Documented SMR schedule changes

Where a source documents that a project milestone’s target moved, the earlier and revised targets are shown side by side.

7 documented revisions across 4 projects: 5 moved earlier, 2 moved later, 0 unchanged and 0 not compared.

Darlington BWRX-300 Unit 1

Canada · Construction

Duke Belews Creek technology-neutral SMR proposal

United States · Licensing

Stellaria Alvin experimental reactor (INB Alpha) at Cadarache

France · Licensing

TVA Clinch River BWRX-300

United States · Licensing

Download these revisions (CSV) · All upcoming targets · Monthly digests · RSS feed (all updates)

Historical schedule reviews

16 projects have source-backed schedule accounts. These include partial histories and qualifications that do not fit the paired-date table above. A review may also cover a project already listed above; the counts are not additive.

Open a project to read its account, sources and limits. These reviews do not establish a complete history, a current target or a comparable delay.

Cite or share this page

SMRMap. “Documented SMR schedule changes”. Data fingerprint 434a3ad4fbbaaa6e4b79ee0db9d79c7b9b85f663d24417697f7e09f26d609d55; build 2026-11-17. https://smrmap.com/schedule-changes.html (accessed [date]). Data license CC BY 4.0.

“Record reviewed” is the record review date. The evidence review, individual sources and later additions keep their own dates. The fingerprint identifies the underlying data collections, not an archived page or a download checksum. Build date is not a source review date. Include your access date; save a PDF if you need a copy of the page you read.