Designs

IMSR (Integral Molten Salt Reactor)

Terrestrial Energy integral molten-salt small modular plant. Module electrical output is not stated in the opened RELLIS lease release. The RELLIS project is site control and research, not a licensed reactor. In its Phase 2 vendor-design-review summary page for the IMSR400 configuration, marked modified 18 April 2023, the CNSC found no fundamental licensing barrier within the reviewed topics but required further design and safety work. The identified follow-up includes salt chemistry, instrumentation, shutdown performance and passive cooling analysis. This voluntary pre-licensing review neither certifies the design nor grants a license, and its historical configuration is not used to assign a rating to the RELLIS project. A 28 October 2025 issuer release describes a two-IMSR plant at 822 MWth / 390 MWe but also calls an IMSR unit 390 MWe. The inconsistent unit/plant wording does not establish a single-module rating or the output of a RELLIS deployment.

Reactor type
Molten salt reactor. How it works, with a 3D view.
Projects
Siting: Terrestrial Energy IMSR at Texas A&M-RELLIS. Furthest recorded stage of 3 using this design. Development status as stated: Detailed design.
Evidence
7 sources; first primary source: Terrestrial Energy begins trading on Nasdaq (IMSR). Record reviewed 1 Oct 2026.
Schematic of IMSR (Integral Molten Salt Reactor). On the left, a tall reactor vessel holds graphite with fuel channels low down and primary heat exchangers above it, with pump motors and shutdown drives on top.
Schematic of IMSR (Integral Molten Salt Reactor).

Key facts

Class
SMR
Technology
Molten salt reactor (MSR)
Coolant
Molten salt
Spectrum
Thermal
Developer / vendor(s)
Terrestrial Energy
Fuel form
Molten salt fuel
Enrichment
Standard Assay Low-Enriched Uranium (SALEU), under 5% uranium-235 (issuer specification, not delivered fuel).
Development status (as stated)
Detailed design
Reactor vessel
18 m tall, 4.1 m across. Developer's figure in the IAEA ARIS catalog, 2026 edition, printed p. 337.
SMRMap has not checked this against drawings or regulators' documents. A larger vessel does not mean a more powerful reactor, and a reactor vessel is not a whole power plant. The catalog has no open license. These figures are quoted from it and are not offered under SMRMap's CC BY 4.0 data license. These vessel figures are page reference material, outside SMRMap's downloadable dataset and its dataset fingerprint. Quoted source material retains its separate rights.
All vessels to scale
Inclusion basis
Vendor SMR claim, capacity checked
Confidence
medium
Not yet recorded
Expected but not recorded as a structured fact: Module rating (reviewed: sources conflict; see Evidence and open questions). A missing structured fact does not mean zero or that it does not exist; a documented review limit is named beside the fact, and the description and sources may say more.
Record reviewed
1 Oct 2026 (record review date, not proof of current availability or a deployment)

All fields

(2 without a known value)
Module electrical
Not recorded
Module thermal
Not recorded

Tracked deployment projects

Agreements naming this design (3)

Agreements, plans, studies and government programs whose sources name this design. They are not deployment projects.

Design sources

(7)

Evidence and open questions

(2 notes)
  • Evidence review. The 2024 SMR Technology Catalogue (third edition, June 2025) describes Terrestrial Energy's Integral Molten Salt Reactor in its IMSR400 configuration as a thermal-spectrum, graphite-moderated, near-atmospheric-pressure molten salt reactor with molten salt fuel under 5% enrichment, for grid power and industrial heat, rated 442 MWt / 195 MWe per operating core-unit and 884 MWt / 390 MWe (net) for the dual core-unit reference plant, at 'Detailed Design' and to be deployed in the early 2030s. The CNSC Phase 2 vendor design review summary (modified 2023-04-18) instead calls the IMSR400 a 400-MWth (200-MWe) reactor and found no fundamental barriers to licensing within the reviewed topics, while requiring further design work; a VDR is not a certification or license. Terrestrial Energy's 28 October 2025 release gives the two-IMSR plant as 822 MWth / 390 MWe but also says 'our IMSR unit' is 390 MWe, and says Texas A&M selected its IMSR plant in February 2025 for the RELLIS campus; the Texas A&M System's 18 June 2026 release reports ground lease and research agreements giving site control of about 77 acres at A&M-RELLIS and R&D tied to DOE projects TETRA and TEFLA (the RELLIS project; TETRA only as a related DOE project). No opened source names the Ameresco Aberdeen deployment (the release names Ameresco only as a partner). Stored vendor, MSR family, molten-salt coolant, thermal spectrum and SALEU fuel stay supported; the module rating remains unset because the opened sources give different per-reactor figures. Last checked 19 Oct 2026. Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition); CNSC: IMSR400 Phase 2 pre-licensing vendor design review summary; Terrestrial Energy issuer release, 2025-10-28; America's Nuclear Energy Race Accelerates at Texas A&M-RELLIS
    What would change this

    A Terrestrial Energy NRC submission (for example a construction permit application or topical report for the RELLIS IMSR plant) or a dated ARIS record that fixes the per-core-unit MWth and MWe for the current configuration; the September 2026 catalog section only repeats the June 2025 figures. Next scheduled check: 19 Jan 2027.

  • Module rating: Sources conflict. Opened sources disagree on the per-reactor rating: the catalog gives 442 MWt / 195 MWe per operating core-unit (884/390 for the dual plant), the 2023 CNSC VDR summary calls the IMSR400 a 400-MWth (200-MWe) reactor, and the October 2025 issuer release calls 'our IMSR unit' 390 MWe while also giving 390 MWe for a plant of two IMSRs. The catalog figure is the most explicit per-core-unit statement but differs from the regulator's earlier description. Terrestrial Energy's section of the September 2026 catalog repeats 442 / 195 per operating Core-unit and 884 / 390 for the dual reference configuration. It is the same contributor's figure, not a reconciliation of the CNSC or issuer wording, so the rating stays unset. Last checked 19 Oct 2026. Small Modular Reactor Technology Catalogue, 2024 edition (contributor material; June 2025 third edition); CNSC: IMSR400 Phase 2 pre-licensing vendor design review summary; Terrestrial Energy issuer release, 2025-10-28; Small Modular Reactor Technology Catalogue, 2026 edition (contributor material; printed September 2026)
    What would change this

    An NRC-docketed Terrestrial Energy design description (or a dated ARIS record) stating the current per-core-unit thermal and electrical rating with its basis, which would settle 442/195 versus 400/200. Next scheduled check: 19 Jan 2027.

Regulatory actions

Compare reviews and approvals across designs

Design assessment

  • CNSC vendor design review, Phase 2 (IMSR400) — applies to the design, not to a site
    Design assessment · Review completed (not an approval) · CNSC · completed Apr 2023
    CNSC lists Phase 1 (executive summary dated November 2017) and Phase 2 (executive summary dated April 2023) of its pre-licensing vendor design review of Terrestrial Energy's IMSR400 among completed reviews. CNSC entered into the Phase 2 agreement with Terrestrial Energy on 9 May 2018; that agreement date is not the start of the whole review. The Phase 2 summary found no fundamental barrier to licensing within the reviewed topics and required further design and safety work. CNSC says a vendor design review does not certify a design, issue a license or bind later Commission decisions.
    Sources: CNSC: vendor design review service agreements and completed reviews; CNSC: IMSR400 Phase 2 pre-licensing vendor design review summary