What is an SMR, and how many are operating or being built?

SMR (small modular reactor): A nuclear fission reactor, generally of up to about 300 MWe per unit, whose main parts are designed to be built in a factory; definitions vary, and SMRMap's inclusion rule is on the Methodology page.

222 published projects and proposals, by recorded stage

A stage is not proof of current activity, and these counts are not a census. Counts are records, not reactors; one record can cover several units.

  1. Operating · 6 (2 power-plant projects · 4 research or test reactor projects)

    Reactor operation is documented, including heat-only or experimental operation where specified.

  2. Commissioning · 5 (1 power-plant project · 4 research or test reactor projects)

    Startup, testing or preparation for operation is documented; electricity delivery is not implied.

  3. Construction · 13 (6 power-plant projects · 7 research or test reactor projects)

    Sources report physical construction for the project; a permit alone is insufficient.

  4. Licensing · 19

    A formal project-specific application has been submitted or is under regulator review; design-only and pre-application advice do not qualify.

  5. Siting · 65

    A proposed location is being selected, evaluated or characterized; pre-application regulator engagement alone remains here.

  6. Announced · 96

    A deployment proposal has been made public; later activity is not yet established here.

  7. Suspended · 6

    Project activity has been paused; resumption is not assumed.

  8. Deferred · 2

    The proposal has been postponed; this does not establish cancellation or a new start date.

  9. Canceled · 10

    The proposal or project has been ended; its page preserves the historical evidence.

Power-plant projects operating, commissioning or under construction

Operating

Commissioning

Construction

All 24 operating, commissioning and construction records, with output, construction start and next target, research and test reactors included · How purpose is assigned

What SMRMap counts as an SMR

SMRMap includes deployment projects for designs that are factory-fabricatable or modularly deployable and generally at or below about 300 MWe per module (some multi-module plants exceed that site total), OR that a competent regulator or IAEA ARIS entry classifies as an SMR/microreactor. Low electrical output alone is not sufficient. Microreactors are labeled separately. A design profile does not need a deployment. A specific source-backed agreement or announcement to deploy a named design, or a described plant, can be published with an undisclosed site and no coordinates. Generic national interest, evaluation or feasibility agreements, non-binding letters and unnamed vendor programs stay context. A company plus a state is enough for an undisclosed-site record only when the source commits to a plant there; it is not a pin and not a named host. One plant record, its planned module count and any unit rows are separate. A configuration count is not a count of built reactors. Program-scope rows are aggregates or non-deployment studies and are not verified deployments. Rolls-Royce SMR (~470 MWe) is included with an explicit capacity-check note.