SMR developments: November 2026
12 recorded developments dated November 2026: 3 permission or environmental decisions, 4 project developments, 2 announcements, 3 policy steps. November 2026 is not over; entries dated later this month appear when they are recorded.
On SMRMap in November 2026: 1 new project record, 55 new Updates entries and 3 stage changes, across 9 release days. What was added or changed on SMRMap
Developments are placed by their recorded date, not by when SMRMap added them; what SMRMap added or changed is listed by release day further down. Entries dated only to a quarter or year are not assigned to a month. Each entry is dated when the development happened unless its label says otherwise, such as “Announced” or “Report dated”. A date recorded only to a month, quarter or year is shown that way. Targets are plans, not achievements or commitments.
Recorded developments
Newest first. An entry dated only to the month follows that month's dated entries.
Announced · Recorded development
OPG: Darlington Unit 1 no longer expected to meet its October 2030 target or C$7.7 billion estimate #
OPG said on 10 November 2026 that the first Darlington BWRX-300 is no longer expected to meet its previously disclosed October 2030 commercial-operation target or C$7.7 billion estimate; its assessment should be substantially complete by mid-2027. Read as republished by Cantech Letter; OPG's own copy and Q3 MD&A not opened. No new date or cost given. Company outlook, not a CNSC decision; does not itself replace the end-2030 grid target.
Checking notes
In its third-quarter 2026 results release of 10 November 2026, OPG said that, while it undertakes a comprehensive assessment of the project's cost and schedule, Darlington New Nuclear Project Unit 1 is no longer expected to achieve the previously disclosed commercial operation date target of October 2030 or be completed within the previously disclosed estimated cost of C$7.7 billion, inclusive of required systems and services that would be common to all planned SMRs. OPG said this reflects GE Vernova Hitachi Nuclear Energy's ongoing engineering for its first-of-a-kind SMR, which OPG says affects construction execution and supply-chain performance, and that the assessment is currently expected to be substantially completed by mid-2027. The release gives no replacement date or cost. OPG's 2025 annual MD&A (12 March 2026) gave grid connection by the end of 2030 and a C$7.7 billion budget, and its first-quarter 2026 MD&A (5 May 2026) listed a 2030 in-service date for Unit 1 against the same approved budget. The release does not mention grid connection; October 2030 is a commercial-operation date, not the end-2030 grid-connection target recorded from OPG's earlier statements.
· Comment period closed
Comments close on NRC licensing, decommissioning and oversight proposal #
Comments closed on 9 November 2026 on the proposal published on 24 September 2026. The proposed changes are not in effect.
Checking notes
NRC published a separate proposal on 24 September 2026 for reactor licensing, decommissioning and operational oversight; comments closed on 9 November. The proposed changes are not in effect. No reactor application, construction permission or operating authority follows from this proposal.
· Regulatory step
NRC issues the Long Mott construction permit #
The NRC says it has issued the construction permit for the four-reactor Long Mott Generating Station in Texas. The permit authorizes construction, not operation. No construction start is recorded.
Checking notes
NRC news release 26-083 of 9 November 2026 says the NRC has issued the construction permit for the Long Mott Generating Station. This event is the same decision as the regulatory action, not a separate announcement. The permit authorizes construction but not operation. It is not a construction start. The permit is CPAR-3 (ADAMS ML26301A133); the Federal Register notice of issuance is 91 FR 72925, 12 November 2026.
· Construction permission recorded
Construction permit issued for the Long Mott Xe-100 station #
The NRC says it has issued a construction permit for Long Mott Energy's four-reactor Xe-100 station at Dow's Seadrift site in Texas. It authorizes construction but not operation. No construction start is recorded; a permit is not a physical construction start.
NRC news release and Construction Permit No. CPAR-3: 9 November 2026. Federal Register notice: 12 November 2026 (91 FR 72925). Application dated 31 March 2025.
Checking notes
Long Mott Energy's construction permit application, dated 31 March 2025, was accepted and docketed by the NRC. NRC news release 26-083 of 9 November 2026 states that the NRC has issued the construction permit for the four-reactor Xe-100 Long Mott Generating Station in Calhoun County, Texas, that staff completed the safety evaluation in October, and that the permit authorizes building the facility but not operation; a separate operating license is required before fuel loading. The release gives no permit number; the permit itself is Construction Permit No. CPAR-3 (ADAMS ML26301A133), issued 9 November 2026, and the Federal Register notice of issuance (91 FR 72925, 12 November 2026) says it is immediately effective and authorizes construction of a power reactor facility in Calhoun County, Texas. The permit sets the earliest construction completion date as 1 July 2033 and the latest as 31 December 2033 and expires on that date. Its conditions include that Long Mott Energy notify the NRC when the site grading design and the passive engineered flooding protection design that may impact site grading are available for NRC staff examination, and that it perform geologic mapping of each foundation excavation for safety-related structures, evaluate it against the site characterization and notify the NRC when it is available for examination; the permit also incorporates an environmental protection plan. It says a license authorizing operation will not be issued unless the applicant submits the complete final safety analysis report, the Commission makes the stated findings on final design and environmental requirements, and the applicant submits proof of financial protection and executes an indemnity agreement. The NRC's project page, updated 12 November 2026, lists the hearing as held on 22 September 2026 and the construction permit decision as 8 November 2026; the permit and the Federal Register notice date issuance to 9 November 2026, and the one-day difference is unexplained in the sources read. Earlier steps: the uncontested (mandatory) hearing was held on 22 September 2026 in Port Lavaca; the Advisory Committee on Reactor Safeguards reported on 16 October 2026 that its review supports issuance; NRC issued an environmental assessment and finding of no significant impact plus related exemptions on 18 May 2026. In the contested proceeding, both admitted contentions were dismissed as moot in 2026 and on 7 August 2026 the Commission dismissed the applicant's appeal as moot; on 6 November 2026 the Commission denied the intervenor's separate petition for review (CLI-26-15). The permit is not an operating license. No construction start is recorded; a permit is not a physical construction start.
· First concrete
Xuwei Unit 3 HTGR pours first nuclear-island concrete #
Construction of the Unit 3 high-temperature gas-cooled reactor formally started on 6 November 2026 with the first nuclear-island concrete. Reported by the technology developer and the owner's parent company; no regulator or IAEA PRIS record of the pour has been read.
Checking notes
Tsinghua University reported on 10 November 2026 that Xuwei Phase I Unit 3 formally started construction on 6 November with the first nuclear-island concrete poured. China National Nuclear Power's announcement 2026-066, dated 6 November, gave that day as the planned pour date. This follows NNSA construction license 国核安证字第2621号 of 2 November.
· Recorded development
Long Mott: Commission denies the intervenor's petition for review #
The Commission denied Waterkeeper's petition for review on 6 November 2026, closing the contested proceeding on the Long Mott construction permit application. An adjudicatory order, not the permit. Whether any court challenge has been filed was not searched.
Checking notes
On 6 November 2026 the Commission denied San Antonio Bay Estuarine Waterkeeper's petition for review of the Licensing Board's rulings, which had rejected or dismissed all of its contentions; the Board had already terminated the proceeding. The order also records that the NRC held its uncontested (mandatory) hearing on 22 September 2026 in Port Lavaca, Texas. An adjudicatory order, not the permit; the construction permit followed on 9 November 2026.
· Comment period closed
Comments close on NRC draft non-light-water reactor materials guidance #
The comment period on draft DANU-ISG-2023-01, Revision 1, closed on 5 November 2026. The draft is not adopted guidance.
Checking notes
NRC published a request for comment on 21 September 2026 on draft DANU-ISG-2023-01, Revision 1, covering material compatibility for non-light-water reactors. This record establishes the consultation notice, not the contents or adoption of the underlying guidance.
Announced · Announcement
X-energy selects Fluor for Cascade nuclear-island engineering #
X-energy said Fluor will provide design and engineering services for the plant areas containing the Xe-100 reactors. An engineering and design contract between X-energy and Fluor, not a construction contract or an NRC application.
Checking notes
X-energy announced on 5 November 2026 that it selected Fluor for engineering, design development, supply chain, estimating and project controls services for the nuclear island of the Cascade facility. The release gives no contract date or value. This is not a construction contract.
Announced · Announcement
X-energy announces first steam-generator tubing order #
X-energy said Alleima and Doosan Enerbility will supply steam-generator tubing and coils for the first Xe-100 deployment. A long-lead component order. It is not a construction start or a final investment decision.
Checking notes
X-energy, Alleima and Doosan Enerbility announced on 4 November 2026 the first procurement of steam-generator tubing for the Xe-100, for its first deployment, the proposed four-unit plant with Dow in Texas. Alleima is to make the tubing and Doosan is to bend it into helical coils. No quantity or value is stated.
Published · Published
NRC publishes new pathways for contested licensing hearings #
The final rule sets Standard, Focused and Expedited pathways for contested adjudications in NRC licensing proceedings. Effective 3 December 2026 for proceedings noticed on or after that date; it decides no project application.
Checking notes
NRC published a final rule on 3 November 2026 to streamline contested adjudications in its licensing proceedings, in response to the ADVANCE Act and Executive Order 14300. It sets Standard, Focused and Expedited hearing pathways, which the Commission says are not rigid designations. It takes effect on 3 December 2026 for contested proceedings noticed on or after that date. It is separate from the mandatory (uncontested) hearing rule of April 2026.
· Construction permission recorded
Construction license issued for Xuwei Unit 3 #
NNSA issued construction license No. 2621 to CNNC Sueneng on 2 November 2026, valid to 1 November 2036, and said the company may begin pouring first concrete for the nuclear-island foundation. No construction start is recorded; a permit is not a physical construction start. It is not an operating license.
Checking notes
China's nuclear regulator reported on 26 June 2025 that it had started the construction-license review for Unit 3 of the Xuwei nuclear heating and power plant, covering the preliminary safety analysis report and the construction-stage environmental impact report, with CNNC Sueneng Nuclear Power presenting the high-temperature gas-cooled reactor. That notice gives no filing day and no license decision. The 9 October 2026 pre-construction inspection report found that preparations met the conditions for issuing a construction license and set seven corrective requirements; it does not itself issue the license. NNSA's notice 国核安发〔2026〕208号 of 2 November 2026 issues construction license 国核安证字第2621号 for Unit 3 to CNNC Sueneng, valid to 1 November 2036, and says the company may begin pouring the first concrete for the nuclear-island foundation. The license requires an operating-license application before first fuel loading. It is not an operating license. No construction start is recorded; a permit is not a physical construction start.
· Site permission recorded
NNSA issues site-selection opinion for Huakun One #
NNSA's site-selection opinion No. 2620 of 2 November 2026 found no disqualifying site factor that engineering measures could not resolve, and agrees design work may proceed on the site parameters. It is not a construction license. Until it holds one, the company may not pour seismic Category I foundation concrete or build other safety-important structures.
Checking notes
The National Nuclear Safety Administration issued its site-selection review opinion (国核安证字第2620号) on 2 November 2026 to CGN Ocean Energy for the Huakun One floating reactor platform and maintenance base at the Taipingling nuclear base in Huidong county. The review found no disqualifying site factor affecting safety that engineering measures could not resolve, and the opinion agrees that design work may proceed on the stated site parameters. It is not a construction license: before holding one the company may not pour seismic Category I foundation concrete or build other safety-important structures.
Targets dated November 2026
Planned, target and estimated dates are not achievements or commitments. A passed target period alone does not mean the step failed or was canceled.
Target · Milestone
Milestone: Executive Order 14300: reform of the Nuclear Regulatory Commission #
Section 5: final rules and guidance to conclude the NRC's revision within 18 months of the order, signed 23 May 2025. The order gives the period, not a calendar date; November 2026 is the month it ends. A target, not a result.
Target · Planned step · Met on
NRC target for the Long Mott final safety evaluation #
NRC schedule target for issuing its final safety evaluation of the construction-permit application. NRC news release 26-083 of 9 November 2026 says staff completed the safety evaluation in October, one month ahead of schedule, and the permit has been issued. The NRC's project page, re-read on 10 November, still showed the November target. The evaluation was completed; the target date itself is kept as the schedule that was stated.
Planned · Provision effective date recorded
Provision effective date recorded: South Korea: Nuclear Safety Act (원자력안전법) #
The government's legislative entry for the enforcement rule gives 20 November as the start date for the pre-review amendment; the Commission's May press release said November.
New and changed on SMRMap in November 2026
Grouped by release day: the day a change first appeared in a public SMRMap build (UTC). A release day is not the date of the development. Re-checks that change only review dates, owners or next triggers are not counted. Changes only to evidence references are listed separately and are not counted as a record change. A renamed record appears as removed and new. Publication history (JSON)
15 November 2026
- Updated: 2 project records. Projects: Energoatom SMR at the Trypilska thermal plant site (Announced, Ukraine) · Stellarium reactors for the Fos-sur-Mer integrated energy hub (2026 MoU) (Announced, France).
- Evidence references updated: 6 project records. No published fact changed.
14 November 2026
- Updated: 1 project record, 2 regulatory records. Projects: Oklo Aurora campus, Pike County, Ohio (Siting, United States).
13 November 2026
- New dated developments on Updates (2): OPG: Darlington Unit 1 no longer expected to meet its October 2030 target or C$7.7 billion estimate (10 Nov 2026) · Long Mott: Commission denies the intervenor's petition for review (6 Nov 2026)
- Updated: 11 project records, 2 companies and organizations, 2 regulatory records, 3 dated developments and targets.
11 November 2026
- New project records (1): Calogena NetZeroHeat CAL30 heat reactor for Pierrelatte (Announced, France)
- New agreements and programs (7): Dairyland Power and Applied Atomics letter of intent to evaluate SMRs at the Genoa site (Wisconsin) · National Tsing Hua University and NuCube Energy assessment of a microreactor on the NTHU campus · Ocean-Power and Copenhagen Atomics MoU to study thorium molten-salt reactors in Norway · Steady Energy and Korea District Heating Corp. cooperation on heat-only SMRs · SÚJB and SSM memorandum on regulatory cooperation for the Rolls-Royce SMR · Thorizon-led Project Pronto under the Dutch MOOI Kernenergie scheme · USTDA-funded SMR assessment and roadmap for TÜPRAŞ refining operations
- New policy records (1): Estonia: Nuclear Energy and Nuclear Safety Act (Tuumaenergia ja -ohutuse seadus)
New dated developments on Updates (20)
- Comments close on NRC licensing, decommissioning and oversight proposal (9 Nov 2026)
- Comments close on NRC draft non-light-water reactor materials guidance (5 Nov 2026)
- X-energy selects Fluor for Cascade nuclear-island engineering (5 Nov 2026)
- X-energy announces first steam-generator tubing order (4 Nov 2026)
- USTDA-funded SMR assessment and roadmap for TÜPRAŞ refining operations (26 Oct 2026)
- Elementl announces proposed partnership of up to $750 million (26 Oct 2026)
- Dairyland Power and Applied Atomics letter of intent to evaluate SMRs at the Genoa site (Wisconsin) (22 Oct 2026)
- National Tsing Hua University and NuCube Energy assessment of a microreactor on the NTHU campus (19 Oct 2026)
- SÚJB and SSM memorandum on regulatory cooperation for the Rolls-Royce SMR (14 Oct 2026)
- Comments close on NRC draft training-review guidance (21 Sep 2026)
- Nuclearelectrica publishes the government Control Body's report on the Doicești SMR (11 Sep 2026)
- Published: Estonia: Nuclear Energy and Nuclear Safety Act (Tuumaenergia ja -ohutuse seadus) (11 Jul 2026)
- Thorizon-led Project Pronto under the Dutch MOOI Kernenergie scheme (2 Jul 2026)
- Awarded: Netherlands: MOOI subsidy module, nuclear energy innovation theme (Missiegedreven Onderzoek, Ontwikkeling en Innovatie) (2 Jul 2026)
- Signed: Estonia: Nuclear Energy and Nuclear Safety Act (Tuumaenergia ja -ohutuse seadus) (2 Jul 2026)
- Estonia adopts a Nuclear Energy and Nuclear Safety Act, to take effect on 1 January 2027 (17 Jun 2026)
- GBE-N and Anglesey council sign a Collaboration Agreement for Wylfa (25 Mar 2026)
- Steady Energy and Korea District Heating Corp. cooperation on heat-only SMRs (5 Dec 2025)
- Ocean-Power and Copenhagen Atomics MoU to study thorium molten-salt reactors in Norway (23 Jul 2025)
- NuScale says FEED Phase 2 work for RoPower finished in late 2025 (2025)
- Stage changes (1): Last Energy first commercial PWR-20 site, Caldwell County: Siting → Licensing
- Updated: 13 project records, 1 design profile, 6 companies and organizations, 1 agreement or program, 6 policy records, 3 dated developments and targets.
10 November 2026
- New policy records (1): NRC final rule: Streamlining Contested Adjudications in Licensing Proceedings
- New dated developments on Updates (6): NRC issues the Long Mott construction permit (9 Nov 2026) · Construction permit issued for the Long Mott Xe-100 station (9 Nov 2026) · Xuwei Unit 3 HTGR pours first nuclear-island concrete (6 Nov 2026) · NRC publishes new pathways for contested licensing hearings (3 Nov 2026) · Last Energy files for a limited work authorization at its Caldwell site (20 Oct 2026) · NRC completes the Long Mott safety evaluation in October (Oct 2026)
- Stage changes (2): Dimitrovgrad SVBR-100 pilot proposal (2013 land lease): Announced → Canceled · Xuwei nuclear heating and power plant Unit 3 (HTGR): Licensing → Construction
- Updated: 6 project records, 2 design profiles, 1 company or organization, 1 regulatory record, 4 dated developments and targets. Projects: Copenhagen Atomics critical experiment at the Paul Scherrer Institute (Siting, Switzerland) · Dimitrovgrad SVBR-100 pilot proposal (2013 land lease) (Canceled, Russia) · Fermi Energia Estonian BWRX-300 plant (Siting, Estonia) · Last Energy first commercial PWR-20 site, Caldwell County (Licensing, United States) · Long Mott Generating Station (Xe-100 at Dow Seadrift) (Licensing, United States) · Xuwei nuclear heating and power plant Unit 3 (HTGR) (Construction, China).
4 November 2026
- New dated developments on Updates (6): Construction license issued for Xuwei Unit 3 (2 Nov 2026) · NNSA issues site-selection opinion for Huakun One (2 Nov 2026) · Radiant says DOE approved its Kaleidos safety analysis (29 Oct 2026) · ARC announces a memorandum with Hyundai Engineering on ARC-100 deployment (29 Oct 2026) · NANO Nuclear announces a memorandum with Hyundai Engineering on KRONOS (27 Oct 2026) · ANSN meets IEN and Terminus on licensing the critical unit (21 Jan 2026)
- New targets on Updates (2): Target: interim report on RoPower Nuclear's measures (31 Dec 2026) · Milestone: Executive Order 14300: reform of the Nuclear Regulatory Commission (Nov 2026)
- Updated: 19 project records, 68 design profiles, 86 companies and organizations, 9 policy records, 4 regulatory records, 4 dated developments and targets.
3 November 2026
- New agreements and programs (1): Indiana Advanced Nuclear Ready Communities program
- New policy records (1): Indiana tax guidance on the SMR manufacturing expense credit
- New dated developments on Updates (1): Published: Indiana tax guidance on the SMR manufacturing expense credit (Jun 2025)
- New targets on Updates (3): Fermi Energia application: first reactor could start operating in 2035 at the earliest (2035) · Kairos target: Hermes 2 to begin operations in 2030 (2030) · Reported target: Linglong One fuel loading and grid connection within 2026 (2026)
- Updated: 11 project records, 37 design profiles, 1 agreement or program, 9 regulatory records, 5 dated developments and targets.
2 November 2026
- New policy records (6): Army adoption of DOE advanced-reactor categorical exclusion · MARAD consultation: a marine SMR concept · NRC consultation: draft non-light-water reactor materials guidance · NRC consultation: draft training-review guidance · NRC proposal: modernizing materials licensing · NRC proposal: package certification and microreactor transport
- New dated developments on Updates (7): NRC seeks comments on draft reactor materials guidance (21 Sep 2026) · Army publishes adoption of DOE advanced-reactor categorical exclusion (1 Sep 2026) · Army can use the adopted advanced-reactor categorical exclusion (1 Sep 2026) · NRC proposes package-certification changes for microreactor transport (27 Jul 2026) · NRC seeks comments on draft training-review guidance (22 Jul 2026) · NRC proposes materials-licensing changes for advanced reactor fuels (24 Jun 2026) · MARAD seeks information about a marine SMR concept (7 May 2026)
1 November 2026
- New dated developments on Updates (7): Long Mott: X-energy says the NRC has completed its final safety evaluation (30 Oct 2026) · Long Mott: NRC's safety advisory committee supports issuing the construction permit (16 Oct 2026) · Holtec submits its design to the UK government for Generic Design Assessment (Jan 2023) · ACU applies for its molten salt research reactor construction permit (12 Aug 2022) · NuScale requests a standard design approval for the US600 (13 Jul 2020) · KAERI and KEPCO apply for a standard design approval of SMART (30 Dec 2010) · OPG applies for the original Darlington site preparation license (Sep 2006)
- Updated: 42 project records, 27 design profiles, 13 regulatory records, 2 dated developments and targets.
Follow new entries for every project with the site-wide RSS feed, or filter every entry on Updates.