Operating, commissioning and under-construction SMRs

The 24 project records SMRMap lists as operating, commissioning or under construction, with output, construction start, the latest recorded step and the next recorded target.

Operating

6 project records: 2 power-plant projects and 4 research or test reactor projects. Stage page

ProjectPurposeDesignOutputConstruction startLatest recorded stepNext recorded target
Akademik Lomonosov floating NPPRussiaPower plantKLT-40S70 MWe (gross) · plant · 300 MWth (nameplate; basis unspecified)15 Apr 2007Akademik Lomonosov construction start (both units, IAEA PRIS)22 May 2020Akademik Lomonosov commercial operation (both units). Updates entryNo dated target recorded
HTR-PM Shidaowan demonstrationChinaPower plantHTR-PM210 MWe (gross) · plant · 500 MWth (nameplate; basis unspecified)9 Dec 2012HTR-PM construction start (IAEA PRIS)6 Dec 2023HTR-PM commercial operation. Updates entryNo dated target recorded
HTR-10 high-temperature gas-cooled test reactor, Tsinghua INETChinaResearch or test reactorHTR-102 MWe (gross/net unspecified) · plant · 10 MWth (nameplate; basis unspecified)Jun 1995HTR-10 construction begins15 Jul 2014HTR-10 operating license valid through June 2024; operation listed, not confirmed. Updates entryNo dated target recorded
HTTR test reactor with planned hydrogen coupling, OaraiJapanResearch or test reactorHTTR30 MWth (thermal only; nameplate; basis unspecified)1991HTTR construction begins26 Sep 2025JAEA files an amendment to the HTTR hydrogen-coupling application. Updates entry2030 (target)Planned step: HTTR hydrogen production (JAEA target)
TMSR-LF1 thorium molten-salt experimental reactor, WuweiChinaResearch or test reactorTMSR-LF1 experimental molten-salt reactor2 MWth (thermal only; nameplate; basis unspecified)Sep 2018TMSR-LF1 construction begins1 Nov 2025SINAP announces first thorium-to-uranium fuel conversion. Updates entryNo dated target recorded
Valar Atomics Ward 250United StatesResearch or test reactorWard 250MWe not recorded · module · 250 kWth (nameplate; basis unspecified)Not recorded2 Jul 2026Ward 250 reaches 100 kW thermal with electricity generation (DOE update). Updates entryNo dated target recorded

Commissioning

5 project records: 1 power-plant project and 4 research or test reactor projects. Stage page

ProjectPurposeDesignOutputConstruction startLatest recorded stepNext recorded target
Linglong One (ACP100) ChangjiangChinaPower plantACP100 (Linglong One)125 MWe (gross) · module · 385 MWth (nameplate; basis unspecified)13 Jul 2021Linglong-1 construction start (IAEA PRIS)Reported 1 Oct 2026Linglong One reported in hot functional testing. Updates entry2026 (target)Planned grid connection
Aalo-X at Idaho National LaboratoryUnited StatesResearch or test reactorAalo-X10 watts thermal (thermal only; zero-power limit)Not recorded4 Jul 2026Aalo-X zero-power criticality. Updates entry2027 (target)Planned step: Aalo-X full-power test (30 MWth, ~10 MWe) planned
Antares Mark-0 at Idaho National LaboratoryUnited StatesResearch or test reactorAntares Mark-0100 watts thermal (thermal only; zero-power limit)Not recorded4 Jun 2026Antares Mark-0 zero-power criticality. Updates entryNo dated target recorded
Deployable Energy Unity at Idaho National LaboratoryUnited StatesResearch or test reactorUnity0 MWth (thermal only; zero-power limit)Not recorded30 Jun 2026Unity criticality demonstration. Updates entry2026 (target)Planned step: Unity reactor-physics testing incl. passive shutdown and decay-heat tests (planned)
Radiant Kaleidos demonstration at INL DOMEUnited StatesResearch or test reactorKaleidosMWe not recorded · module · 3.5 MWth (nameplate; basis unspecified)Not recordedAnnounced 29 Oct 2026Radiant says DOE approved its Kaleidos safety analysis. Updates entryNo upcoming target recorded. The latest recorded target, Jul–Sep 2026 (target), has passed.

Construction

13 project records: 6 power-plant projects and 7 research or test reactor projects. Stage page

ProjectPurposeDesignOutputConstruction startLatest recorded stepNext recorded target
Baim / Cape Nagloynyn floating PEB-106 (RITM-200S)RussiaPower plantRITM-200S—Aug 2022Keel laid for the first Cape Nagloynyn floating unit's bargePublished 24 Sep 2026Second RITM-200S completed at ZiO-Podolsk for the first PEB-106. Updates entry2027 (target)Planned step: First Baimsky floating unit: reported power-service target (August 2022) (stated 31 Aug 2022)
BREST-OD-300 SeverskRussiaPower plantBREST-OD-300300 MWe (gross) · module · 700 MWth (nameplate; basis unspecified)8 Jun 2021BREST-OD-300 construction start (IAEA PRIS)Reported 7 Oct 2026BREST-OD-300 turbine hall receives separator-superheaters. Updates entry2027 (target)Planned step: Concreting of the BREST-OD-300 reactor vessel to finish (company target)
Darlington BWRX-300 Unit 1CanadaPower plantBWRX-300300 MWe (net) · module · 870 MWth (nameplate; basis unspecified)22 Apr 2026IAEA PRIS records construction start for Darlington SMR1Announced 10 Nov 2026OPG: Darlington Unit 1 no longer expected to meet its October 2030 target or C$7.7 billion estimate. Updates entry2030 (planned)Planned grid connection
Natrium Kemmerer Unit 1United StatesPower plantNatrium345 MWe (gross/net unspecified) · module · 840 MWth (nameplate; basis unspecified)23 Apr 2026TerraPower announces the official start of construction at Kemmerer Unit 1Reported Sep 2026Bechtel steps away from Natrium Kemmerer Unit 1; TerraPower to rebid EPC contract. Updates entry2030 (target)Planned step: TerraPower target: Kemmerer Unit 1 construction completion in 2030
RITM-200N JizzakhUzbekistanPower plantRITM-200N55 MWe (gross/net unspecified) · module4 Jun 2026First concrete poured for the foundation of the first RITM-200N unit (Uzatom)4 Jun 2026First concrete poured for Uzbekistan's first RITM-200N unit. Updates entry2029 (target)First criticality: First criticality of first RITM-200N unit (expected late 2029)
Xuwei nuclear heating and power plant Unit 3 (HTGR)ChinaPower plantDesign profile not linked660 MWe (gross/net unspecified) · plant6 Nov 2026Xuwei Unit 3 (HTGR) first nuclear-island concrete6 Nov 2026Xuwei Unit 3 HTGR pours first nuclear-island concrete. Updates entry2031 (target)Planned step: Xuwei Phase I (all three units) full completion expected
Kairos Hermes 1United StatesResearch or test reactorHermes / KP-FHR35 MWth (thermal only; nameplate; basis unspecified)1 May 2025Hermes nuclear safety-related construction begins1 May 2025Hermes nuclear safety-related construction begins. Updates entry2028 (target)Planned step: Kairos expects to complete Hermes construction in 2028
Kairos Hermes 2United StatesResearch or test reactorHermes / KP-FHR—Not recorded17 Apr 2026Hermes 2 groundbreaking. Updates entry2030 (planned)Planned commercial operation
Last Energy PWR-5 pilot at Texas A&M-RELLISUnited StatesResearch or test reactorLast Energy PWR-55 MWe (gross/net unspecified) · module2026Last Energy states it began PWR-5 construction at RELLISAnnounced 7 Oct 2026Last Energy says DOE approved its PWR-5 final safety analysis. Updates entry2026 (target)First criticality: Last Energy targets a PWR-5 criticality demonstration in 2026
MARVEL microreactor test bed at INL's TREAT facilityUnited StatesResearch or test reactorMARVEL10 kWe (gross/net unspecified) · plant · 85 kWth (nameplate; basis unspecified)Not recordedRelease dated 6 Oct 2026INL reports DOE approval of MARVEL's final documented safety analysis. Updates entry2026 (target)Planned step: MARVEL assembly expected to finish
Natura MSR-1 demonstration at Abilene Christian UniversityUnited StatesResearch or test reactorNatura MSR-1thermal onlyNot recorded18 Sep 2026FLiBe coolant salt arrives at Natura's MSR-1 facility at Abilene Christian University. Updates entryNo dated target recorded
Oklo Aurora-INLUnited StatesResearch or test reactorAurora—2025Oklo-reported Aurora-INL construction start20 Jul 2026Environmental decision recorded: DOE Aurora-INL B5.26 environmental categorical exclusion. Updates entry2028 (target)Commercial operation: Aurora-INL commercial deployment target
Project Pele (INL microreactor demonstration)United StatesResearch or test reactorProject Pele microreactor (BWXT HTGR)1.5 MWe (gross/net unspecified) · moduleNot recordedCompany timeline Sep 2026BWXT says Pele core barrel cartridge installation is complete. Updates entry2027 (target)Planned step: Formal Pele system testing (BWXT plan, as early as)

All stages · All upcoming targets · Downloads

Cite or share this page

SMRMap. “Operating, commissioning and under-construction SMRs”. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/operating-and-construction.html (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.