked 23 Oct 2026. NRC pre-application activities: Texas A&M University System; Texas A&M System Goes Nuclear
What would change this
Texas A&M's early site permit application for RELLIS, or a Kairos license application naming the site. Next scheduled check: 23 Apr 2027.
- Site dependencies (land, grid, water). Texas A&M's February 2025 announcement says the System offered land at the 2,400-acre RELLIS campus in Bryan, Texas, to four reactor companies including Kairos Power, and that power from the proving ground could supply the ERCOT grid. An offer of land under a cooperation agreement is not a lease, and the sources read state no Kairos-specific plot, interconnection or cooling-water arrangement. Last checked 23 Oct 2026. Texas A&M System Goes Nuclear
What would change this
A ground lease or site agreement for Kairos Power at RELLIS, or an ERCOT interconnection request. Next scheduled check: 23 Apr 2027.
Not yet reviewed against sources: Spent fuel, waste and closure. An unreviewed question is unfinished research, not a finding that nothing exists.
Evidence dates
(0 of 3 sources with a publication or document date)
Dates describe the listed documents and recorded events, not proof of current project activity. An announcement dates the announcement, not the promised physical step. Permission dates remain in Permissions and applications. Targets, page-update, access and review dates are separate. Undated evidence may be newer.
Sources
(3)
- Texas A&M System Goes Nuclear (government, accessed 1 Oct 2026)
- NRC Kairos Hermes construction permit materials (regulator, accessed 14 Oct 2026)
- NRC pre-application activities: Texas A&M University System (regulator, accessed 9 Oct 2026)
Suggest an update
If something on this record is wrong, missing or out of date, email a suggested update. It opens your own email program with this project’s name and link filled in; nothing is sent until you send it.
No email program? Write to corrections@smrmap.com and include the project name and link: Kairos commercial proposal at Texas A&M-RELLIS — https://smrmap.com/projects/kairos-rellis/. Suggestions are checked against sources before anything changes; see how corrections work.
Cite or share this page
SMRMap. “Kairos commercial proposal at Texas A&M-RELLIS”. Record reviewed 9 Oct 2026. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/projects/kairos-rellis/ (accessed [date]). Data license CC BY 4.0.
“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.